ML18060A144 | 4 May 2018 | DCA Chapter 8 SER with Open Items (May 2018) | Safe Shutdown Anticipated operational occurrence Tornado Missile Probabilistic Risk Assessment Emergency Lighting Open Phase Condition Exemption Request Earthquake Maintenance Rule Program |
ML18171A205 | 24 September 2018 | SER W/Oi for NuScale DCA, Tier 2, Chapter 17, Quality Assurance and Reliability Assurance. | Probabilistic Risk Assessment |
ML18214A195 | 7 December 2018 | DCA - Chapter 2 SER with Open Items | Ultimate heat sink Anticipated operational occurrence Tornado Missile Safe Shutdown Earthquake Internal Flooding Hydrostatic Tornado Generated Missile Earthquake |
ML18220B313 | 24 April 2019 | DCA - Chapter 21 - Multi-Module Design Considerations - SE with Open Items | Ultimate heat sink |
ML18228A692 | 16 August 2018 | Chapter 7 SER W OIs (Public) | Safe Shutdown Health Physics Network Ultimate heat sink Mission time Anticipated operational occurrence Probabilistic Risk Assessment Operator Manual Action Incorporated by reference Surveillance Frequency Control Program Exemption Request Earthquake Failure to Scram |
ML18233A533 | 3 January 2019 | DCA - Chapter 13 SE with Open Items | Safe Shutdown Fitness for Duty Shutdown Margin Ultimate heat sink Probabilistic Risk Assessment Incorporated by reference FLEX B.5.b Process Control Program Severe Accident Management Guideline Exemption Request Fire Protection Program |
ML18257A276 | 23 January 2019 | Staff'S Phase 2 SER for NuScale DCA Chapter 10, Steam and Power Conversion System | Safe Shutdown Ultimate heat sink Grab sample Stroke time Anticipated operational occurrence Safe Shutdown Earthquake Internal Flooding Nondestructive Examination Earthquake Turbine Missile |
ML19015A051 | 17 January 2019 | Chapter 11 Phase 2 SER | Safe Shutdown Offsite Dose Calculation Manual Anticipated operational occurrence Coatings Annual Radiological Environmental Operating Report Process Control Program Pressure Boundary Leakage Accidental discharge |
ML19015A137 | 18 January 2019 | Chapter 12 Phase 2 SER | Unanalyzed Condition Boric Acid High Radiation Area Ultimate heat sink Grab sample Anticipated operational occurrence Earthquake Fuel cladding Pressure Boundary Leakage Overexposure |
ML19017A253 | 2 January 2019 | DCA - Chapter 18 SE with Open Items (Public) | Safe Shutdown Ultimate heat sink Anticipated operational occurrence Probabilistic Risk Assessment Incorporated by reference Exemption Request |
ML19050A439 | 21 March 2019 | Nuscale DCA SER-OI Chapter 16 - Technical Specifications | Safe Shutdown Boric Acid Shutdown Margin High Radiation Area Ultimate heat sink Offsite Dose Calculation Manual Anticipated operational occurrence Post Accident Monitoring Hydrostatic Probabilistic Risk Assessment Pressure and Temperature Limits Report Surveillance Frequency Control Program Annual Radiological Environmental Operating Report Exemption Request Pressure Boundary Leakage |
ML19073A071 | 19 April 2019 | DCA - Safety Evaluation Report with Open Items - Chapter 19, Probabilistic Risk Assessment and Severe Accident Evaluation for New Reactors | Hot Short Safe Shutdown High winds Ultimate heat sink Mission time Fire Barrier Internal Flooding Probabilistic Risk Assessment Multiple Spurious Operation Significance Determination Process Severe Accident Management Guideline Overtravel Exemption Request Earthquake Control of Heavy Loads Fatality |
ML19084A286 | 25 March 2019 | DCA Chapter 9 Phase 2 Safety Evaluation Report with Open Items - Public | Safe Shutdown Boric Acid High winds Shutdown Margin Loop seal Ultimate heat sink Grab sample Fire Barrier Anticipated operational occurrence Tornado Missile Safe Shutdown Earthquake Internal Flooding Nondestructive Examination Multiple Spurious Operation Emergency Lighting Incorporated by reference Surveillance Frequency Control Program License Renewal Exemption Request Earthquake Control of Heavy Loads Turbine Missile Biofouling Fire Protection Program GOTHIC |
