|
---|
Category:Letter
MONTHYEARIR 05000223/20242012024-11-0404 November 2024 University of Massachusetts Lowell– U.S. Nuclear Regulatory Commission Safety Inspection Report 05000223/2024201 ML24227A9662024-08-14014 August 2024 Submittal of Annual Report for the University of Massachusetts Lowell Research Reactor ML24221A1562024-08-0808 August 2024 University of Massachusetts, Umlrr Physical Security Plan – Revision 7 IR 05000223/20244102024-08-0505 August 2024 University of Massachusetts-Lowell - Us Nuclear Regulatory Commission Security Inspection Report 05000223/2024410 (Public) ML24024A2372024-01-31031 January 2024 Examination Confirmation Letter No. 50-223/OL-24-01, University of Massachusetts-Lowell IR 05000223/20232012023-11-24024 November 2023 University of Massachusetts, Lowell – U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000223/2023201 ML23241A0502023-08-29029 August 2023 Univ. of Massachusetts - Lowell, Submittal of Annual Report ML23152A1582023-06-0101 June 2023 To the Emergency Preparedness Plan for the University of Massachusetts Lowell Research Reactor (Umlrr) ML23107A1862023-04-21021 April 2023 Examination Results Letter No. 50-223/OL-23-01 ML23024A1412023-03-0707 March 2023 Examination Confirmation Letter, University of Massachusetts-Lowell, OL-23-01 IR 05000223/20222012022-10-16016 October 2022 University of Massachusetts Lowell - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000223/2022201 ML22243A1412022-08-30030 August 2022 Annual Report for the University of Massachusetts Lowell Research Reactor ML22154A4812022-06-0909 June 2022 Examination Confirmation Letter No. 50-223/OL-22-01, University of Massachusetts-Lowell ML22075A1172022-03-15015 March 2022 University of Massachusetts-Lowell Research Reactor - Designation of Level-1 and Level-2 Per License Technical Specifications 6.1.2(1 and 2) and 6.7.2(3) ML21168A0532022-02-0303 February 2022 University of Massachusetts Lowell, Transmittal Letter for Renewal of Facility Operating License No. R-125 IR 05000223/20212012021-12-17017 December 2021 University of Massachusetts-Lowell - Nuclear Regulatory Commission Security Inspection Report No. 05000223/2021201 - Cover Letter IR 05000223/20212022021-12-17017 December 2021 University of Massachusetts Lowell U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000223/2021202 ML21302A0552021-11-0909 November 2021 University of Massachusetts Lowell Update Regarding the Renewal of Facility Operating License No. R-125 ML21229A0812021-08-30030 August 2021 University of Massachusetts Lowell, Update Regarding the Renewal of Facility Operating License No. R-125 ML21214A1102021-08-0202 August 2021 Univ of Massachusetts - Lowell, Submittal of Routine Annual Report ML21133A1682021-05-19019 May 2021 University of Massachusetts Lowell, Update Regarding the Renewal of Facility Operating License No. R-125 ML21110A0532021-04-20020 April 2021 University of Massachusetts-Lowell Research Reactor - Draft Renewed License ML20317A1942021-04-13013 April 2021 University of Massachusetts Lowell Routine Reactor Inspection Report - October 2020 ML21095A2452021-04-0505 April 2021 University of Massachusetts, Lowell Research Reactor - Request for Additional Language to Item 2.B of the Proposed Renewed Facility Operating License ML21042B8572021-03-0404 March 2021 University of Massachusetts Lowell, Report on the Regulatory Audit Re the Renewal of Facility Operating License No. R-125 ML21047A2452021-02-16016 February 2021 University of Massachusetts-Lowell Research Reactor - Response to Items Discussed in NRC Telephone Conference with Uml on 02/11/21 ML21030A0052021-01-30030 January 2021 University of Massachusetts-Lowell Research Reactor - Response to NRC License Renewal Audit Letter Dated 12/17/2020 (ML20303A305) ML21007A1722021-01-11011 January 2021 University of Massachusetts Lowell, Status of the Regulatory Audit and Update Regarding the Renewal of Facility Operating License No. R-125 ML21005A2372021-01-0505 January 2021 Univ. of MA-Lowell Research Reactor - Response to NRC Letter Dated December 17, 2020, Report on Regulatory Audits the Renewal of Facility Operating License No. R-125 ML20303A3052020-12-17017 December 2020 University of Massachusetts Lowell, Report on the Regulatory Audits the Renewal of Facility Operating