MONTHYEARML18066A3251998-11-0909 November 1998 Application for Amend to License DPR-20,deleting CVCS Operability Requirements Currently in LCOs 3.2 & 3.17.6 & Associated Testing Requirements in SRs 4.2 & 4.17 ML18066A1981998-06-17017 June 1998 Application for Amend to License DPR-20,updating TS to Reflect Reduced Min Reactor Vessel Flow Rate Assumption in Accident Analyses ML18065B1831998-03-13013 March 1998 Revised Application for Amend to License DPR-20,requesting Relocation of TS Section 4.16 Snubber Testing Requirements to Plant Operating Requirements Manual (Orm).Affected Orm Pages Encl ML18065B1781998-03-13013 March 1998 Application for Amend to License DPR-20,changing Auxiliary Feedwater TS to Allow Installation of Plant Mod W/O Requiring Plant Shutdown ML18067A7051997-10-0101 October 1997 Application for Amend to License DPR-20,proposing That TS Flywheel Insp Period Be Lengthened to Ten Years & Deleting Note Re Insp at End of Cycle 12 ML18067A6751997-09-0303 September 1997 Application for Amend to License DPR-20,deleting Snubber Operability Requirements in LCO 3.20 & Snubber Testing Requirements in Surveillance Requirement 4.16 ML18067A6711997-09-0303 September 1997 Application for Amend to License DPR-20,reflecting Capabilities of Installed CR Ventilation Equipment & Emulate Std Tech Specs,C-E Plants,Per NUREG-1432 Requirements for Sys ML18067A4511997-03-26026 March 1997 Application for Amend to License DPR-20,allowing Entry Into Air Lock to Perform Repairs on Inoperable Air Lock Door & Thereby Avoid Potential for Unnecessary Plant Shutdown ML18065A4891996-02-0606 February 1996 Application for Amend to License DPR-20,requesting to Remove cross-train Testing Requirements from LCO Action Statements ML18065A4381996-01-18018 January 1996 Application for Amend to License DPR-20,revising TS to Allow Use of 10CFR50 App J Option B Containment Testing & Use of Warning Light to Identify Certain High Radiation Areas,To Suppl 951211 Administrative Controls Change Request ML18065A4341996-01-18018 January 1996 Application for Amend to License DPR-20,revising TS Re Primary Coolant Pump Flywheel Insp.Rev 1 to Structural Integrity Assoc,Inc Rept SIR-94-080, Relaxation of Reactor Coolant Pump Flywheel Insp Requirements Encl ML18065A4051996-01-10010 January 1996 Application for Amend to License DPR-20,requesting Exemption from 10CFR50 App J TS Change Request Concerning Local Leak Test Requirements for Emergency Escape Airlock in Plant Containment Bldg ML18065A3821996-01-0505 January 1996 Application for Amend to License DPR-20,revising SDC Requirements & Bases for TS Section 3.1.9.3 Prior to 1996 Refueling Outage ML18065A3751995-12-27027 December 1995 Application for Amend to License DPR-20,rewriting Electrical Power Sys Sections of TS & Bases to Closely Emulate STS ML18065A3461995-12-11011 December 1995 Application for Amend to License DPR-20,revising Administrative Controls Section to Emulate CE STS by Removing Review & Audit Requirements of Section 6.5 & Record Retention Requirements of Section 6.10 from TS ML18065A3321995-12-0606 December 1995 Application for Amend to License DPR-20,relocating Crane Operation & Movement of Heavy Loads Requirements & Bases from TS to Other Plant Documents Prior to 1996 Refueling Outage ML18065A1741995-10-17017 October 1995 Application for Amend to License DPR-20,changing Paragraph 2.B.