MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20240012024-06-28028 June 2024 NRC Inspection Report No. 05000271/2024001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24053A2572024-03-0101 March 2024 Withdrawal of Requested Licensing Action for a License Amendment Submitted for Approval of the License Termination Plan BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G IR 05000271/20230022024-02-20020 February 2024 NRC Inspection Report Nos. 05000271/2023002 and 07200059/2023001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust 2024-09-18
[Table view] |
Text
SECURITY - RELATED INFORMATION SECURITY - RELATED INFORMATION UNITEDSTATESNUCLEARREGULATORYCOMMISSIONREGIONI2100RENAISSANCEBOULEVARD,SUITE100KINGOFPRUSSIA,PENNSYLVANIA194062713November 6, 2013 Mr. Christopher Wamser Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station PO Box 250 Vernon, VT 05354
SUBJECT: VERMONT YANKEE NUCLEAR POWER STATION, TEMPORARY INSTRUCTION 2515/186, "INSPECTION OF PROCEDURES AND PROCESS FOR RESPONDING TO POTENTIAL AIRCRAFT THREATS;" INSPECTION REPORT NO. 05000271/2013404
Dear Mr. Wamser:
On September 25, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Vermont Yankee Nuclear Power Station using Temporary Instruction 2515/186, "Inspection of Procedures and Processes for Responding to Potential Aircraft Threats." The enclosed inspection report documents the results of the inspection, which were discussed with you and other members of your staff.
The objective of this inspection was to assess the implementation procedures and processes at the Vermont Yankee Nuclear Power Station that are required by Title 10 of the Code of Federal Regulations (10 CFR) 50.54(hh)(1), which provides the requirements for responding to a potential aircraft threat. The results from this inspection, along with the results from this inspection performed at other operating commercial nuclear plants in the United States, will be used to evaluate the U.S. nuclear industry's readiness to safely respond to similar events. These results will also help the NRC to determine if additional regulatory actions are warranted. The inspection examined activities conducted under your license as they relate to the implementation of 10 CFR 50.54(hh)(1), your compliance with the Commission's rules and regulations, and with the conditions of your operating licenses. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel. No findings were identified during this inspection. Enclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. SECURITY - RELATED INFORMATION SECURITY - RELATED INFORMATION In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1).
In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,/RA/ Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-271 License No. DPR-28
Enclosure:
Inspection Report 05000271/2013404
w/Attachment:
Supplemental Information
cc w/o encl; w/o OUO-SRI: Distribution via ListServ cc w/encl; w/OUO-SRI P. Ryan, Security Manager C. Recchia, Commissioner, Department of Public Service J. Giarrusso, Division Chief, MA Emergency Management Agency P. Plummer, Acting Director, State of New Hampshire Homeland Security SECURITY - RELATED INFORMATION