ML17102B069 | |
Person / Time | |
---|---|
Site: | Diablo Canyon |
Issue date: | 03/31/2017 |
From: | Halpin E D Pacific Gas & Electric Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
DCL-17-022 | |
Download: ML17102B069 (206) | |
Similar Documents at Diablo Canyon | |
---|---|
Category:Decommissioning Funding Plan DKTs 30
MONTHYEARDCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024
[Table view]Decommissioning Funding Report DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 DCL-22-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22022-03-30030 March 2022 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 L-21-010, Independent Spent Fuel Storage Installation, Decommissioning Funding Plan2021-12-14014 December 2021 Independent Spent Fuel Storage Installation, Decommissioning Funding Plan DCL-21-026, Decommissioning Funding Report2021-03-31031 March 2021 Decommissioning Funding Report DCL-20-014, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 22020-03-30030 March 2020 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 2 ML19345D3452019-12-0404 December 2019 Site-Specific Decommissioning Cost Estimate DCL-19-055, Revised Enclosure for the Decommissioning Funding Report2019-07-0101 July 2019 Revised Enclosure for the Decommissioning Funding Report DCL-17-022, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22017-03-31031 March 2017 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-15-044, Decommissioning Funding Report for Diablo Canyon, Units 1 and 22015-03-31031 March 2015 Decommissioning Funding Report for Diablo Canyon, Units 1 and 2 DCL-13-033, Decommissioning Funding Report2013-04-0101 April 2013 Decommissioning Funding Report DCL-11-039, Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 20102011-03-31031 March 2011 Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 2010 DCL-11-039, Submittal of Decommissioning Funding Report2011-03-31031 March 2011 Submittal of Decommissioning Funding Report ML1109006722011-03-31031 March 2011 Decommissioning Funding Report for 2010 DCL-09-021, Submittal of Decommissioning Funding Report2009-03-31031 March 2009 Submittal of Decommissioning Funding Report DCL-07-028, Supplemental to Decommissioning Funding Report2007-06-13013 June 2007 Supplemental to Decommissioning Funding Report DCL-05-026, Decommissioning Funding Report2005-03-31031 March 2005 Decommissioning Funding Report DCL-03-035, Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 72003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 7 ML0309902892003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 1 - 4, Appendix C ML0509605442002-02-12012 February 2002 P01-1421-003, Rev. 0, Decommissioning Cost Study for Diablo Canyon Power Plant Units 1 and 2. 2024-03-27 Category:40 MONTHYEARDCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024
[Table view]Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 DCL-22-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22022-03-30030 March 2022 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-22-011, License Amendment Request 22-02 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections2022-03-10010 March 2022 License Amendment Request 22-02 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections L-22-003, Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation2022-03-0909 March 2022 Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation L-21-010, Independent Spent Fuel Storage Installation, Decommissioning Funding Plan2021-12-14014 December 2021 Independent Spent Fuel Storage Installation, Decommissioning Funding Plan DCL-21-026, Decommissioning Funding Report2021-03-31031 March 2021 Decommissioning Funding Report DCL-20-014, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 22020-03-30030 March 2020 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 2 ML19345D3452019-12-0404 December 2019 Site-Specific Decommissioning Cost Estimate DCL-19-055, Revised Enclosure for the Decommissioning Funding Report2019-07-0101 July 2019 Revised Enclosure for the Decommissioning Funding Report DCL-17-022, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22017-03-31031 March 2017 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-15-107, License Amendment Request 15-07, Revision of Reactor Coolant System Minimum Flow Specified in Technical Specification 3.4.1. RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits.2015-09-16016 September 2015 License Amendment Request 15-07, Revision of Reactor Coolant System Minimum Flow Specified in Technical Specification 3.4.1. RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits. DCL-15-044, Decommissioning Funding Report for Diablo Canyon, Units 1 and 22015-03-31031 March 2015 Decommissioning Funding Report for Diablo Canyon, Units 1 and 2 DCL-13-033, Decommissioning Funding Report2013-04-0101 April 2013 Decommissioning Funding Report DCL-11-039, Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 20102011-03-31031 March 2011 Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 2010 DCL-11-039, Submittal of Decommissioning Funding Report2011-03-31031 March 2011 Submittal of Decommissioning Funding Report ML1109006722011-03-31031 March 2011 Decommissioning Funding Report for 2010 DCL-09-021, Submittal of Decommissioning Funding Report2009-03-31031 March 2009 Submittal of Decommissioning Funding Report DCL-07-028, Supplemental to Decommissioning Funding Report2007-06-13013 June 2007 Supplemental to Decommissioning Funding Report DCL-05-026, Decommissioning Funding Report2005-03-31031 March 2005 Decommissioning Funding Report DCL-03-035, Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 72003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 7 ML0309902892003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 1 - 4, Appendix C ML0509605442002-02-12012 February 2002 P01-1421-003, Rev. 0, Decommissioning Cost Study for Diablo Canyon Power Plant Units 1 and 2. 2024-08-28 Category:50 MONTHYEARDCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024
