Other: GNRO-2013/00014, Entergy'S Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, GNRO-2016/00010, Entergy Update to Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, ML13057A116, ML13058A066, ML13127A146, NLS2013028, Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, PLA-7034, Response to Follow-Up Letter on Technical Issues for Resolution Regarding Licensees Communication Submittals
|
MONTHYEARNOC-AE-12002867, Revised 60-Day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-06-0404 June 2012 Revised 60-Day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI NOC-AE-12002859, Day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident2012-06-0404 June 2012 Day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-Ichi Accident Project stage: Response to RAI GNRO-2012/00052, Entergy'S 90-Day Response to the March 12, 2012, Information Request, Action Plan for Completing Emergency Communication and Staffing Assessments2012-06-0808 June 2012 Entergy'S 90-Day Response to the March 12, 2012, Information Request, Action Plan for Completing Emergency Communication and Staffing Assessments Project stage: Request ML12311A0282012-10-31031 October 2012 Emergency Preparedness Information Requested by NRC Letter, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1,... Project stage: Request NOC-AE-13002958, STPNOC Response to January 23, 2013, Request for Additional Information Related to the Near-Term Task Force Recommendation 9.3 on Communications2013-02-21021 February 2013 STPNOC Response to January 23, 2013, Request for Additional Information Related to the Near-Term Task Force Recommendation 9.3 on Communications Project stage: Request NLS2013028, Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.32013-02-21021 February 2013 Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other GNRO-2013/00014, Entergy'S Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.32013-02-21021 February 2013 Entergy'S Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other ML13057A1162013-02-22022 February 2013 Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other ML13058A0662013-02-22022 February 2013 Response to NRC Follow-up Letter on Technical Issues for Resolution Regarding Licensee Communication Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other ML13057A5932013-02-22022 February 2013 Response to Follow-up Letter on Technical Issues for Resolution Regarding Licenses Communication Submittals Project stage: Request L-13-047, Supplement to Response to NRC Letter, Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2013-02-22022 February 2013 Supplement to Response to NRC Letter, Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Supplement ML13127A1462013-05-0606 May 2013 Email Table 2 Response Question Project stage: Other PLA-6978, Response to Follow-Up Letter on Technical Issues for Resolution Regarding Licensees Communication Submittals2013-06-0303 June 2013 Response to Follow-Up Letter on Technical Issues for Resolution Regarding Licensees Communication Submittals Project stage: Request PLA-7034, Response to Follow-Up Letter on Technical Issues for Resolution Regarding Licensees Communication Submittals2013-06-28028 June 2013 Response to Follow-Up Letter on Technical Issues for Resolution Regarding Licensees Communication Submittals Project stage: Other GNRO-2016/00010, Entergy Update to Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.32016-08-24024 August 2016 Entergy Update to Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other 2013-02-22
[Table View] |
|
---|
Category:Letter
MONTHYEARML24250A1882024-09-11011 September 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal 05000499/LER-2024-001, Supplement to Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators2024-08-29029 August 2024 Supplement to Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators IR 05000498/20243012024-08-27027 August 2024 NRC Initial Operator Licensing Examination Approval 05000498/2024301; 05000499/2024301 IR 05000498/20240052024-08-22022 August 2024 Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2024005 and 05000499/2024005) IR 05000498/20240022024-08-0909 August 2024 Integrated Inspection Report 05000498/2024002 and 05000499/2024002 IR 05000498/20240102024-08-0808 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000498/2024010 and 05000499/2024010 NOC-AE-240040, Application for Order Consenting to Direct Transfer of Licenses2024-07-31031 July 2024 Application for Order Consenting to Direct Transfer of Licenses ML24218A1462024-07-26026 July 2024 2. EPA Comments on South Texas Project Exemption Ea/Fonsi ML24207A1782024-07-25025 July 2024 Licensed Operator Positive Fitness-For-Duty Test ML24184C0832024-07-0202 