(2) to Ref 10CFR40 & to Allow Use of Source Matls as Reactor Fuel,Rewording Paragraph 2.E & Deleting Paragraph 2.7 & Revising TS Pressurizer Cooldown Limit ML18064A8391995-07-0505 July 1995 Application for Amend to License DPR-20,deleting TS 6.4, Training & Revising TS 6.5.1.2 on Plant Review Committee Composition & 6.5.3.1 & 6.5.3.2,clarifying & Modifying Function & Composition of Plant Safety & Licensing Staff ML18064A7591995-05-0101 May 1995 Application for Amend to License DPR-20.Amend Would Place Requirements in TS Section 4.7 for Periodic DG Peak Load Tests ML18064A6121995-02-10010 February 1995 Application for Amend to License DPR-20,proposing One Time Deferral of 18-month Refueling Interval Surveillance Tests ML18064A5821995-01-13013 January 1995 Tech Specs Change Request to License DPR-20 Addressing Required Settings & Allowable as Found & as Left Tolerances for Primary & Secondary Safety Valves ML18064A5341994-12-29029 December 1994 Application for Amend to License DPR-20,revising TSs Re Iodine Removal Sys ML18064A5061994-12-13013 December 1994 Application for Amend to License DPR-20,adding Third High Thermal Performance DNB Correlation to Safety Limit 2.1 ML18064A4081994-10-0505 October 1994 Application for Amend to License DPR-20,revising TS Relating to Primary Coolant Sys pressure-temp Limits.Rev 0 to Engineering Analysis EA-A-PAL-92-095-01 & Excerpts from Rosemount Instruction Manual 4515,dtd Jan 1988 Encl ML18059B0961994-07-0707 July 1994 Application for Amend to License DPR-20,revising TS Re Shutdown Cooling.Changes Intended to Resolve Concerns Arose During NRC Review of Change Request ML18059A9751994-05-0505 May 1994 Application for Amend to License DPR-20,revising TS Re Shutdown Cooling.Changes Necessary Due to Intervening Amends Containing Listed Differences from Pages Submitted on 930519 ML18059A9321994-04-0707 April 1994 Application for Amend to License DPR-20,requesting TS Change Re Instrumentation & Control Section ML18059A9411994-04-0707 April 1994 Application for Amend to License DPR-20,relocating Cycle Specific Operating Limits to Colr,Per Guidance of GL 88-16, Removal of Cycle-Specific Parameter Limits from Ts. Proposed COLR Encl ML18059A8851994-03-11011 March 1994 Rev to 940222 I&C TS Change Request to License DPR-20,adding Surveillance Item 10 to Table 4.2.1 Which Require Verifying SIT Level & Pressure Each Shift & Adding Three Paragraphs to Basis for Proposed Section 3.17 ML18059A3721993-09-0303 September 1993 Changes to 930129 Application for Amend to License DPR-20, Modifying Radial Peaking Factor Limits in TS Table 3.23-2 to Incorporate Appropriate Limits for Modified L Fuel Assemblies Recently Installed in Reactor for Cycle 11 ML18058B8991993-06-25025 June 1993 Revises 921208 Application for Amend to License DPR-20 & Brings Proposed Specifications Closer to Model Tech Specs, While Retaining Necessary plant-specific Differences & Updating Proposed Pages to Reflect Amends 147 & 149 ML18058B7421993-03-29029 March 1993 Application for Amend to License DPR-20,changing TS to Required Frequency for Surveillance Test Which Requires Moving Each Control Rod to Once Each 92 Days Instead of Once Every 2 Wks ML18058B3881993-01-29029 January 1993 Application for Amend to License DPR-20,consisting of Proposed TS Changes to Table 3.23-2, Radiation Peaking Factor Limits for Cycle 11. Offsite Dose Calculations & EMF-92-178, Palisades Cycle 11:Disposition & ... Encl ML18058B3481993-01-19019 January 1993 Application for Amend to License DPR-20,changing Surveillance Interval for Testing Control Rod Drive mechanisms,CRD-20 & CRD-31 from Every Two Wks to Once in Mar 1993 ML18058A5631992-06-22022 June 1992 Suppl to 920317 Application for Amend to License DPR-20, Consisting of Revised Page 3-82 Re Shutdown Cooling ML18058A5561992-06-12012 June 1992 Application for Amend to License DPR-20,changing TS to Better Coordinate Required Action Statement of Electrical Sys Spec W/Lco to Allow Testing & Loading of DG When Plant Above 