(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
|
---|
Category:Letter
MONTHYEARIR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 ML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23352A3692023-12-18018 December 2023 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23334A2342023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 2024-02-06
[Table view] |
Text
VIRGINIA ELECTRIC::
AND POWER COMPANY RICHMOND, VIRGINIA 23261 September 10, 2018 U.S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, D.C. 20555-0001 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION ISFSI SURRY POWER STATION ISFSI Serial No.: NRA/MAE: Docket Nos.: License Nos.: 18-355 RO 72-2/16 SNM-2501/2507 TEMPORARY MODIFICATION OF INTERIM COMPENSATORY MEASURES FOR ORDER EA-02-104 On October 16, 2002, the NRC issued Orders EA-02-104 (the Orders) that modified the specific licenses for North Anna and Surry Power Stations' Independent Spent Fuel Storage Installations (ISFSls).
These Orders required compliance with the specified interim safeguards and security compensatory measures.
Virginia Electric and Power Company (Dominion Energy Virginia) initially responded to the October 16, 2002 Order in letters dated November 1, 2002 (Serial Nos.02-646 and 02-64 7 for North Anna and Surry Power Stations, respectively).
As part of preparations for the arrival of Hurricane Florence, we have assessed our compliance strategy for the Orders and determined that due to presently predicted weather conditions and the concern for security personnel safety, Dominion Energy Virginia may need to temporarily modify our implementation of those interim compensatory measures (IC Ms) C.1.b, C.3.a(1 ), and C.3.d. Alternate security measures will be initiated when possible based on weather limitations and personnel safety concerns.
Dominion Energy Virginia specifically requests a one-time temporary modification of the implementation of our response to the identified ICMs. This one-time temporary modification will be used as necessary to address the effects of weather and for a period of time corresponding to abnormally high wind conditions and rain due to the passing of Hurricane Florence.
This request is necessary to protect security personnel from hazards associated with the weather conditions during the hurricane.
Any suspension of security measures due to this weather-related situation will be reported and documented in accordance with the provisions of 10 CFR 73.71.
'*--\,, Serial No.18-355 Docket Nos. :72-2/16 Page 2 of 3 If you have any questions, please contact Ms. Margaret A. Earle at (804) 273-2768.
Sincerely, JJ?flz--6 Gerald T. Bischof VICKI L. HULL NOTARY PUBLIC REG. # 140542 COMMONWEALTH OF VIRGINIA MY COMMISSLON EXPIRES 5131/2022 Senior Vice President
-Nuclear Operations
& Fleet Performance COMMONWEA~
TH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Gerald T. Bischof who is Senior Vice President
-Nuclear Operations
& Fleet Performance of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowlrd belief Acknowledged before me this /tl_!3ay of\ /;h,1r,/.Jer, 2018. My Commission Expires: ,I/tty 3~ m. ;t;..2--/;L/L_
Notary Public Commitments made by this letter: None cc: U. S. Nuclear Regulatory Commission, Region II Attn.: Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257
- Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Ms. Yen-Ju Chen NRC Senior Project Manager U. S. Nuclear Regulatory Commission Mail Stop 4B34 Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738
._, Mr. Christian Jacobs NRC Project Manager U.S. Nuclear Regulatory Commission Mail Stop 4872 Two White Flint North 11545 Rockville Pike Rockville, MD 20852-2738 Ms. K. R. Cotton Gross NRC Project Manager Surry U. S. Nuclear Regulatory Commission Mail Stop 08 G-9A One White Flint North 11'555 Rockville Pike Rockville, MD 20852-2738 Mr. James R. Hall NRC Senior Project Manager North Anna U. S. Nuclear Regulatory Commission Mail Stop 08 B1-A One White Flint North 11555 Rockville Pike . Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station Serial No.18-355 Docket Nos.:72-2/16 Page 3 of 3