MONTHYEARML24036A0162024-02-0101 February 2024 NRC Email - Acknowledge and Accept the Indian Point Energy Center Request to Be Removed from NRC Headquarters Operation Officer (Hoo) Morning Authentication Code Calls ML23341A2002023-12-0707 December 2023 Email - Indian Point Energy Center Generating Units 1, 2, and 3 – Implementation Notice of Amendment No. 67, 300 and 276 to Independent Spent Fuel Storage Installation Only Emergency Plan (Ioep) ML23332A0802023-11-0808 November 2023 – Email from State of New York on the Revised License Amendment for Indian Point Energy Center ISFSI Only Emergency Plan ML23331A9542023-11-0808 November 2023 Email - State of New York Comments on the Revised License Amendment for Indian Point Unit 2 and 3 Technical Specification Changes Reflecting Permanent Removal of Spent Fuel ML23325A1632023-11-0808 November 2023 – State of New York Comments on the Revised License Amendment for Indian Point Unit 2 and 3 Technical Specification Changes Reflecting Permanent Removal of Spent Fuel ML23144A3382023-05-25025 May 2023 Dawn Giambalvo of Jersey City, New Jersey Email Against Treated Water Release from Indian Point Site ML23144A3422023-05-25025 May 2023 Peter Duda of Pearl River, New York Email Against Treated Water Release from Indian Point Site ML23144A3452023-05-25025 May 2023 Adam Kahn of Monsey, New York Email Against Treated Water Release from Indian Point Site ML23144A3502023-05-25025 May 2023 Dan Kwilecki of Montebello, New York Email Against Treated Water Release from Indian Point Site ML23144A3392023-05-25025 May 2023 David Morris of New City, New York Email Against Treated Water Release from Indian Point Site ML23144A3442023-05-25025 May 2023 Peggy Kurtz of Rockland County, New York Email Against Treated Water Release from Indian Point Site ML23136B1622023-05-15015 May 2023 – Town of North Salem, County of Westchester, New York Board Resolution Letter Regarding Treated Water Release from Indian Point Site ML23109A0632023-04-17017 April 2023 Email Acceptance Review for IP2 and IP3 Amended Facility License and Technical Specification to Reflect Permanent Removal of Spent Fuel from Spent Fuel Pits ML23055A1112023-02-23023 February 2023 Alyse Peterson Email- NYSERDA No Comments on Indian Point Unit 2 - Regarding Holtec License Amendment Request to Revise Permanently Defueled Technical Specifications and Staffing Requirements with Spent Fuel Transfer to ISFSI (Dockets 50-24 ML23049A0032023-02-14014 February 2023 – NRC Acceptance Email to Holtec for License Amendment Request for Approval of New ISFSI-Only Emergency Plan and Associated EAL Scheme ML22313A1682022-11-0909 November 2022 NRC Response to Updates to the Proposed Amended IP2 Master Trust ML22308A0912022-11-0303 November 2022 Email Acknowledgement for IP2 and IP3 Amended Facility License and Technical Specification to Reflect Permanent Removal of Spent Fuel from Spent Fuel Pits ML22276A1642022-09-29029 September 2022 New York State Revised Draft EA Response E-Mail ML22271A8492022-09-28028 September 2022 E-Mail Transmitting Revised Indian Point Exemption Draft EA ML22269A3452022-09-22022 September 2022 Email Objection to Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2, EPID L-2022-LLA-0072 ML22259A1992022-09-0202 September 2022 Acceptance for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage ML22265A0142022-08-31031 August 2022 Email Acknowledgement for Amended and Restated Holtec IP3 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 3 ML22242A2592022-08-19019 August 2022 E-mail from K. Sturzebecher, NRC, to B. Noval, HDI, Acknowledgement for Amended and Restated Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2 ML22228A1332022-08-0909 August 2022 Acknowledgement for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage ML22215A0432022-08-0101 August 2022 E-Mail Transmitting NYS NSA Exemption Comments & Draft EA Review Completion ML22208A0292022-07-19019 July 2022 E-Mail Transmitting Indian Point Exemption Draft EA ML22168A0072022-06-16016 June 2022 Acceptance Review for License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML22112A0102022-04-21021 April 2022 Acceptance Review: Request for Exemption from 10 CFR 50.54(w)(1) Concerning Indian Point Energy Center Onsite Property Damage Insurance ML22112A0122022-04-21021 April 2022 Acceptance Review: Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance for