Information Notice 2016-07, Operating Experience Regarding Impacts on Site Electrical Power Distribution from Inadequate Oversight of Contractor Activities

From kanterella
Revision as of 23:31, 30 October 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Operating Experience Regarding Impacts on Site Electrical Power Distribution from Inadequate Oversight of Contractor Activities
ML16057A842
Person / Time
Issue date: 06/20/2016
From: Michael Cheok, Louise Lund
Division of Construction Inspection and Operational Programs, Generic Communications Projects Branch
To:
Schwab A
References
IN-16-007
Download: ML16057A842 (6)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

OFFICE OF NEW REACTORS

WASHINGTON, DC 20555-0001 June 20, 2016 NRC INFORMATION NOTICE 2016-07: OPERATING EXPERIENCE REGARDING

IMPACTS ON SITE ELECTRICAL POWER

DISTRIBUTION FROM INADEQUATE

OVERSIGHT OF CONTRACTOR ACTIVITIES

ADDRESSEES

All holders of an operating license or construction permit for a nuclear power reactor under

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of

Production and Utilization Facilities, except those that have permanently ceased operations

and have certified that fuel has been permanently removed from the reactor vessel.

All holders of and applicants for a power reactor combined license under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to inform

addressees of adverse effects to off-site power availability that have resulted from inadequate

licensee oversight of contractor activities. It is expected that recipients will review the

information for applicability to their facilities and consider actions, as appropriate, to avoid

similar problems. However, suggestions contained in this IN are not NRC requirements;

therefore, no specific action or written response is required.

DESCRIPTION OF CIRCUMSTANCES

Wolf Creek Generating Station, Unit 1

On January 13, 2012, Wolf Creek Generating Station (Wolf Creek) experienced an automatic reactor trip after the catastrophic failure of the main generator output breaker. The start-up

transformer assumed nonsafety-related loads, but subsequently experienced a differential relay

actuation on its B phase. This caused a lockout of the start-up transformer and a loss of

off-site power (LOOP). Both emergency diesel generators started and supplied power to the

safety-related 4160 volt busses as expected.

The LOOP resulted in several complications, including:

  • erratic source range nuclear instrumentation indications resulting from the loss of power

to containment cavity cooling fans

ML16057A842 * containment sump high level alarms caused by a through-wall leak in essential service

water (ESW) piping in containment resulting from a known issue with water hammer

caused by the stop-start sequence of ESW pumps following a LOOP

  • a loss of firefighting capability for 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> because of the loss of power to normal fire

pumps in conjunction with the long-term inoperability of the installed diesel-powered fire

pump and inadequacies with the procedure for starting a temporary fire pump

  • a loss of reactor coolant pumps necessitating a natural circulation cooldown, and
  • a loss of instrument air complicating operator control of pressurizer level and pressure

The cause of the LOOP was the actuation of protective relaying resulting from a short between

two taps on the high side current transformers. During the previous year, the licensee had

contracted with a vendor to replace electrical seal assemblies in the start-up transformer that

experienced oil leakage. This vendor performed the majority of the work in accordance with

established instructions and practices, but failed to install insulating sleeves on 2 of the 37 wiring connections. These sleeves are required to prevent terminal-to-terminal contact. The

investigation that followed determined that the licensee failed to satisfy the requirements of

written procedures to ensure that (1) field activities were adequately monitored, and (2) periodic

verification of contracted work was conducted to verify that it was performed in accordance with

applicable work orders. After the event, the licensee installed the missing insulation sleeves, and updated station procedures regarding the oversight of contractors performing work on

risk-significant components.

This IN provides no new information on this event. The condition described was summarized

from previously-released reports prepared by an NRC Augmented Inspection Team (AIT)

chartered shortly after the event in 2012 to review the facts surrounding the LOOP, and the

complications that resulted. Additional information can be found in Licensee Event Report

05000482/2012-001, Failure of 345 kV Switchyard Breaker due to Internal Fault Resulting in

Reactor Trip and Coincident Loss of Offsite Power, dated April 9, 2012, in Wolf Creek Nuclear

Operating Corporation-NRC Augmented Inspection Team Report 05000482/2012008, dated

April 4, 2012, and in the NRC Augmented Inspection Team Follow-Up Report

05000482/2012009, dated August 6, 2012 (Agencywide Documents Access and Management

System (ADAMS) Accession Nos. ML12109A049, ML12095A414, and ML12227A919, respectively).