July 2024 Automatic Reactor Trip and Actuation of Two of Three Emergency Diesel Generators ML24183A1742024-07-0101 July 2024 Condition Prohibited by Technical Specifications and Potential Loss of Safety Function Due to Inoperable Low Head Safety Injection Pump ML24179A3412024-06-27027 June 2024 Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24171A0112024-06-19019 June 2024 Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function IR 05000498/20244042024-06-0303 June 2024 Cyber Security Inspection Report 05000498/2024404 (Cover Letter) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24137A0882024-05-15015 May 2024 Operator Licensinq Examination Schedule Revision 3 ML24136A2842024-05-15015 May 2024 Independent Spent Fuel Storage Installation Supplement to Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance ML24136A2872024-05-15015 May 2024 Submittal of 2024 Nrc/Fema Evaluated Exercise Scenario Manual NOC-AE-240040, Operator Licensinq Examination Schedule Revision 32024-05-15015 May 2024 Operator Licensinq Examination Schedule Revision 3 ML24130A2712024-05-0909 May 2024 Re Two Essential Chilled Water Trains Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function ML24128A1572024-05-0707 May 2024 Independent Spent Fuel Storage Installation Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance IR 05000498/20240012024-05-0606 May 2024 Integrated Inspection Report 05000498/2024001 & 05000499/2024001 ML24120A3762024-04-29029 April 2024 Annual Dose Report for 2023 NOC-AE-240040, Annual Dose Report for 20232024-04-29029 April 2024 Annual Dose Report for 2023 ML24116A3032024-04-25025 April 2024 Operations Quality Assurance Plan Condition Adverse to Quality Definition Change Resulting in a Reduction in Commitment ML24116A3172024-04-25025 April 2024 Condition Prohibited by Technical Specifications Due to Inoperable Train of Essential Chilled Water ML24116A2282024-04-25025 April 2024 Annual Environmental Operating Report ML24117A1602024-04-24024 April 2024 2023 Radioactive Effluent Release Report ML24102A2452024-04-23023 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0046 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24113A3122024-04-22022 April 2024 Cycle 24 Core Operating Limits Report ML24097A0072024-04-0606 April 2024 Relief Request Number RR-ENG-4-07 – Request for an Alternative to ASME Code Case N-729-6 for Reactor Vessel Head Penetration 75 ML24092A1902024-04-0101 April 2024 Re Two Steam Generator Power Operated Relief Valves (Porvs) Inoperable Resulting in a Condition That Could Have Prevented Fulfillment of a Safety Function NOC-AE-240040, Financial Assurance for Decommissioning - 2024 Update2024-03-28028 March 2024 Financial Assurance for Decommissioning - 2024 Update ML24088A3022024-03-28028 March 2024 Financial Assurance for Decommissioning - 2024 Update ML24081A3972024-03-21021 March 2024 Response to Request for Additional Information for Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24080A2902024-03-19019 March 2024 Nuclear Liability Certificates of Insurance ML24066A2002024-03-0606 March 2024 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes ML24079A1312024-03-0505 March 2024 Nuclear Insurance Protection ML24060A1742024-02-28028 February 2024 Submittal of Annual Fitness for Duty Performance Report for 2023 IR 05000498/20230062024-02-28028 February 2024 Annual Assessment Letter for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2023006 and 05000499/2023006) IR 05000498/20240132024-02-27027 February 2024 Design Basis Assurance Inspection (Programs) Commercial Grade Dedication IR 05000498/2024013 and 05000499/2024013 ML24022A2252024-02-20020 February 2024 Issuance of Amendment Nos. 227 and 212 to Authorize the Revision of the Alternative Source Term Dose Calculation ML24050A0082024-02-19019 February 2024 Evidence of Financial Protection ML24045A0922024-02-16016 February 2024 Response to STP FOF Move Letter (2024) ML24017A2972024-02-15015 February 2024 Project Manager Assignment NOC-AE-240040, Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation2024-02-0808 February 2024 Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation ML24039A1112024-02-0808 February 2024 Operator Licensing Examination Schedule Revision 2 ML24039A1602024-02-0808 February 2024 Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation ML24033A3002024-02-0707 February 2024 Summary of Regulatory Audit Regarding a Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ML24038A3342024-02-0707 February 2024 Change to South Texas Project Electric Generating Station (Stepgs) Emergency Plan 2024-09-11
[Table view] |
Text
Nuclear Operating Company South Tebas Project E1ecttc Generating Station PO. Box 289 Wadsworth.