License No. R-125 ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20274A2492020-09-30030 September 2020 University of Massachusetts-Lowell Research Reactor - Response to NRC License Renewal Audit Letter Dated 9/1/2020 (ML20240A043) ML20274A2552020-09-30030 September 2020 Opto 22 Procedures: Software Quality Assurance Plan ML20240A0432020-09-0101 September 2020 University of Massachusetts Lowell, Status of the Regulatory Audit and Update Regarding the Renewal of Facility Operating License No. R-125 ML20196L9762020-07-16016 July 2020 University of Massachusetts Lowell, Status of the Regulatory Audit and Update Regarding the Renewal of Facility Operating License No. R-125 ML20114E0592020-04-27027 April 2020 University of Massachusetts Lowell, Status of the Regulatory Audit and Update Regarding the Renewal of Facility Operating License No. R-125 ML20055F6042020-02-24024 February 2020 University of Massachusetts-Lowell - Closeout of Open RAI Items 7.4c and 7.5a, NRC Letter Dated July 19, 2019 - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125 ML20036E5012020-02-13013 February 2020 Request for Withholding of Information from Public Disclosure Documents in Support of Licensing Requests Initiated by the University of Massachusetts Lowell ML20021A3152020-02-0404 February 2020 University of Massachusetts Lowell - Regulatory Audit the Renewal of Facility Operating License No. R-125 ML20009E8482020-01-13013 January 2020 University of Massachusetts Lowell, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125 ML20017A1552020-01-0808 January 2020 Request by General Atomics to Withhold Certain Information from Public Disclosure Under 10CFR2.390 ML19354A6102019-12-20020 December 2019 Supplement to University of Massachusetts Lowell Letter Dated 12/19/2019 in Response to Letter from NRC ML19353C5232019-12-19019 December 2019 Second Supplement to Response Dated October 18, 2019 (First Supplement Dated 10/24/19) Regarding NRC Letter Dated July 19, 2019 - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125 and Second Re ML19296E2792019-10-30030 October 2019 University of Massachusetts Lowell, Response to Request for Extension of Time to Respond to Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125 ML19297F4332019-10-24024 October 2019 University of Massachusetts-Lowell Research Reactor - Supplement to Response Dated October 18, 2019 Regarding NRC Letter Dated July 19, 2019 - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125 ML19291C2932019-10-18018 October 2019 University of Massachusetts - Lowell - Response to NRC Letter Dated July 19, 2019 - Request for Additional Information Re the Renewal of Facility Operating License No. R-125 Instrumentation and Controls (EPID No. L-2015-RNW-0001) & Request ML19248C1162019-08-30030 August 2019 Submittal of Routine Annual Report for the University of Massachusetts Lowell Research Reactor ML19214A0192019-08-27027 August 2019 University of Massachusetts Lowell, Review of Emergency Plan in Support of License Renewal ML19214A0172019-08-27027 August 2019 University of Massachusetts Lowell, Review of Physical Security Plan in Support of License Renewal ML18092B0902019-07-19019 July 2019 University of Massachusetts Lowell - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-125 for the University of Massachusetts Lowell Research Reactor and Primarily Related to Instrumentation and C 2024-08-08
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML21095A2452021-04-0505 April 2021 University of Massachusetts, Lowell Research Reactor - Request for Additional Language to Item 2.B of the Proposed Renewed Facility Operating License ML16082A4042016-03-22022 March 2016 University of Massachusetts-Lowell - License Amendment Request ML16042A0162016-02-16016 February 2016 University of Massachusetts, Lowell - Safety Analysis Report (Chapters 8-15)- Redacted ML16042A0172016-02-16016 February 2016 University of Massachusetts, Lowell - Safety Analysis Report, (Chapters 1-7) - Redacted ML16014A0462016-01-12012 January 2016 Univ. of Massachusetts-Lowell - License Amendment Request to Revise Technical Specification 4.4, Containment Building ML15293A3842015-10-20020 October 2015 University of Massachusetts - Lowell - Request for Renewal of Facility Operating License R-125 ML0918203232009-06-29029 June 2009 University of Massachusetts - Lowell, License Amendment Request to Increase in Uranium-235 Limit 2021-04-05