Indian Point Energy Center ML22103A2432022-04-13013 April 2022 E-mail - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center ML22104A0342022-04-13013 April 2022 E-mail from Z. Cruz, NRC to J. Fleming, Holtec - Request for Additional Information Related to Request for Exemption from Portions of 10 CFR 50.47 and Part 50 Appendix E for Indian Point Energy Center ML22038A2572022-02-0707 February 2022 E-mail from Z. Cruz, NRC, to J. Fleming, HDI - Acceptance Review: License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme to Address Permanently Defueled Condition for Indian Point Energy Center ML22035A1862022-02-0404 February 2022 E-mail to J. Fleming, Holtec, from Z. Cruz Perez, NRC - Acceptance Review: Exemption Requests from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E, Section IV for Indian Point Energy Center ML22028A1032022-01-28028 January 2022 E-mail Dated 1/28/2022, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device ML22038A1592022-01-24024 January 2022 NRR E-mail Capture - (External_Sender) 2021 IPEC Annual Sturgeon Impingement Report ML22006A0442022-01-0505 January 2022 Email from Z Cruz to J Fleming Request for Additional Information - HDI Indian Point Post-Shutdown Decommissioning Activities Report ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) ML21335A3692021-12-0101 December 2021 Acceptance Review: Indian Point Energy Center - Exemption Request from 10 CFR Part 20 App G Section Iii.E ML21266A2972021-08-18018 August 2021 8/18/2021 E-mail from H. Specter to R. Guzman Public Comments to NRC, Indian Point Post-Shutdown Decommissioning Activities Report Public Meeting on July 29, 2021 ML21225A5012021-08-0909 August 2021 Email from NRC to the Shinnecock Indian Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21224A3032021-08-0909 August 2021 Email from NRC to the Mashantucket Pequot Tribe of Connecticut Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A6142021-08-0909 August 2021 Email from NRC to the Tuscarora Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5682021-08-0909 August 2021 Email from NRC to the Stockbridge-Munsee Community Band of Mohican Indians Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A4252021-08-0909 August 2021 Email from NRC to the Oneida Nation of Wisconsin Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A3142021-08-0606 August 2021 Email from NRC to the Oneida Indian Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A4402021-08-0606 August 2021 Email from NRC to the Onondaga Nation of Wisconsin Announcing the IPEC PSDAR Meeting on August 18, 2021 ML21225A5352021-08-0606 August 2021 Email from NRC to the Tonawanda Band of Seneca Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5462021-08-0606 August 2021 Email from NRC to the St. Regis Mohawk Tribe Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21266A2942021-07-25025 July 2021 E-mail from Paul Blanch to NRC (N. Sheehan, D. Screnci) Public Comments to NRC, Indian Point Post-Shutdown Decommissioning Activities Report Public Meeting, July 29, 2021 ML21197A2002021-07-16016 July 2021 (E-mail 7/16/2021) NRC Staff Assessment and RAI Closeout HDI Fleet Decommissioning Quality Assurance Program and Indian Point Energy Center Quality Assurance Program Manual 2024-02-01
[Table view] |
Text
1 IPRenewal NPEmails From: Kimberly Green Sent: Thursday, May 01, 2008 11:16 AM To: STROUD, MICHAEL D Cc: dtyner@entergy.com
Subject:
Advanced E-Copy of RAI letter on FP and Elastomers Attachments:
ML0811504350 RAI on FP and Elastomers.docMike, Attached is an advanced copy of the RAI letter on fire protection and elastomers. The formal paper copy is in the mail.
KimberlyGreenSafetyPM(301)4151627kimberly.green@nrc.gov Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 86 Mail Envelope Properties (Kimberly.Green@nrc.gov20080501111500)
Subject:
Advanced E-Copy of RAI letter on FP and Elastomers Sent Date: 5/1/2008 11:15:32 AM Received Date: 5/1/2008 11:15:00 AM From: Kimberly Green Created By: Kimberly.Green@nrc.gov Recipients: "dtyner@entergy.com" <dtyner@entergy.com> Tracking Status: None "STROUD, MICHAEL D" <MSTROUD@entergy.com>
Tracking Status: None Post Office: Files Size Date & Time MESSAGE 261 5/1/2008 11:15:00 AM ML0811504350 RAI on FP and Elastomers.doc 105466 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received:
April 29, 2008
Vice President, Operations
Entergy Nuclear Operations, Inc.