Texas 77483 _June 4, 2012 NOC-AE-12002859 10 CFR 50.54(f)U. S. Nuclear Regulatory Commission Attention:
Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 South Texas Project Units 1 & 2 Docket Nos. STN 50-498, STN 50-499 90-Day Response to Request for Information Pursuant to 10 CFR 50.54(f)Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insiqhts from the Fukushima Dai-ichi Accident
References:
- 1. Letter, Eric Leeds to E. D. Halpin, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," dated March 12, 2012 (ML12053A340)
- 2. Letter, D.W. Rencurrel to NRC, "60-Day Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident", dated May 9, 2012 On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Reference 1.Enclosure 5 of Reference 1 contained specific Requested Actions and Requested Information associated with Recommendation 9.3 for Emergency Preparedness (EP)programs.
In accordance with 10 CFR 50.54, "Conditions of licenses," paragraph (f), addressees were requested to submit a written response to the information requests.The letter also provided requested due dates for written responses.
In accordance with the Reference 1, STP Nuclear Operating Company submitted an alternative course of action for providing the requested information in Reference
- 2. The alternative course of action included revised information due dates and the basis for those dates. As described in our alternative course of action, Attachment 1 to this letter transmits the responses to the following information requests:
Enclosure 5, communications request #2, staffing requests #3, #4, and #5.The only commitments in this letter are summarized in Attachment 2.STI33553629 NOC-AE-12002859 Page 2 of 3 If there are any questions regarding this letter, please contact Robyn Savage at (361) 972-7438 or me at (361) 972-7867.I declare under penalty of perjury that the foregoing is true and correct.Executed on: 41/2 .1..D. ncurrel Chief Nuclear Officer Attachments:
- 1. Response to Request for Information Regarding Recommendation
9.3 Related
to Communications and Staffing 2. List of Commitments rds NOC-AE-12002859 Page 3 of 3 cc: (paper copy)(electronic copy)Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 1600 East Lamar Boulevard Arlington, TX 76011-4511 Balwant K. Singal Senior Project Manager U.S. Nuclear Regulatory Commission One White Flint North (MS 8 B1)11555 Rockville Pike Rockville, MD 20852 Senior Resident Inspector U. S. Nuclear Regulatory Commission P. 0. Box 289, Mail Code: MN1 16 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704 Eric Leeds Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North (MS 13 H 16M)11555 Rockville Pike Rockville, MD 20852 A. H. Gutterman, Esquire Morgan, Lewis & Bockius LLP Balwant K. Singal U. S. Nuclear Regulatory Commission John Ragan Chris O'Hara Jim von Suskil NRG South Texas LP Kevin Polio Richard Pena City Public Service Peter Nemeth Crain Caton & James, P.C.C. Mele City of Austin Richard A. Ratliff Texas Department of State Health Services Alice Rogers Texas Department of State Health Services Attachment 1 NOC-AE-12002859 Page 1 of 2 Response to Request for Information Regarding Recommendation
9.3 Related
to Communications and Staffing Communications NRC Request #2 -Describe any interim actions that have been taken or are planned to be taken to enhance existing communications systems power supplies until the communications assessment and the resulting actions are complete.STPNOC Actions TakenlActions Planned 1. STPNOC has purchased 2 additional satellite phones and 4 spare batteries with chargers for each Unit. These satellite phones will enhance the ability to communicate with offsite organizations.