325 F But Not Yet Critical ML18058A5491992-06-12012 June 1992 Application for Amend to License DPR-20,changing TS to Delete Requirements Re Iodine Removal Sys Hydrazine Storage Tank Since Use of Hydrazine No Longer Considered in Current Rev of SRP ML18058A3631992-04-15015 April 1992 Application for Amend to License DPR-20,changing TSs to Incorporate Generic Ltr 90-06 PORV Requirements for Power Operation & Modifying Pcs Overpressure Protection Spec Venting Requirements ML18058A2921992-03-18018 March 1992 Application for Amend to License DPR-20,revising TS Re Shutdown Cooling ML18058A1541992-02-0303 February 1992 Application for Amend to License DPR-20,deleting Three Primary Coolant Pump Testing Requirements & Revising Safety Limits & Limiting Safety Sys Settings Specs to Enhance Clarity of Subj Requirements ML18057B3711991-11-12012 November 1991 Application for Amend to License DPR-20,revising Tech Specs to Remove Schedule for Withdrawal of Reactor Vessel Matl Specimens,Per Generic Ltr 91-01 ML18057B3481991-11-0101 November 1991 Application for Amend to License DPR-20,changing TS for Operation During Cycle 10 as Results of Changes to Fuel Design (Reload N) & Fuel Mgt Scheme for Low Leakage Core. Siemens Repts EMF-91-176 & EMF-91-177 Encl ML18057B3061991-09-27027 September 1991 Application for Amend to License DPR-20,proposing Change to Tech Spec 5.2.3.a Re Containment Air Cooler Design,Per 861020 & 870430 Requests ML18057B3021991-09-26026 September 1991 Application for Amend to License DPR-20,consisting of Rev 2 to 890628 Request,In Response to Recommendations of Generic Ltr 88-17 to Add Shutdown Cooling Sys Operability Requirements to Tech Specs ML18057B1681991-07-15015 July 1991 Application for Amend to License DPR-20,requesting Tech Spec Changes in Administrative Controls W/Emphasis on Changes in Engineering ML18057A9821991-06-13013 June 1991 Application for Amend to License DPR-20,revising Tech Specs to Incorporate Change to Inservice Insp Program for Shock Suppressors (Snubbers) ML18057A9631991-05-30030 May 1991 Application for Amend to License DPR-20,changing Tech Specs to Incorporate Change to Reactor Variable High Power Trip setpoint.ANF-90-181, Review & Analysis of SRP Chapter 15 Events for Palisades W/15% Variable High Power... Encl ML18057A9551991-05-28028 May 1991 Application for Amend to License DPR-20,changing Tech Specs Re Inservice Insp Program for Shock Suppressors (Snubbers) ML18057A8881991-05-0101 May 1991 Rev 1 to Application for Amend to License DPR-20,changing TS Re Shutdown Cooling Sys Per Generic Ltr 88-17,by Adding Operability Requirements for Shutdown Cooling Sys & Steam Generators ML18057A8291991-03-25025 March 1991 Application for Amend to License DPR-20,changing Tech Specs Section 4.5.2a(2) & 4.5.2b(3) 1998-06-17
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML18066A3251998-11-0909 November 1998 Application for Amend to License DPR-20,deleting CVCS Operability Requirements Currently in LCOs 3.2 & 3.17.6 & Associated Testing Requirements in SRs 4.2 & 4.17 ML18066A1981998-06-17017 June 1998 Application for Amend to License DPR-20,updating TS to Reflect Reduced Min Reactor Vessel Flow Rate Assumption in Accident Analyses ML18065B1831998-03-13013 March 1998 Revised Application for Amend to License DPR-20,requesting Relocation of TS Section 4.16 Snubber Testing Requirements to Plant Operating Requirements Manual (Orm).Affected Orm Pages Encl ML18065B1781998-03-13013 March 1998 Application for Amend to License DPR-20,changing Auxiliary Feedwater TS to Allow Installation of Plant Mod W/O Requiring Plant Shutdown ML18067A7051997-10-0101 October 1997 Application for Amend to License DPR-20,proposing