ML19092A423 | 15 April 2019 | Draft 14.2 SER with OI | Safe Shutdown Unanalyzed Condition Shutdown Margin Ultimate heat sink Probabilistic Risk Assessment |
ML19098B507 | 8 April 2019 | Chapter 5 (Pressure-Temperature Limits Report) Phase 2 SER | Hydrostatic Incorporated by reference Pressure and Temperature Limits Report |
ML19102A109 | 17 April 2019 | Phase 2 SER-MEB 3.9.2 - Chapter 3 | Anticipated operational occurrence Nondestructive Examination Earthquake |
ML19165A282 | 27 November 2019 | DCA - Chapter 2 SER with No Open Items | Safe Shutdown Ultimate heat sink Anticipated operational occurrence Tornado Missile Internal Flooding Hydrostatic Probabilistic Risk Assessment Tornado-Generated Missile Earthquake |
ML19165A286 | 17 October 2019 | DCA - Chapter 13 SER with No Open Items | Fitness for Duty Probabilistic Risk Assessment Process Control Program Exemption Request Fire Protection Program |
ML19169A118 | 22 November 2019 | Letter to NuScale Transmitting Phase 4 SER for Chapter 8 | |
ML19169A131 | 10 December 2019 | Letter to NuScale Transmitting SER | |
ML19169A132 | 10 December 2019 | Memo to ACRS Transmitting SER | |
ML19169A139 | 9 September 2019 | Letter to NuScale Transmitting Chapter 10 (Phase 4) SER | |
ML19169A141 | 9 September 2019 | Memo to ACRS Transmitting Chapter 10 (Phase 4) SER | |
ML19169A149 | 29 August 2019 | Letter to NuScale Transmitting SER with No Open Items for Chapter 11, Radioactive Waste Management. | |
ML19169A150 | 29 August 2019 | Nuscale Power, LLC, Design Certification Application - Safety Evaluation with No Open Items for Chapter 11, Radioactive Waste Management | |
ML19169A272 | 23 October 2019 | DCA - Chapter 21 SER with No Open Items | Ultimate heat sink |
ML19169A290 | 22 November 2019 | Letter to NuScale Transmitting SER | |
ML19169A291 | 22 November 2019 | Memo to ACRS Transmitting SER | |
ML19169A295 | 26 November 2019 | Memo to ACRS Transmitting SER | |
ML19169A312 | 4 December 2019 | LLC, Design Certification Application - Safety Evaluation with No Open Items for Chapter 16, Technical Specifications - Letter | |
ML19182A241 | 16 December 2019 | DCA - Chapter 13.6 SE with No Open Items | Safe Shutdown Fitness for Duty Probabilistic Risk Assessment Cyber Security Incorporated by reference Finite Element Analysis |
ML19207A371 | 8 August 2019 | Chapter 17 Phase 4 SER | Probabilistic Risk Assessment |
ML19218A037 | 12 September 2019 | Phase 4 SER - Chapter 10 | Safe Shutdown Ultimate heat sink Grab sample Stroke time Anticipated operational occurrence Safe Shutdown Earthquake Internal Flooding Nondestructive Examination Earthquake Turbine Missile |
ML19224B376 | 8 August 2019 | Chapter 17 Phase 4 SER (Public) | Probabilistic Risk Assessment |
ML19233A071 | 21 August 2019 | Ser_Areva Seismic Methodology TR-0716-50351_Non_Proprietary | Earthquake |
ML19238A017 | 23 August 2019 | Preliminary P2 SER NuScale Ch 15 Redacted Version - Clean | Safe Shutdown Boric Acid Shutdown Margin Ultimate heat sink Anticipated operational occurrence Internal Flooding Probabilistic Risk Assessment Incorporated by reference Surveillance Frequency Control Program Exemption Request Fuel cladding Coast down |
ML19240A442 | 29 August 2019 | LLC, Design Certification Application - Safety Evaluation with No Open Items for Chapter 11, Radioactive Waste Management - SER | Safe Shutdown Offsite Dose Calculation Manual Anticipated operational occurrence Coatings Annual Radiological Environmental Operating Report Process Control Program Accidental discharge |
ML19254C858 | 11 September 2019 | Non-Proprietary Version - SER for NuScale TR-0516-49417 Evaluation Methodology for Stability Analysis of the NuScale Power Module, Rev 0 | |
ML19267A086 | 8 January 2020 | Phase 4 Chapter 14 SER | Safe Shutdown Unanalyzed Condition Shutdown Margin Ultimate heat sink Anticipated operational occurrence Safe Shutdown Earthquake Internal Flooding Hydrostatic Probabilistic Risk Assessment Nondestructive Examination Emergency Lighting Incorporated by reference Safeguards Contingency Plan Exemption Request Earthquake Power-Operated Valves Turbine Missile Pressure Boundary Leakage |