Arkansas Nuclear One, Unit 1 and Unit 2

On March 31, 2013, at Arkansas Nuclear One (ANO) during its Unit 1 outage, an inadequately

designed temporary lifting rig failed while moving the Unit 1 main generator stator out of the

turbine building. The 525-ton stator fell onto the turbine deck and then continued falling

approximately 30 feet into a train bay that is shared between Units 1 and 2. The collapse of the

lifting rig resulted in one fatality and injured eight others. The impact of the dropped stator on

the turbine deck damaged the Unit 1 non-vital electrical switchgear connecting plant vital busses

to off-site power, causing a LOOP to Unit 1 for six days.

At the time of the event, Unit 2 was operating at 100 percent power. Vibrations from the stator

drop and temporary lift rig collapse caused a Unit 2 reactor coolant pump breaker to trip, resulting in an automatic reactor trip of Unit 2. Water spray from a ruptured fire water pipe migrated into the ANO-2 non-vital switchgear area located just off the train bay causing an

electrical fault inside the non-vital Unit 2 electrical switchgear approximately 90 minutes after the

stator drop. This fault caused a lockout of start-up transformer 3 and a partial LOOP for Unit 2.

Loss of power to all four reactor coolant pumps necessitated a natural circulation plant

cooldown, which was complicated by additional equipment unavailability due to the partial

LOOP.

The temporary lifting rig collapse resulted from errors in contractor design calculations. The

basic lifting rig design had been used by the contractor for stator lifts at other nuclear power

plants; however, the design of the rig had been modified for use at ANO. The licensee failed to

perform an adequate review of the contractors modified design calculations, and failed to

require the contractor to perform a load test in accordance with site procedures and applicable

regulations. These failures were the result of inadequate oversight by the licensee. The

licensee repaired the damage to the plant and updated procedures to provide guidance on

review of calculations, quality requirements, and standards associated with third party reviews.

The NRC chartered and dispatched an AIT to review the facts of the event. Additional

information can be found in Licensee Event Report 05000313/2013-001, Collapse of a Main

Generator Stator Temporary Lift Assembly Results in a Fatality, Multiple Injuries, a Plant Scram, a Notification of Unusual Event, and Dual Unit Structural Damage, dated August 22, 2013 (ADAMS Accession No. ML12109A049).

Comanche Peak Nuclear Power Plant, Unit 1 and Unit 2

On December 4, 2013, Comanche Peak Nuclear Power Plant (Comanche Peak) experienced a

LOOP to safety-related busses when an energized cable feeding the in-service start-up

transformer was mistakenly cut while the other start-up transformer was out of service for

modifications. Both units remained at full power as nonsafety-related loads (including reactor

coolant pumps) continued to receive power from the main generator through the unit auxiliary

transformer. All four emergency diesel generators started automatically and re-energized the

safety-related busses.

Comanche Peak was in the process of implementing a modification to start-up transformer

XST-1. In preparation for the work, contract personnel had walked down the cables for XST-1 to ensure the correct cables were identified. However, an incorrect assumption about the layout

of the cable bus enclosure routing, combined with a failure to use design drawings to facilitate

the walkdown, contributed to the contractors misidentifying a feeder cable for the other start-up

transformer, XST-2, rather than the cable for XST-1. The licensee did not validate the resulting

work plan provided by the contractors. The contract electricians performing the work raised

questions about the accuracy of the cable identification, but failed to pursue the issue, contrary

to station procedures. The licensee repaired the cut cable to restore off-site power, and

improved procedures regarding the design change development, review, and oversight

processes.

Additional information can be found in Licensee Event Report 05000445/2013-003, Auto Start

of Both Units' Auxiliary Feedwater Pumps and Emergency Diesel Generators Due to a Loss of

Both Units' Safeguards Electrical Power, dated January 30, 2014 and in Comanche Peak Nuclear Power Plant-NRC Integrated Inspection Report 05000445/2014003 and Notice of

Violation, dated August 6, 2014 (ADAMS Accession Nos. ML14043A089 and ML14218A072, respectively).

Joseph M. Farley Nuclear Plant, Unit 2

On October 14, 2014, a lightning strike on a 500kV line caused a partial LOOP to Joseph M.