That TS Flywheel Insp Period Be Lengthened to Ten Years & Deleting Note Re Insp at End of Cycle 12 ML18067A6751997-09-0303 September 1997 Application for Amend to License DPR-20,deleting Snubber Operability Requirements in LCO 3.20 & Snubber Testing Requirements in Surveillance Requirement 4.16 ML18067A6711997-09-0303 September 1997 Application for Amend to License DPR-20,reflecting Capabilities of Installed CR Ventilation Equipment & Emulate Std Tech Specs,C-E Plants,Per NUREG-1432 Requirements for Sys ML18067A4511997-03-26026 March 1997 Application for Amend to License DPR-20,allowing Entry Into Air Lock to Perform Repairs on Inoperable Air Lock Door & Thereby Avoid Potential for Unnecessary Plant Shutdown ML18065A4891996-02-0606 February 1996 Application for Amend to License DPR-20,requesting to Remove cross-train Testing Requirements from LCO Action Statements ML18065A4381996-01-18018 January 1996 Application for Amend to License DPR-20,revising TS to Allow Use of 10CFR50 App J Option B Containment Testing & Use of Warning Light to Identify Certain High Radiation Areas,To Suppl 951211 Administrative Controls Change Request ML18065A4341996-01-18018 January 1996 Application for Amend to License DPR-20,revising TS Re Primary Coolant Pump Flywheel Insp.Rev 1 to Structural Integrity Assoc,Inc Rept SIR-94-080, Relaxation of Reactor Coolant Pump Flywheel Insp Requirements Encl ML18065A4051996-01-10010 January 1996 Application for Amend to License DPR-20,requesting Exemption from 10CFR50 App J TS Change Request Concerning Local Leak Test Requirements for Emergency Escape Airlock in Plant Containment Bldg ML18065A3821996-01-0505 January 1996 Application for Amend to License DPR-20,revising SDC Requirements & Bases for TS Section 3.1.9.3 Prior to 1996 Refueling Outage ML18065A3751995-12-27027 December 1995 Application for Amend to License DPR-20,rewriting Electrical Power Sys Sections of TS & Bases to Closely Emulate STS ML18065A3461995-12-11011 December 1995 Application for Amend to License DPR-20,revising Administrative Controls Section to Emulate CE STS by Removing Review & Audit Requirements of Section 6.5 & Record Retention Requirements of Section 6.10 from TS ML18065A3321995-12-0606 December 1995 Application for Amend to License DPR-20,relocating Crane Operation & Movement of Heavy Loads Requirements & Bases from TS to Other Plant Documents Prior to 1996 Refueling Outage ML18065A1741995-10-17017 October 1995 Application for Amend to License DPR-20,changing Paragraph 2.B.(2) to Ref 10CFR40 & to Allow Use of Source Matls as Reactor Fuel,Rewording Paragraph 2.E & Deleting Paragraph 2.7 & Revising TS Pressurizer Cooldown Limit ML18064A8391995-07-0505 July 1995 Application for Amend to License DPR-20,deleting TS 6.4, Training & Revising TS 6.5.1.2 on Plant Review Committee Composition & 6.5.3.1 & 6.5.3.2,clarifying & Modifying Function & Composition of Plant Safety & Licensing Staff ML18064A7591995-05-0101 May 1995 Application for Amend to License DPR-20.Amend Would Place Requirements in TS Section 4.7 for Periodic DG Peak Load Tests ML18064A6121995-02-10010 February 1995 Application for Amend to License DPR-20,proposing One Time Deferral of 18-month Refueling Interval Surveillance Tests ML18064A5821995-01-13013 January 1995 Tech Specs Change Request to License DPR-20 Addressing Required Settings & Allowable as Found & as Left Tolerances for Primary & Secondary Safety Valves ML18064A5341994-12-29029 December 1994 Application for Amend to License DPR-20,revising TSs Re Iodine Removal Sys ML18064A5061994-12-13013 December 1994 Application for Amend to License DPR-20,adding Third High Thermal Performance DNB Correlation