Indian Point Energy Center
450 Broadway, GSB
P.O. Box 249
Buchanan, NY 10511-0249
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE
RENEWAL APPLICATION - METAL ENCLOSED BUSES AND FIRE
PROTECTION
Dear Sir or Madam:
By letter dated April 23, 2007, as supplemented by letters dated May 3, 2007, and June 21, 2007, Entergy Nuclear Operations, Inc., submitted an application pursuant to Title 10 of the
Code of Federal Regulations Part 54, to renew the operating licenses for Indian Point Nuclear Generating Unit Nos. 2 and 3, for review by the U.S. Nuclear Regulatory Commission (NRC or
the staff). The staff is reviewing the information contained in the license renewal application
and has identified, in the enclosure, areas where additional information is needed to complete
the review. Further requests for additional information may be issued in the future.
Items in the enclosure were discussed with Mr. Robert Walpole, and a mutually agreeable date
for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-1627 or via e-mail at kimberly.green@nrc.gov. Sincerely, /RA/
Kimberly Green, Safety Project Manager
Projects Branch 2
Division of License Renewal
Office of Nuclear Reactor Regulation
Docket Nos. 50-247 and 50-286
Enclosure:
As stated
cc w/encl: See next page
ML081150435 OFFICE PM:RPB2:DLR LA:DLR BC:RPB2:DLR NAME KGreen IKing RFranovich (JRowley for)
DATE 04/29/08 04/29/08 0429/08 Letter to M. Balduzzi from K. Green, dated April 29, 2008
DISTRIBUTION
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE
RENEWAL APPLICATION - METAL ENCLOSED BUSES AND FIRE
PROTECTION HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr
RidsNrrDlrRpb1
RidsNrrDlrRpb2
RidsNrrDlrRer1
RidsNrrDlrRer2
RidsNrrDlrRerb
RidsNrrDlrRpob
RidsNrrDciCvib
RidsNrrDciCpnb
RidsNrrDraAfpb
RidsNrrDraAplb
RidsNrrDeEmcb
RidsNrrDeEeeb
RidsNrrDssSrxb
RidsNrrDssSbpb RidsNrrDssScvb
RidsOgcMailCenter
RFranovich EDacus, OCA BPham GMeyer, RI KGreen MMcLaughlin, RI NIqbal NMcNamara, RI RAuluck DScrenci, RI OPA KChang NSheehan, RI OPA MKowal PCataldo, RI JBoska CHott, RI STurk, OGC DJackson, RI LSubin, OGC BWelling, RI BMizuno, OGC RConte, RI SBurnell, OPA ECobey, RI DMcIntyre, OPA MCox, RI
TMensah, OEDO
DNguyen Indian Point Nuclear Generating Units 2 and 3 cc:
Senior Vice President
Entergy Nuclear Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Vice President Oversight
Entergy Nuclear Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Senior Manager, Nuclear Safety &
Licensing
Entergy Nuclear Operations, Inc.
P.O. Box 31995
Jackson, MS 39286-1995
Senior Vice President and COO
Entergy Nuclear Operations, Inc.
440 Hamilton Avenue
White Plains, NY 10601
Assistant General Counsel
Entergy Nuclear Operations, Inc.
440 Hamilton Avenue
White Plains, NY 10601
Manager, Licensing
Entergy Nuclear Operations, Inc.