Farley Nuclear Plant (Farley), Unit 2. A power circuit breaker opened to clear the fault, and

experienced an internal fault on the bus side of the main contacts. The high-fault current

exposed a loose connection, creating a high resistance and differential current signal that led to

isolation of the 2B start-up auxiliary transformer (SAT), and a LOOP to its associated B train

power bus. The 2B emergency diesel generator was out of service at the time for scheduled

maintenance, and was unable to assume the B train safety-related loads. One of these loads

was the B train of component cooling water, which was supplying cooling water to reactor

coolant pump oil coolers and seal coolers at the time of the event. In accordance with the

abnormal operating procedure for loss of component cooling water, operators inserted a manual

reactor trip.

The loose connection that caused the isolation of the 2B SAT resulted from improper wiring that

was introduced during installation of a power circuit breaker 18 months earlier. The breaker

installation was part of a design change package for the high-voltage switchyard implemented

by the grid operator to replace and upgrade several power circuit breakers and their control

relay packages. Testing during the implementation verified the correct installation of the current

transformers and associated wiring. However, inadequate verification practices failed to identify

a missing nut on one of the terminals during the installation. This led to a loose connection that

was adequate for normal testing and operational purposes, but not for the conditions

experienced during a ground fault isolation. A contributing cause of this event was the

licensees failure to fully understand the extent of differences in verification practices performed

by an outside organization.

The missing nut on the power circuit breaker current transformer was installed, and the

transformer primary and secondary protective relaying functions were tested satisfactorily. In

addition, the licensee worked to strengthen the application of verification procedures used by

the utility performing the switchyard maintenance.

Additional information can be found in Licensee Event Report 05000364/2014-002, Manual Reactor Trip due to Loss of 2B [Start-up] Auxiliary Transformer and Loss of Offsite Power, dated December 12, 2014 (ADAMS Accession No. ML14346A391).

DISCUSSION

Licensees often rely on contractors and supplemental personnel to perform work. This is

especially the case during scheduled outages. This work includes specialized, low-frequency

tasks involving one-time modifications or the overhaul of major equipment. The NRC has

previously issued several other INs regarding contractor oversight issues, such as IN 97-74, Inadequate Oversight of Contractors During Sealant Injection Activities, and IN 00-11, Licensee Responsibility for Quality Assurance Oversight of Contractor Activities Regarding

Fabrication and Use of Spent Fuel Storage Cask Systems.

Although the performance of particular tasks, including the development and execution of work

instructions and procedures, may be delegated to outside organizations, the licensee retains overall responsibility for ensuring that the procedures and their execution meet the quality

assurance expectations of plant process controls and, for safety-related equipment, the

requirements of the plants NRC-approved quality assurance program. While the work activities

discussed in this IN were associated with non-safety related equipment, each event placed the

plant in a LOOP condition and challenged the operability and reliability of safety-related

equipment.

Industry operating experience has shown the importance of licensee programs designed to

ensure effective station oversight of contractor activities. Establishing clear lines of

accountability within the licensee organization that maintains sufficient knowledge and technical

expertise to exercise an appropriate level of oversight of the design, maintenance, modification, or refurbishment activities performed by contracted personnel is essential. This includes

verification that procedures and work instructions contain sufficient detail, and that supplemental

personnel are familiar with site work control processes and expectations for procedure

adherence.

CONTACT

This IN requires no specific action or written response. Please direct any questions about this

matter to the technical contacts listed below, or the appropriate Office of Nuclear Reactor

Regulation (NRR) project manager.

/ra/ /ra/

Michael C. Cheok, Director Louise Lund, Director

Division of Construction Inspection Division of Policy and Rulemaking

and Operational Programs Office of Nuclear Reactor Regulation

Office of New Reactors

Technical Contacts: Rebecca Sigmon, NRR Jesse Robles, NRR

301-415-0895 301-415-2940

E-mail: Rebecca.Sigmon@nrc.gov E-mail: Jesse.Robles@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under NRC Library.

ML16057A842 *via email TAC: MF7293 OFFICE TECH EDITOR NRR/DIRS/IOEB/TL NRR/DIRS/IOEB/TL NRR/DE/EEEB/BC NRR/DIRS/IOEB/BC

NAME JDougherty* RSigmon* JRobles* JZimmerman* HChernoff*

DATE 03/11/2016 05/16/2016 05/18/2016 05/25/2016 05/18/2016 OFFICE NRR/DIRS/D NRR/DPR/PGCB/PM NRR/DPR/PGCB/LA NRR/DPR/PGCB/BC NRO/DCIP/D

NAME SMorris* ASchwab* ELee* SStuchell* MCheok

DATE 05/27/2016 05/27/2016 05/31/2016 05/31/2016 06/20/2016 OFFICE NRR/DPR/D

NAME LLund

DATE 06/20/2016