Procedures will be revised to inventory and check the functionality of the additional satellite phones, batteries, and chargers.2. STPNOC has purchased 6 two-way radio batteries with chargers for each Unit. These batteries enhance onsite communications by increasing the length of time the two-way radios can be used by plant operations.
Procedures will be revised to inventory and check the functionality of the dedicated radio batteries and chargers.3. STPNOC has purchased 8 sound powered headsets for each Unit. The headsets enhance communications within the plant during a prolonged station blackout.
The headsets will supplement existing headsets.
They will be pre-staged in areas important to operations during this event. Operators will be able to easily locate the headsets and communicate with the control room while performing critical tasks. Procedures will be revised to inventory and check the functionality of the sound powered headsets.4. STPNOC has purchased 6 diesel powered generators that could be used to provide power to battery chargers for satellite phones and two-way radio batteries.
The generators will be included in the Flexible Coping strategies (FLEX) being developed for NRC Order EA-12-049 (ML12054A735).
Actions Planned Estimated Condition Completion Date Report 1. Procedures will be revised to inventory and check 12/31/12 12-11657-13 the functionality of the additional satellite phones, batteries, and chargers.2. Procedures will be revised to inventory and check 12/31/12 12-11657-13 the functionality of the dedicated radio batteries and chargers.3. Procedures will be revised to inventory and check 12/31/12 12-11657-13 the functionality of the sound powered headsets Staffing Attachment 1 NOC-AE-1 2002859 Page 2 of 2 Response to Request for Information Regarding Recommendation
9.3 Related
to Communications and Staffing NRC Request #3 -Identify how the augmented staff would be notified given degraded communications capabilities.
STPNOC Actions Taken/Actions Planned 1. Expectations will be communicated to ERO members to automatically respond to a designated staging area when made aware of a large scale external event (e.g. by direct observation, media reports, word-of-mouth, etc). These expectations will be communicated to the ERO by July 12, 2012. Procedures will be revised by December 31, 2012.NRC Request #4 -Identify the methods of access (e.g., roadways, navigable bodies of water and dockage, airlift, etc.) to the site that are expected to be available after a widespread large scale natural event.STPNOC Actions Taken/Actions Planned 1. STP has multiple roadways to access the site: a. From the West -Highway 521 b. From the North -Farm to Market (FM) 1468 c. From the East -Highway 521 2. STP's owner controlled area is located on the west bank of the Colorado River. The river can be used to transport personnel and small equipment by boat from surrounding areas to the site.3. Helicopters can be used to transport personnel to the site.4. STP has road clearing equipment and a boat onsite which may be available after a large scale event.5. STPNOC has an agreement with Matagorda County to provide local resources upon request or state and federal resources if there is a disaster declaration.
These resources include road clearing equipment, off-road and high water vehicles, boats and helicopters.
NRC Request #5 -Identify any interim actions that have been taken or are planned prior to the completion of the staffing assessment.
STPNOC Actions Taken/Actions Planned 1. STPNOC is not planning on supplementing staff at this time.
Attachment 2 NOC-AE-12002859 Page 1 of 1 List of Commitments The following table identifies those actions committed to by the STP Nuclear Operating Company (STPNOC) in this document.
Any statements in this submittal with the exception of those in the table below are provided for information purposes and are not considered commitments.
Please direct questions regarding these commitments to Robyn Savage at (361)972-7438.Commitment Scheduled Condition Due Date Report 1. ERO members will be advised of the expectation to 7/12/12 12-11657-14 automatically respond to a designated staging area when made aware of a large scale external event (e.g. by direct observation, media reports, word-of-mouth, etc).2. Procedures will be revised to include the expectation 12/31/12 12-11657-15 that ERO members automatically respond to a designated staging area when made aware of a large scale external event (e.g. by direct observation, media reports, word-of-mouth, etc).