Finding | |
---|---|
Title | Failure to Recalculate Suppression Pool Peak Temperature Response (1R21.b.2) |
Description | Green. The team identified a finding of very low safety significance involving a noncited violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, in that, design control measures for verifying the adequacy of design were not implemented. Specifically, the licensee did not recalculate suppression pool peak temperature response when a more severe single failure condition was identified. In response, the licensee entered this issue in the corrective action program as Condition Report CR-RBS-2008-03661 and determined that suppression pool peak temperature response was acceptable. The finding was more than minor because it was associated with the design control attribute of the Mitigating Systems Cornerstone and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Traditional enforcement does not apply because the issue did not have any actual safety consequences or potential for impacting the NRCs regulatory function, and was not the result of any willful violation of NRC requirements. In accordance with Inspection Manual Chapter 0609, Attachment 4, Phase 1 Initial Screening and Characterization of Findings, a Phase 1 screening was performed and determined the finding was of very low safety significance (Green) because it was a design or qualification deficiency confirmed not to result in a loss of operability or functionality of the suppression pool. The finding had a cross-cutting aspect in the area of problem identification and resolution because the licensee initiated a corrective action program action to re-evaluate long-term suppression pool peak temperature performance but closed the action without its completion. (P.1 (d)) (Section 1R21.b.2 |
Site: | River Bend |
---|---|
Report | IR 05000458/2008006 Section 1R21 |
Date counted | Sep 30, 2008 (2008Q3) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.21 |
Inspectors (proximate) | B Henderson R Kopriva D Loveless S Graves P Gage R Bywater H Campbell G Nicely |
CCA | P.3, Resolution |
INPO aspect | PI.3 |
' | |