Indian Point Energy Center
450 Broadway, GSB
P.O. Box 249
Buchanan, NY 10511-0249
Mr. Paul D. Tonko
President and CEO
New York State Energy Research and
Development Authority
17 Columbia Circle
Albany, NY 12203-6399
Mr. John P. Spath
New York State Energy, Research and
Development Authority
17 Columbia Circle
Albany, NY 12203-6399
Mr. Paul Eddy New York State Department
of Public Service
3 Empire State Plaza
Albany, NY 12223-1350
Regional Administrator, Region I
U.S. Nuclear Regulatory Commission
475 Allendale Road
King of Prussia, PA 19406
Senior Resident Inspector's Office
Indian Point 2
U.S. Nuclear Regulatory Commission
P.O. Box 59
Buchanan, NY 10511
Senior Resident Inspector's Office
Indian Point 3
U.S. Nuclear Regulatory Commission
P.O. Box 59
Buchanan, NY 10511
Mr. Charles Donaldson, Esquire
Assistant Attorney General
New York Department of Law
120 Broadway
New York, NY 10271
Mr. Raymond L. Albanese
Four County Coordinator
200 Bradhurst Avenue
Unit 4 Westchester County
Hawthorne, NY 10532
Mayor, Village of Buchanan
236 Tate Avenue
Buchanan, NY 10511
Mr. William DiProfio
PWR SRC Consultant
48 Bear Hill Road
Newton, NH 03858
Indian Point Nuclear Generating Units 2 and 3 cc:
Mr. Garry Randolph
PWR SRC Consultant
1750 Ben Franklin Drive, 7E
Sarasota, FL 34236
Mr. William T. Russell
PWR SRC Consultant
400 Plantation Lane
Stevensville, MD 21666-3232
Mr. Jim Riccio
Greenpeace
702 H Street, NW
Suite 300
Washington, DC 20001
Mr. Phillip Musegaas
Riverkeeper, Inc.
828 South Broadway
Mr. Mark Jacobs
IPSEC 46 Highland Drive
Garrison, NY 10524
Mr. R. M. Waters
Technical Specialist Licensing
450 Broadway
P.O. Box 0249
Buchanan, NY 10511-0249
Mr. Sherwood Martinelli
351 Dyckman
Peekskill, NY 10566
Ms. Susan Shapiro, Esq.
21 Perlman Drive
Spring Valley, NY 10977
Tarrytown, NY 10591
John Sipos
Assistant Attorney General
New York State Department of Law
Environmental Protection Bureau
The Capitol
Albany, NY 12224
Robert Snook Assistant Attorney General
Office of the Attorney General
State of Connecticut
55 Elm Street
P.O. Box 120
Hartford, CT 06141-0120
Ms. Kathryn M. Sutton, Esq.
Morgan, Lewis & Bockius, LLP
1111 Pennsylvania Avenue, NW
Washington, DC 20004
Mr. Paul M. Bessette, Esq.
Morgan, Lewis & Bockius, LLP
1111 Pennsylvania Avenue, NW
Washington, DC 20004
Mr. Martin J. O'Neill, Esq.
Morgan, Lewis & Bockius, LLP
1111 Pennsylvania Avenue, NW
Washington, DC 20004
The Honorable Nita Lowey
222 Mamaroneck Avenue, Suite 310
White Plains, NY 10605
Joan Leary Matthews
Senior Counsel for Special Projects
Office of General Counsel
NYS Department of Environmental
Conservation
625 Broadway
Albany, NY 12233-5500 INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION DRAFT REQUEST FOR ADDITIONAL INFORMATION METAL ENCLOSED BUSES AND FIRE PROTECTION RAI 3.6.2.3-1 License renewal application (LRA), Table 3.6.1, under Item Number 3.6.1-10, "Metal enclosed
bus - Enclosure assemblies," states that the only elastomers are access door gaskets and are
considered consumables. NUREG-1801, Volume 2, Item VI.A-12, identifies elastomers as a commodity type that requires an aging management re view (AMR). Confirm that for in-scope metal enclosed buses, there are no other elastomers or gaskets other than the access door
gaskets. For access door elastomers, provide a technical justification of why these components
are excluded from an AMR.
RAI 3.0.3.2.7-2 In response to RAI 3.0.3.2.7-1 in a letter dated March 12, 2008, Entergy states that fire stops (penetration seals) are visually inspected at least once every seven operating cycles (15%
every 24 months). During an audit, the NRC staff reviewed bases documents (for Indian Point
Unit 3) associated with the fire protection AMP. One of the bases documents states that 15% of
fire seals located in fire barriers are demonstrated to be operable by visual inspection on a
frequency of 24 months. However, for those penetration seals that are inaccessible, the
frequency of inspection is given as "not required." Justify the lack of visual inspections of
inaccessible penetration seals.
ENCLOSURE