Annual Environ Operating Rept for 1989.
ML17305A740
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 12/31/1989
From: CARPENTER M L
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
Shared Package
ML17305A739 List:
References
NUDOCS 9005100136
Download: ML17305A740 (10)


Text

ARIZONA PUBLIC SERVICE COMPANY PALO VERDE NUCLEAR GENERATING STATION ANNUAL ENVIRONMENTAL OPERATING REPORT FOR 1989 PREPARED BY: MANNIE L.CARPENTER PVNGS ENVIRONMENTAL LICENSING APRIL 1990 9005100136 900480"PDR ADOCK 0500052S R PDC If TABLE OF CONTENTS I.Introduction II~III IV+V VI.References Environmental Monitoring Summaries and Plant Design and Operation Changes EPP Noncompliances Nonroutine Reports Page 1 Analysis Page 2 Page 2 Page 2 Page 3 Page 3 1 I PVNGS 1989 Annual Environmental Operating Rep'ort Page 1 I.INTRODUCTION I The Palo Verde Nuclear Generating Station (PVNGS)is located in Maricopa County, Arizona, approximately 50 miles west of the Phoenix metropolitan

'rea.The PVNGS site comprises approximately 4050 acres..Site eleva-tions range from 890 feet above me'an sea level at the southern boundary to 1030 feet above mean sea level at the northern boundary.The station consists of three pressurized water reactor electrical generating units with a nominal generating capacity of 1270 MWe per unit.PVNGS Units 1, 2 and 3 were all in commercial operation at sometime during 1989.'PVNGS was issued low power operating licenses NPF-34, NPF-46 and NPF-65 for Units 1, 2 and 3, respectively, by the United States Nuclear Regulatory Commission (NRC)on December 31, 1984, December 9, 1985 and March 25, 1987, respectively.

The Unit 1 full power operating license NPF-41 was issued June 1, 1985.The Unit 2 full power operating license NPF-51 was issued April 24, 1986.The Unit 3 full power operating license NPF-74 was issued November 25, 1987.Appendix B to these operating licenses is entitled the"Environmental Protection Plan (Non-Radiological)".

The Environmental Protection Plans (EPP)of each of the current operating licenses are identical.

The EPP has as its stated purpose the"protection of environmental values during construction and operation of the nuclear facility".

In conjunction with this general purpose, the EPP also has the principal objectives to: "(1)Verify that the station is operated in an environmentally acceptable manner, as established by the FES[Final Environ-mental Statement]

and other NRC environmental impact assess-ments.(2)Coordinate NRC requirements and maintain consistency with other Federal, State and local requirements for environmen-tal protection.

(3)Keep NRC informed of the environmental effects of facility construction and operation and of actions taken to control those effects".This report is intended to satisfy the requirements of section 5.4.1 of the EPP regarding the submittal of an Annual Environmental Operating Report to the Commission.

This report describes the activities during the year 1989 related to the PVNGS EPP.For purposes of this report, references to the EPP shall be considered to be the EPP of NPF-41, NPF-51 or NPF-74 unless otherwise specified.

l

'PVNGS 1989 Annual Environmental Operating Report Page 2 II.ENVIRONMENTAL MONITORING SUMMARIES AND ANALYSIS A.Cultural Resources IJ Section 4.2.1 of the EPP requires that an archaeological survey be performed when final al'ignment of the PVNGS-to-Saguaro transmis-sion line is completed.

As of the date of this report, plans for this transmission line have been placed on indefinite hold.Therefore, there has been no,further activity in this area of the EPP.B.Terrestrial Ecology Monitoring I Section 4.2.2.of the EPP requires that the provisions of the Salt Deposition and Impact Monitoring Plan be implemented by the onset of commercial operation of the first unit.The EPP further stipulates that the monitoring plan continue'or a minimum of three full years after the onset of operation of all three units or until shown to not be necessary.

The enclosed report, Annual Report for PVNGS Salt Deposition Monitoring Program, January-December 1989 (NUS-5241) describes the results of the salt drift monitoring activities during 1989.Results for the various media sampled in the 1989 PVNGS drift monitoring program have been compared with corresponding pre-operational values.There are clear indications of the effects of cooling tower emissions, particularly in the deposition samples from close-in monitoring.

Monitoring also detected statistically significant changes in some ions present in deposition, soil and plant tissue samples at one offsite control location about 19 miles west-northwest of the plant, which appears to be unrelated to plant operation.

Operation during 1989 does not appear to have extended the range of influence of the PVNGS cooling tower drift emissions beyond that observed previously.

The deposition rates measured offsite are much too low to produce any significant adverse environmental impacts.III.PLANT DESIGN AND OPERATION CHANGES Section 3.1 of the.EPP allows changes in station design or operation or the performance of tests or experiments affecting the environment provided that such changes, tests or experiments do not, constitute an unreviewed environmental question and do not require a change to the EPP.Changes, tests or experiments in which all measurable non-radiological effects are confined to the onsite areas previously disturbed during site preparation and plant construction or in which the environment is not affected are exempt from the evaluation and reporting requirements of Section 3.1.Section 3.2 of the EPP also exempts changes, tests, or experiments which are required to comply with other Federal State or local environmental regulations.

There were no plant changes or tests requiring evaluation for unreviewed environmental questions during 1989.

I PVNGS 1989 Annual Environmental Operating Report Page 3 IV.EPP NONCOMPLIANCES There were no instances of noncompliance with the'PP identified during 1989.V.NONROUTINE REPORTS There were no nonroutine reports required by Section 5.4.2 of the EPP submitted during 1989.VI.REFERENCES NUS-5241, NUS Corporation, Annual Report for PVNGS Salt Deposition Monitoring Program, January-December 1989, April 1990.AEOR89.MLC f"A\/I g t