to Safety Limit 2.1 ML18064A4081994-10-0505 October 1994 Application for Amend to License DPR-20,revising TS Relating to Primary Coolant Sys pressure-temp Limits.Rev 0 to Engineering Analysis EA-A-PAL-92-095-01 & Excerpts from Rosemount Instruction Manual 4515,dtd Jan 1988 Encl ML18059B0961994-07-0707 July 1994 Application for Amend to License DPR-20,revising TS Re Shutdown Cooling.Changes Intended to Resolve Concerns Arose During NRC Review of Change Request ML18059A9751994-05-0505 May 1994 Application for Amend to License DPR-20,revising TS Re Shutdown Cooling.Changes Necessary Due to Intervening Amends Containing Listed Differences from Pages Submitted on 930519 ML18059A9321994-04-0707 April 1994 Application for Amend to License DPR-20,requesting TS Change Re Instrumentation & Control Section ML18059A9411994-04-0707 April 1994 Application for Amend to License DPR-20,relocating Cycle Specific Operating Limits to Colr,Per Guidance of GL 88-16, Removal of Cycle-Specific Parameter Limits from Ts. Proposed COLR Encl ML18059A8851994-03-11011 March 1994 Rev to 940222 I&C TS Change Request to License DPR-20,adding Surveillance Item 10 to Table 4.2.1 Which Require Verifying SIT Level & Pressure Each Shift & Adding Three Paragraphs to Basis for Proposed Section 3.17 ML18059A3721993-09-0303 September 1993 Changes to 930129 Application for Amend to License DPR-20, Modifying Radial Peaking Factor Limits in TS Table 3.23-2 to Incorporate Appropriate Limits for Modified L Fuel Assemblies Recently Installed in Reactor for Cycle 11 ML18058B8991993-06-25025 June 1993 Revises 921208 Application for Amend to License DPR-20 & Brings Proposed Specifications Closer to Model Tech Specs, While Retaining Necessary plant-specific Differences & Updating Proposed Pages to Reflect Amends 147 & 149 ML18058B7421993-03-29029 March 1993 Application for Amend to License DPR-20,changing TS to Required Frequency for Surveillance Test Which Requires Moving Each Control Rod to Once Each 92 Days Instead of Once Every 2 Wks ML18058B3881993-01-29029 January 1993 Application for Amend to License DPR-20,consisting of Proposed TS Changes to Table 3.23-2, Radiation Peaking Factor Limits for Cycle 11. Offsite Dose Calculations & EMF-92-178, Palisades Cycle 11:Disposition & ... Encl ML18058B3481993-01-19019 January 1993 Application for Amend to License DPR-20,changing Surveillance Interval for Testing Control Rod Drive mechanisms,CRD-20 & CRD-31 from Every Two Wks to Once in Mar 1993 ML18058A5631992-06-22022 June 1992 Suppl to 920317 Application for Amend to License DPR-20, Consisting of Revised Page 3-82 Re Shutdown Cooling ML18058A5561992-06-12012 June 1992 Application for Amend to License DPR-20,changing TS to Better Coordinate Required Action Statement of Electrical Sys Spec W/Lco to Allow Testing & Loading of DG When Plant Above 325 F But Not Yet Critical ML18058A5491992-06-12012 June 1992 Application for Amend to License DPR-20,changing TS to Delete Requirements Re Iodine Removal Sys Hydrazine Storage Tank Since Use of Hydrazine No Longer Considered in Current Rev of SRP ML18058A3631992-04-15015 April 1992 Application for Amend to License DPR-20,changing TSs to Incorporate Generic Ltr 90-06 PORV Requirements for Power Operation & Modifying Pcs Overpressure Protection Spec Venting Requirements ML18058A2921992-03-18018 March 1992 Application for Amend to License DPR-20,revising TS Re Shutdown Cooling ML18058A1541992-02-0303 February 1992 Application for Amend to License DPR-20,deleting Three Primary Coolant Pump Testing Requirements & Revising Safety Limits & Limiting Safety Sys Settings Specs to Enhance Clarity of Subj Requirements ML18057B3711991-11-12012 