[Table view] |
Text
Pinanski Building One University Avenue Lowell, Massachusetts 01854 tel: 978.934.3280 fax. 978.934.4067 e-mail: GunterKegel@uml.edu Gunter H.R.Kegel, Ph.D.Director, Radiation Laboratogy
/9J University of Massachusetts UMASS Lowell RADIATION LABORATORY June 29, 2009 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Re: SNM Limit, License No. R-125, Docket No. 50-223 The University of Massachusetts Lowell hereby requests an amendment to its Facility Operating License No. R-125. The requested amendment is for an increase in the Uranium-235 limit specified in paragraph 2.B.(2) of the license from 6 kilograms to 11 kilograms of Uranium-235 at enrichments equal to or less than 20% in the form of material test reactor (MTR) fuel.A detailed justification for this request is provided in the attached document.Please direct any requests for additional information regarding this submittal to: Mr. Leo Bobek, Reactor Supervisor Radiation Laboratory University of Massachusetts Lowell One University Avenue Lowell, MA 01854 I declare under penalty of perjury that the foregoing is true and correct.Sincerely, cxL LAACA P Gunter H. R. Kegel Director, Radiation Laboratory Cc: Ms. Cindy Montgomery NRR/ADRO USNRC A cam Information Related to the Increased SNM Limit Amendment Facility Operating License No. R-125 University of Massachusetts Lowell Docket No. 50-223 Overview The 10 kW research reactor at Worcester Polytechnic Institute
('WPI) is in the process of decommissioning.
The WPI and the University of Massachusetts Lowell (UML) research reactors were both designed and manufactured by General Electric.
Both reactors use low-enriched uranium (<20% U-235) MTR-type flat plate fuel having the same physical dimensions.
The fuel elements used in the WPI reactor have a combined negligible bum-up of less than 0.2 gram U-235 resulting from a combined usage of less than 2% of 1 Megawatt Day (MWD).Currently, the fuel in the UML research reactor has an estimated useful life of approximately 120 MWD. A small number of unused elements stored on site will provide an additional estimated 60 MWD. Given a not unreasonable usage of 20 MWD per year, the current fuel inventory will last approximately 9 years. Usage of the WPI fuel could provide approximately another 150 MWD of operation.
There are slight differences in the material composition and U-235 loading between the WPI and UJML fuels. The WPI fuel elements consist of 18 plates having a U-Al, fuel matrix with approximately 170 grams of U-235 per element. The UML fuel consists of 16 plates having a U 3 Si 2-Al fuel matrix with approximately 200 grams of U-235 per element. Thus, the WPI fuel is slightly less reactive than the UML fuel. Nonetheless, usage of the WPI fuel would provide a low-cost solution to the long-term fuel needs of the UML research reactor.Storage Fuel storage at the UML research reactor is described in the UMLRR Final Safety Analysis Report (1984) section 6.1 and as evaluated in section 9.1 of NUREG-1 139 (SER Related to the Renewal of the Operating License for the Training and Research Reactor at the University of Lowell -November 1985) and as evaluated in section 2.4 of the safety evaluation for facility license R-125, amendment
- 12. In summary, the UMLRR has a safe and secure storage capacity for 72 MTR-type flat plate fuel elements.
This capacity exceeds that required for both the existing on-site fuel and the WPI fuel.Security The storage is located within the designated areas of the control access area as described in the Physical Security Plan for Protection of Special Nuclear Material of Moderate Strategic Significance at the University of Massachusetts Lowell Research Reactor (Rev. 5). The security systems, plans and procedures as described in the aforementioned plan meet or exceed the 1 OCFR 73.67 requirements for SNM quantities of moderate strategic significance.
Usage The Technical Specifications for Facility License R-125 (Section 5.1) do not permit the use of the WPI fuel in the UML reactor. A supplemental safety analysis will be performed and then submitted along with license amendment request to allow use the WPI fuel in the UML reactor.