License Renewal Phase IV Report 05000263/2020014
ML20182A685
Person / Time
Site: Monticello 
Issue date: 06/30/2020
From: Ann Marie Stone
NRC/RGN-III/DRP/B1
To: Conboy T
Northern States Power Company, Minnesota
References
IR 2020014
Download: ML20182A685 (10)


Text

June 30, 2020

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - LICENSE RENEWAL PHASE IV REPORT 05000263/2020014

Dear Mr. Conboy:

On June 10, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant and discussed the results of this inspection with Ms. M. Kelly, Director of Site Performance and Support and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Ann Marie J. Stone, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 05000263 License No. DPR-22

Enclosure:

As stated

Inspection Report

Docket Number: 05000263 License Number: DPR-22 Report Number: 05000263/2020014 Enterprise Identifier: I-2020-014-0002 Licensee: Northern States Power Company, Minnesota Facility: Monticello Nuclear Generating Plant Location: Monticello, MN Inspection Dates: June 01, 2020 to June 10, 2020 Inspectors: J. Corujo-Sandin, Reactor Inspector G. O'Dwyer, Reactor Engineer J. Park, Reactor Inspector Approved By: Ann Marie J. Stone, Chief Engineering Branch 1 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a License Renewal Phase IV at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), regional inspectors were directed to begin telework. For the inspection documented below, it was determined that the objectives and requirements stated in the IP could be performed remotely.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===71003 - Post-Approval Site Inspection for License Renewal The team conducted this Phase IV license renewal inspection remotely. The team selected Aging Management Programs (AMPs) for evaluation considering risk insights and programs that were enhanced or new under the renewed operating license. The team also considered for selection those programs with monitoring results that were performed for the first time or those that identified examination or test results not experienced in the past. For the AMPs selected, the team reviewed records and interviewed plant staff to evaluate whether AMP elements were being implemented involving program scope, preventive actions, parameters monitored or inspected, detection of aging effects, monitoring and trending, acceptance criteria, corrective actions, confirmation process, administrative controls, and operating experience.

The following aging management programs were evaluated by the team:

Post-Approval Site Inspection for License Renewal ===

(1) EWI-11.01.11; Fuel Oil Chemistry
(2) EWI-11.01.14; Buried Piping & Tanks Inspection
(3) EWI-11.01.19; Compressed Air Monitoring
(4) EWI-11.01.31; Protective Coating Monitoring & Maintenance Program
(5) EWI-11.01.33; Bolting Integrity
(6) EWI-11.01.35; Selective Leaching of Materials

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On June 10, 2020, the inspectors presented the License Renewal Phase IV results to Ms. M. Kelly, Director of Site Performance and Support and other members of the licensee staff.
  • On June 10, 2020, the inspectors presented the Technical Debrief inspection results to Mr. J. Madden, Engineering Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71003 Corrective Action 01226439 Corrosion Discovered on Removed Fire Protection Valve 06/28/2010

Documents 01228174 FP-13, License Renewal, Evidence of Selective Leaching 11/08/2010

232662 Add Note to MMP-008 to Clarify Requirements for Thread 05/23/2020

Lubrication

249063 Selective Leaching Identified on FP-7-2 Valve 09/09/2010

254764 Selective Leaching Identified on FP-199 10/19/2010

01356511 Selective Leaching Long Term Management Strategy 10/25/2012

01449311 Selective Leaching: Program Not Updated for New Strategy 10/03/2014

01475664 Torus Internal Coating Flaking Noted During 1132 04/22/2015

01475667 Torus Internal Corrosion Noted During 1132 04/22/2015

01477384 Numerous Small Areas of PCT Coatings Failed Acceptance 05/28/2015

Criteria

01558080 Numerous Small Areas of PCT Coatings Failed Acceptance 05/05/2017

Criteria

501000002818 1R XFMR - Moisture Found in 13.8KV Bus 09/22/2017

501000002848 1R XFMR - Enclosed Buses Need Sealing 09/20/2017

501000012494 PM 4159 Air Leaks Identified 05/25/2018

501000026573 4159-PM -3 Air Leaks Identified in the Drywell and 1 Minor Air 04/30/2019

Leak in Steam Chase

501000026876 Small Areas of Unsat PCT Coating 05/04/2019

501000028542 1362 Air Quality Test for IA System under WO 700042064 06/14/2019

Single Benign Particle Detected

501000032327 LR FSA AMP Ownership Needs Improvement 09/26/2019

501000032338 LR FSA: AMP Documents Outdated/Incorrect 09/26/2019

501000032354 LR FSA: Sel. Leaching Strategy Unclear 09/26/2019

501000032360 LR FSA: Bus Duct Inspection Criteria 09/26/2019

501000032360 LR FSA- Bus Duct Procedures Correct but USAR Not Updated 10/31/2019

501000036476 Bolting AMP OE Review 01/13/2020

501000036529 GAP Review for EWI-11.01.33 vs GALL 2 01/15/2020

501000038263- USAR-K Update Needed for ASME XI ISI Programs 03/01/2020

200421-000

Inspection Type Designation Description or Title Revision or

Procedure Date

501000038783 App J AMP Doc Issue 03/13/2020

501000039741 Unable to Find Form 3839 Records 04/16/2020

501000039871 SL AMP Procedures - Add Ductile Iron 04/20/2020

501000039968 1362 Air Quality Test for 17 AC Detected 10 Particles Greater 04/23/2020