November 1991 Application for Amend to License DPR-20,revising Tech Specs to Remove Schedule for Withdrawal of Reactor Vessel Matl Specimens,Per Generic Ltr 91-01 ML18057B3481991-11-0101 November 1991 Application for Amend to License DPR-20,changing TS for Operation During Cycle 10 as Results of Changes to Fuel Design (Reload N) & Fuel Mgt Scheme for Low Leakage Core. Siemens Repts EMF-91-176 & EMF-91-177 Encl ML18057B3061991-09-27027 September 1991 Application for Amend to License DPR-20,proposing Change to Tech Spec 5.2.3.a Re Containment Air Cooler Design,Per 861020 & 870430 Requests ML18057B3021991-09-26026 September 1991 Application for Amend to License DPR-20,consisting of Rev 2 to 890628 Request,In Response to Recommendations of Generic Ltr 88-17 to Add Shutdown Cooling Sys Operability Requirements to Tech Specs ML18057B1681991-07-15015 July 1991 Application for Amend to License DPR-20,requesting Tech Spec Changes in Administrative Controls W/Emphasis on Changes in Engineering ML18057A9821991-06-13013 June 1991 Application for Amend to License DPR-20,revising Tech Specs to Incorporate Change to Inservice Insp Program for Shock Suppressors (Snubbers) ML18057A9631991-05-30030 May 1991 Application for Amend to License DPR-20,changing Tech Specs to Incorporate Change to Reactor Variable High Power Trip setpoint.ANF-90-181, Review & Analysis of SRP Chapter 15 Events for Palisades W/15% Variable High Power... Encl ML18057A9551991-05-28028 May 1991 Application for Amend to License DPR-20,changing Tech Specs Re Inservice Insp Program for Shock Suppressors (Snubbers) ML18057A8881991-05-0101 May 1991 Rev 1 to Application for Amend to License DPR-20,changing TS Re Shutdown Cooling Sys Per Generic Ltr 88-17,by Adding Operability Requirements for Shutdown Cooling Sys & Steam Generators ML18057A8291991-03-25025 March 1991 Application for Amend to License DPR-20,changing Tech Specs Section 4.5.2a(2) & 4.5.2b(3) 1998-06-17
[Table view] |
Text
. ,. .. consumers Power POW ERi Nii /IAICHlliAN'S PROGRESS General Offices: 1945 West Parnell Road, Jackson, Ml 49201 o (517) 788-1636 June 20, 1986 Director, Nuclear Reactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 -LICENSE DPR-20 -PALISADES PLANT -LICENSE AND TECHNICAL SPECIFICATIONS CHANGE REQUEST -ALLOWABLE QUANTITY OF SOURCE MATERIAL Kenneth W Berry Director Nuclear Licensing Attached are .three (3) originals and thirty-seven (37) conformed copies of a request to Palisades Provisional Operating.License DPR-20 and the Palisades -specifications.,.
The attached proposal requests a change to the allowable quantity of Cesium-137 as calil;>ration source specified in the Palisades Provisional Operating License. An increase in this limit is required to allow possession of sealed sources for calibration of high range radiation detection instruments.
The addition of the Cesium-137 calibration source is to fulfill a commitment to INPO. Since the receipt of this additional source is dependent upon approval of the requested License amendment we ask for prompt NRC action to approve this change. The proposal also requests the addition of new technical specifications that describe the leak test requirements for sealed. sources. The additional requirements are adopted from those provided in the CE Standard Technical Specifications (NUREG-0212, rev. 2) section 3/4.7.10.
A revised Table of Contents and correction of a typographical error are also included in this request. In a letter dated January 24, 1975, to Consumers Power Company, Big Rock Point Docket 50-155, D L Ziemann, NRC, described improvements that could be made to the license in regard to special nuclear, byproduct, and source materials.