[Table view]Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 DCL-22-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22022-03-30030 March 2022 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 L-21-010, Independent Spent Fuel Storage Installation, Decommissioning Funding Plan2021-12-14014 December 2021 Independent Spent Fuel Storage Installation, Decommissioning Funding Plan DCL-21-026, Decommissioning Funding Report2021-03-31031 March 2021 Decommissioning Funding Report DCL-20-014, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 22020-03-30030 March 2020 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 2 ML19345D3452019-12-0404 December 2019 Site-Specific Decommissioning Cost Estimate DCL-19-055, Revised Enclosure for the Decommissioning Funding Report2019-07-0101 July 2019 Revised Enclosure for the Decommissioning Funding Report DCL-17-022, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22017-03-31031 March 2017 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-15-044, Decommissioning Funding Report for Diablo Canyon, Units 1 and 22015-03-31031 March 2015 Decommissioning Funding Report for Diablo Canyon, Units 1 and 2 DCL-13-033, Decommissioning Funding Report2013-04-0101 April 2013 Decommissioning Funding Report DCL-11-039, Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 20102011-03-31031 March 2011 Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 2010 DCL-11-039, Submittal of Decommissioning Funding Report2011-03-31031 March 2011 Submittal of Decommissioning Funding Report ML1109006722011-03-31031 March 2011 Decommissioning Funding Report for 2010 DCL-09-021, Submittal of Decommissioning Funding Report2009-03-31031 March 2009 Submittal of Decommissioning Funding Report DCL-07-028, Supplemental to Decommissioning Funding Report2007-06-13013 June 2007 Supplemental to Decommissioning Funding Report DCL-05-026, Decommissioning Funding Report2005-03-31031 March 2005 Decommissioning Funding Report DCL-03-035, Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 72003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 7 ML0309902892003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 1 - 4, Appendix C ML0509605442002-02-12012 February 2002 P01-1421-003, Rev. 0, Decommissioning Cost Study for Diablo Canyon Power Plant Units 1 and 2. 2024-08-28 Category:70 MONTHYEARDCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024
[Table view]Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 DCL-22-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22022-03-30030 March 2022 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-22-011, License Amendment Request 22-02 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections2022-03-10010 March 2022 License Amendment Request 22-02 Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections L-22-003, Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation2022-03-0909 March 2022 Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation L-21-010, Independent Spent Fuel Storage Installation, Decommissioning Funding Plan2021-12-14014 December 2021 Independent Spent Fuel Storage Installation, Decommissioning Funding Plan DCL-21-026, Decommissioning Funding Report2021-03-31031 March 2021 Decommissioning Funding Report DCL-20-014, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 22020-03-30030 March 2020 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 & 2 ML19345D3452019-12-0404 December 2019 Site-Specific Decommissioning Cost Estimate DCL-19-055, Revised Enclosure for the Decommissioning Funding Report2019-07-0101 July 2019 Revised Enclosure for the Decommissioning Funding Report DCL-17-022, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22017-03-31031 March 2017 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-15-107, License Amendment Request 15-07, Revision of Reactor Coolant System Minimum Flow Specified in Technical Specification 3.4.1. RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits.2015-09-16016 September 2015 License Amendment Request 15-07, Revision of Reactor Coolant System Minimum Flow Specified in Technical Specification 3.4.1. RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits. DCL-15-044, Decommissioning Funding Report for Diablo Canyon, Units 1 and 22015-03-31031 March 2015 Decommissioning Funding Report for Diablo Canyon, Units 1 and 2 DCL-13-033, Decommissioning Funding Report2013-04-0101 April 2013 Decommissioning Funding Report DCL-11-039, Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 20102011-03-31031 March 2011 Diablo Canyon Power Plant, Units 1 & 2, Decommissioning Funding Report for 2010 DCL-11-039, Submittal of Decommissioning Funding Report2011-03-31031 March 2011 Submittal of Decommissioning Funding Report ML1109006722011-03-31031 March 2011 Decommissioning Funding Report for 2010 DCL-09-021, Submittal of Decommissioning Funding Report2009-03-31031 March 2009 Submittal of Decommissioning Funding Report DCL-07-028, Supplemental to Decommissioning Funding Report2007-06-13013 June 2007 Supplemental to Decommissioning Funding Report DCL-05-026, Decommissioning Funding Report2005-03-31031 March 2005 Decommissioning Funding Report DCL-03-035, Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 72003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 4 - 7 ML0309902892003-03-27027 March 2003 Decommissioning Funding Reports for Diablo Canyon, Units 1 & 2 and Humboldt Bay, Unit 3, Enclosures 1 - 4, Appendix C ML0509605442002-02-12012 February 2002 P01-1421-003, Rev. 0, Decommissioning Cost Study for Diablo Canyon Power Plant Units 1 and 2. 2024-08-28 Category:Letter MONTHYEARML24260A1222024-09-14014 September 2024
[Table view]14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application DCL-24-054, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 IR 05000275/20240012024-04-23023 April 2024 Integrated Inspection Report 05000275/2024001 and 05000323/2024001 ML24114A2032024-04-22022 April 2024 Request for Information for EP Program and Performance Indicator Verification Inspection (Wolf Creek Nuclear Generating Station) Inspection Report 05000482/2024003 ML24106A2882024-04-18018 April 2024 License Renewal Application Environmental Review RCIs and RAIs ML24106A2892024-04-18018 April 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of March 2024 Audit Regarding the Environmental Review of the License Renewal Application DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24108A1122024-04-15015 April 2024 License Amendment Request 24-02 Request for Approval of DCPP Early Warning System to Meet 10 CFR 73.55(i)(2) and 10 CFR 73.55(e)(9)(vi)(A) DCL-24-022, Notification of Changes to Decommissioning Schedule2024-04-0202 April 2024 Notification of Changes to Decommissioning Schedule DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-24-032, 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant2024-03-27027 March 2024 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant ML24082A2592024-03-25025 March 2024 Notice of Enforcement Discretion for Diablo Canyon Power Plant, Unit 2 (EPID L-2024-LLD-0002) - March 25, 2024 ML24081A0462024-03-22022 March 2024 Audit Summary in Support of the License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-24-028, Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability2024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability ML24081A4052024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability 2024-09-09 |