ML19270F278 | 27 September 2019 | Public Version of Phase 4 SER for Chapter 7 | Safe Shutdown Health Physics Network Ultimate heat sink Mission time Anticipated operational occurrence Probabilistic Risk Assessment Operator Manual Action Incorporated by reference Surveillance Frequency Control Program Exemption Request Earthquake Failure to Scram |
ML19284A372 | 13 January 2020 | Chapter P4 SER, Reactor Coolant System and Connecting Systems | Boric Acid Ultimate heat sink Anticipated operational occurrence Safe Shutdown Earthquake Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Finite Element Analysis Pressure and Temperature Limits Report Foreign Material Exclusion Process Control Program Exemption Request Earthquake Liquid penetrant Pressure Boundary Leakage Pressure boundary leak Fire Protection Program Unidentified leakage |
ML19289C159 | 18 October 2019 | Dnrl Memo to ACRS - Safety Evaluation for Topical Report, TR-0915-17565 | |
ML19318E303 | 4 December 2019 | Chapter 12 Phase 4 SE - Clean Version OGC Reviewed NLO | Boric Acid High Radiation Area Ultimate heat sink Anticipated operational occurrence Exemption Request Earthquake Fuel cladding Pressure Boundary Leakage Overexposure |
ML19319A684 | 3 December 2019 | Phase 4 SER - Chapter 8 | Safe Shutdown Ultimate heat sink Anticipated operational occurrence Tornado Missile Probabilistic Risk Assessment Emergency Lighting Open Phase Condition Exemption Request Earthquake Maintenance Rule Program |
ML19330E020 | 27 December 2019 | LLC, Design Certification Application - Phase 4 Chapter 16 Safety Evaluation | Safe Shutdown Boric Acid Shutdown Margin High Radiation Area Ultimate heat sink Offsite Dose Calculation Manual Stroke time Anticipated operational occurrence Probabilistic Risk Assessment Pressure and Temperature Limits Report Surveillance Frequency Control Program Annual Radiological Environmental Operating Report Power-Operated Valves Pressure Boundary Leakage |
ML19336B593 | 16 January 2020 | Chapter 4 Phase 4 SER with No Ols | Safe Shutdown Shutdown Margin Ultimate heat sink Anticipated operational occurrence Safe Shutdown Earthquake Operating Basis Earthquake Nondestructive Examination Incorporated by reference Exemption Request Earthquake Fuel cladding Power change |
ML19337A787 | 8 January 2020 | Phase 4 SE Input for Chapter 3 (Public) | Safe Shutdown Unanalyzed Condition Boric Acid High Radiation Area Ultimate heat sink Fire Barrier Anticipated operational occurrence Tornado Missile Safe Shutdown Earthquake Internal Flooding Hydrostatic Probabilistic Risk Assessment Nondestructive Examination Squib Incorporated by reference Finite Element Analysis Tornado Generated Missile Exemption Request Earthquake Power-Operated Valves Turbine Missile Fuel cladding Liquid penetrant Pressure Boundary Leakage Flow Induced Vibration |
ML19338B783 | 11 December 2019 | LLC, Design Certification Application - Safety Evaluation with No Open Items for Chapter 20, Mitigation of Beyond-Design-Basis Events - Public SER | Ultimate heat sink Post Accident Monitoring Emergency Lighting Incorporated by reference FLEX Spent Fuel Pool Instrumentation B.5.b Mitigating Strategies Earthquake GOTHIC |
ML19340A065 | 16 December 2019 | DCA - Chapter 18 SER with No Open Items | Safe Shutdown Ultimate heat sink Anticipated operational occurrence Post Accident Monitoring Probabilistic Risk Assessment Severe Accident Management Guideline Exemption Request |
ML19343A027 | 18 December 2019 | Phase 4 SER - Chapter 6 | Safe Shutdown Boric Acid Ultimate heat sink Mission time Stroke time Anticipated operational occurrence Weld Overlay Hydrostatic Probabilistic Risk Assessment Coatings Incorporated by reference Foreign Material Exclusion Excess Flow Check Valve Severe Accident Management Guideline License Renewal Exemption Request Earthquake Fuel cladding |