Enclosed with the letter were standardized requirements which removed reference to specific quantities of the materials.
The standardized requirements were suggested to licensees to circumvent the need for issuing, on a priority basis, a license amendment when the required quantities of on-site material were to be changed-.
The License Change Request herein does 8606260309 860620 } ' PDR ADOCK 05000255 P ' PDR OC0686-'0097-NL04 ' \
_ .. Director, Nuclear Reactor Regulation Palisades Plant License & TSCR -Source Material June 20, 1986 not incorporate these requirements however it is our intent to submit an appropriate License Change Request in the near future that will be consistent with these requirements.
A check in the amount of $150.00 is enclosed as required by Kenneth W Berry Director, Nuclear Licensing CC Administrator, Region III, USNRC NRC Resident Inspector
-Palisades Attachment OC0686-0097-NL04 2
1 -----CUNSUMERS-.PbWER-*--cOMPANY
Docket 50-255 Request for Change to the Provisional Operating License DPR-20 and the Technical ications For the reasons hereinafter set forth, it is requested that the Provisional Operating License DPR-20, and the Technical Specifications, Docket 50-255, issued to Consumers Power Company on October 16, 1972, for the Palisades Plant be changed as described in Section I below: I. Changes: A. Change item 2(C) of the Provisional .Operating License to read: "C. Pursuant to the Act and 10CFR30,. "Rules of General Applicability
_of Licensing of Byproduct Material", to receive,.
possess, and use in connection with operation of the facility 1500 curies of Polonium-210 as two sealed sources not to exceed 750 curies each, 1000 curies of Cesium-137 as multiple . sealed calibration sources and up to 500 millicuries per nuclide of any byproduct material with Atomic Numbers 3 to 83, inclusive, without restriction to chemical and physical form to a total of 10. curies;" B. Revise the Table of Contents to remove deleted section 3.1.9, add Listing of Tables and Figures, add section 6.2.1 Sealed Source Contamination, and make miscellaneous corrections.
C. Revise Table 3.17.4 note (g) to read: "(g) Calculate the Quandrant Power Tilt using the excore readings *at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.when the excore detectors deviation*alarms are inoperable." D. Add a new Section 6.21 to read: "6.21 SEALED SOURCE CONTAMINATION 6.21.1 Each sealed source containing radioactive material either in excess of 100 microcuries of beta and/or gamma emitting material or 5 microcuries of alpha emitting mate.rial shall be 9f than or equal. to 0. 005 of removable contamination.
6.21.2 With a sealed source having removable contamination in excess of 0.005 microcuries, immediately withdraw the sealed source from use and either: 1. Decontaminate and repair the sealed source, or TS0586-0001A-LI01-NL04
- 2. Dispose of the sealed source in accordance with applicable regulations.
6.21.3 Each category of sealed sources as described in 6.21.l (excluding startup sources and fission detectors previously subjected to core flux) with a half-life greater than 30 days (excluding Hydrogen-3), and in any other form than gas, shall be tested for leakage and/or contamination at intervals not to exceed six months. 2 6.21.4 The test shall be performed by the licensee or by other persons specifically authorized by the Commission or an Agreement State. The test method shall have a detection sensitivity of at least 0.005 microcuries per test sample. 6.21.5 The test sample shall be taken from the sealed source or, in the case of permanently mounted sources, from the surfaces of the mounting device on which contamination would be expected to accumulate.
6.21.6 The leak test does not apply to sealed sources that are stored and not being used. These sources shall be tested prior to use or transfer to another licensee, unless tested within the previous six months. Sealed sources which are continuously enclosed within .a shielded mechanism (ie, sealed sources within radiation monitoring or boron measuring devices) are considered to be stored and need not be tested unless they are removed from the shielded mechanism.
