Semantic search
Jump to navigation
Jump to search
Issue date | Title | |
---|---|---|
IR 05000285/2015005 | 1 September 2015 | Mid-Cycle Assessment Letter for Fort Calhoun Station (Report 05000285/2015005) |
IR 05000285/2015006 | 2 March 2016 | Annual Assessment Letter for Fort Calhoun Station (Report 05000285/2015006) |
IR 05000285/2016005 | 12 September 2016 | Errata for Mid-Cycle Assessment Letter for Fort Calhoun Station (Report 05000285/2016005) |
IR 05000285/2017001 | 8 May 2017 | NRC Inspection Report 05000285/2017001 and 05000285/2017008 |
LIC-12-0035, Omaha Public Power District'S Answer to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 30 March 2012 | Omaha Public Power District'S Answer to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
LIC-12-0155, OPPD Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 27 October 2012 | OPPD Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
LIC-13-0011, Spent Fuel Pool Instrumentation Overall Integrated Plan | 28 February 2013 | Spent Fuel Pool Instrumentation Overall Integrated Plan |
LIC-13-0124, First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation | 28 August 2013 | First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
LIC-13-0144, Omaha Public Power District Response to NRC Request for Additional Information Regarding the Overall Integrated Plan in Response to Order EA-12-051 Reliable Spent Fuel Pool Instrumentation | 18 October 2013 | Omaha Public Power District Response to NRC Request for Additional Information Regarding the Overall Integrated Plan in Response to Order EA-12-051 Reliable Spent Fuel Pool Instrumentation |
LIC-14-0023, Omaha Public Power District'S Second Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation | 24 February 2014 | Omaha Public Power District'S Second Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
LIC-14-0098, License Amendment Request 14-06 to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors | 26 December 2014 | License Amendment Request 14-06 to Adopt Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors |
LIC-15-0024, Fourth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation | 27 February 2015 | Fourth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
LIC-15-0096, Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation | 19 August 2015 | Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
LIC-15-0113, Response to Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation | 28 September 2015 | Response to Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation |
LIC-16-0009, Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation | 26 February 2016 | Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
LIC-16-0048, Request for Relaxation of March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool Instrumentation (EA-12-049.. | 12 August 2016 | Request for Relaxation of March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool Instrumentation (EA-12-049.. |
LIC-16-0061, Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | 12 August 2016 | Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
LIC-16-0062, Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation | 12 August 2016 | Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
LIC-16-0078, Revision to Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Flood Hazard Reevaluation Report | 14 September 2016 | Revision to Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Flood Hazard Reevaluation Report |
LIC-16-0080, Omaha Public Power District Request to Rescind the March 12, 2012, NRC Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) | 9 September 2016 | Omaha Public Power District Request to Rescind the March 12, 2012, NRC Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051) |
LIC-16-0095, Transmittal of Revised Overall Integrated Plan for Fuel Permanently Removed from the Reactor Vessel to the Spent Fuel Pool in Response to Requirements for Mitigation Strategies for Beyond Design Basis External Events | 31 October 2016 | Transmittal of Revised Overall Integrated Plan for Fuel Permanently Removed from the Reactor Vessel to the Spent Fuel Pool in Response to Requirements for Mitigation Strategies for Beyond Design Basis External Events |
LIC-17-0018, Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | 24 February 2017 | Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
ML12054A679 | 12 March 2012 | Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
ML12056A044 | 12 March 2012 | Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status |
ML13235A168 | 23 August 2013 | Draft Request for Additional Information Email, Overall Integrated Plan in Response to 3/12/2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) |
ML13317A583 | 25 November 2013 | Interim Staff Evaluation and Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML13339A724 | 5 December 2013 | Meeting Summary Slides |
ML14055A412 | 24 February 2014 | Omaha Public Power District'S Second Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
ML14065A253 | 5 March 2014 | Summary of Category 1 Public Meeting with Omaha Public Power District to Discuss Status of Oversight Activities at Fort Calhoun Station |
ML14083A620 | 26 March 2014 | Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 |
ML14143A289 | 23 May 2014 | May 13, 2014 Summary of Meeting with Omaha Public Power District Presented the Status of Inspection Manual Chapter 0350 Oversight Activities at Fort Calhoun Station |
ML14237A574 | 25 August 2014 | Third Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
ML15288A005 | 15 December 2015 | Issuance of Amendment No. 285, Adopt Emergency Action Level Scheme Pursuant to Nuclear Energy Institute (NEI) 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors |
ML16064A077 | 8 March 2016 | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 |
ML16179A373 | 5 July 2016 | Audit Report for Orders EA 12-049 and EA 12-051 |
ML16237A038 | 31 August 2016 | Mid-Cycle Assessment Letter for Fort Calhoun Station (Report 05000285/2016005) |
ML16320A287 | 8 December 2016 | Rescission of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
ML17263B198 | 11 December 2017 | Letter and Safety Evaluation, Request for Exemption from 10 CFR 50.47 and 10 CFR 50 Appendix E to Reduce Emergency Planning Requirements for Permanently Defueled Condition (CAC MF9067; EPID L-2016-LLE-0003) |
ML20235T603 | 6 October 1987 | Insp Repts 50-285/87-21 on 870914-18.Violations Noted.Major Areas Inspected:Radiological Environ Monitoring & External Occupational Exposure Control Programs & Allegation |
NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status | 12 March 2012 | Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status |