6.21.7 sources transferred without a certificate indicating the last test date shall be tested prior to being placed in use. 6.21.8 A report shall be prepared and submitted to the Commission on an annual basis if sealed source leakage tests reveal the presence of greater than or equal to 0.005 microcuries of removable contamination." II. Discussion The proposed change requests an increase in the possession limit for Cesium-137 as sealed sources. The change consolidates the individual listing of each Cesium-137 source into a single stated quantity.
In addition, a new administrative section reque.sted to descr:ibe the leak -test --requirements for calibration sources. Also a typographical error that was incorporated in Amendment 96, 1/30/86 has been corrected in item I.C. The increased Cesium-137 quantity limit is needed to allow the possession of a calibration source for high range radiation detection instruments.
The source will allow the verification of the accuracy of these instruments on all measurement scales. This is a des*irable TS0586-0001A-LI01-NL04 feature that can be expected to improve radiation protection capabilities.
The consolidation of the individual Cesium-137 sources into a single possession limit is intended to remove the need for further amendments.
3 The additional administrative requirements are based on the guidance provided in the Standard Technical Specifications.
These requirements have been modified sufficiently for application to the Palisades Plant. The significant variations and other items of interest are as follows: 1. The proposed Section 6.21.5 includes provisions that allow for a test sample to be taken from the surface of a mounting device. This allowance was deemed necessary to limit the potential dose received from attempting to achieve direct access to these sources. 2. Current Technical Specifications provide record retention requirements for sealed source leak tests in Section 6.10.l(i).
Analysis of No Significant Hazards Considerations Possession of byproduct materials is licensed under the requirements of 10CFR30. Typically, commercial nuclear plants have incorporated this byproduct license into the plant operating license. Inclusion in the operating license necessitates an application for an amendment to the byproduct license through a more restrictive process than that prescribed by 10CFR30. A request to amend a* 10CFR30 byproduct license does not require an analysis of the significant hazards considerations.
As provided in 10CFR30.38, the application for amendment needs only to specify the desired changes and the grounds for the change. This information has been detailed in the preceding Sections I and II. Although not required by 10CFR30, the significant hazards evaluation of this change is presented in support of the request for an amendment to the operating license. The effects of the additional tive requirements are also presented.
The analysis is as follows: 1. The requested changes do not result in an increase in the probability or consequences of a previously evaluated accident.
The change affects the aliowable quantity as sealed source material.
The change also provides additional istrative requirements for the control of sealed sources. The types of occurrences that would result from sealed sources are not evaluated in the FSAR. Formal evaluation of these potential occurrences is not required to assure nuclear safety, and does not relate to nuclear safety or previously evaluated accidents.
TS0586-0001A-LI01-NL04
- 2. 4 The change does not create the possibility of a new or different kind of accident.
The operating license previously authorized the -p-oss-e*s-sion*-o*f--seal-ed--s*o*ur*c*es
.-Potent-ia.1-occurrence-s-from-th-eSe___ -------*----------sources were not required to be formally analyzed.
An analysis remains unnecessary for this category of occurrence.
The administrative requirements provided by this proposal result in additional controls not presently included in the Technical Specifications.
As such, these controls will enhance the radiation safety program and the control of sealed sources. Also, these requirements are not new in that the leak testing of sealed sources is an existing program. This request only results in further emphasis on the importance of this program. 3. The change does not result in a reduction in the margin of safety. The increased possession limit affects an aspect of plant operation that is unrelated to nuclear safety. The provisions for formalized leak testing requirements in conjunction with existing procedural controls are adequate to ensure no reduction in any type of radiological safety margin. III. Conclusion The Palisades Plant Review Committee has reviewed this Technical Specification Change Request and has determined that this' change does not involve an unreviewed safety question and therefore involves no significant hazards consideration.
This change has also been reviewed under the cognizance of the Nuclear Safety Board. A copy of this Technical Specification Change Request has been sent to the State of* Michigan official designated to receive such Amendments to the
- Operating License. CONSUMERS POWER COMPANY By Sworn and subscribed to before me this 20th day of June 1986. Elaine E Buehrer, Notary Public Jackson County, Michigan My commission expires October.31, 1989 TS0586-0001A-LI01-NL04