than 40 Microns

Corrective Action 501000039970 2020 LR NRC Insp: LR-ISG-2012-02 OEE 04/22/2020

Documents 501000040540 2020 LR NRC Insp: AMP Doc PM Lists 05/12/2020

Resulting from 501000041198 2020 LR NRC Insp: Buried Pipe AMP PM 06/02/2020

Inspection 501000041227 2020 LR NRC Insp: Response >24 hrs 06/03/2020

501000041258 2020 LR NRC Insp: USAR-K SL Outdated 06/03/2020

501000041281 2020 LR NRC Insp: SL Valve Strategy 06/03/2020

501000041300 2020 LR NRC Insp: SL Inspection Doc 06/03/2020

501000041300 2020 LR NRC Insp: SL Inspection Doc 06/03/2020

501000041303 2020 LR NRC Insp: Duct Iron SL Insp Proc 06/04/2020

501000041313 2020 LR NRC Inspection: EWI-11.01.33 Should Be Enhanced 06/04/2020

to Clarify Molybdenum Disulfide (MoS2) SHALL NOT Be Used

on Bolts in Scope of Bolting Integrity Program

501000041313 2020 LR NRC Insp: EWI-11.01.33 MoS2 Enh 06/04/2020

501000041316 2020 LR NRC Insp: EWI-11.01.31 Enh 06/04/2020

501000041342 2020 LR NRC Insp: Inadequate CAP Closure 06/05/2020

501000041351 Gap in RM Process for Lost Records 06/05/2020

501000041384 2020 LR NRC Insp Questioned EWI-11.01.19 Pump Casing 06/08/2020

Requirement

501000041463 2020 LR NRC Insp: Coatings Observation 06/11/2020

Miscellaneous OE Fermi Power Plant, Unit 2 - Special Inspection Reactive Report 05/01/2020

600000676449 05000341/2019050

OE EPRI Selective Leaching State of the Art Technical Update 03/25/2020

610000000867 (3002016057)

OE NUREG-2191 Vol 2, Generic Aging Lessons Learned for 05/12/2020

610000000879 Subsequent License Renewal (GALL-SLR) Report, Section

XI.M33 Selective Leaching

Procedures 0140 Drywell Interior Surface Inspection 25

268 Fire Protection System Flow Test 24

Inspection Type Designation Description or Title Revision or

Procedure Date

AWI-08.11.03 Nuclear Coatings Program 16

4108-01-PM Emergency Diesel Generator 6 Year Maintenance 36

EWI-08.26.02 Selective Leaching Inspection Process 2

EWI-11.01.01 Bus Duct Inspection Program 5

EWI-11.01.11 Fuel Oil Chemistry 2

EWI-11.01.14 Buried Piping & Tanks Inspection 2

EWI-11.01.19 Compressed Air Monitoring 2

EWI-11.01.31 Protective Coating Monitoring & Maintenance Program 4

EWI-11.01.33 Bolting Integrity 1

EWI-11.01.35 Selective Leaching of Materials 0

FP-G-RM-01 Quality Assurance Records Control 32

FP-G-RM-02 Records Processing 22

FP-PE-RLP-01 License Renewal Implementation 9

FP-PE-UPT-01 Underground Piping and Tanks Integrity Program 4

FP-WM-PLA-01 Work Order Planning Process 37

NSP-DOL-0598 Diesel Fuel Oil Tank Inspection 6

NSP-DOL-0598 Diesel Fuel Tank Inspection 6

PCR Procedure Change Request for EWI-11.01.33 Bolting Integrity 03/09/2020

2000015193-

200420-000

PCR Procedure Change Request for MMP-008, Bolting Practices 3

2000015610

PCR Procedure Change Request for MMP-008 2

2000015610

PEI-03.01.03 Selective Leaching (Graphitic Corrosion) Inspection 1

Self-Assessments 01468275 Audit Aging Management Programs 03/02/2015

01533999 Aging Management SSA in Prep for 2016 P&IR 09/07/2016

6060000001098 SnapShot Report, Perform AMP Effectiveness Reviews in 03/01/2020

Accordance with NEI 14-12

606000000952 License Renewal Phase IV Self-Assessment Plan 09/26/2020

Work Orders 00453355 CONST - T-44, Transfer Fuel to FRAC Tanks and Clean T-44 06/12/2013

00453355 CONST - T-44, Transfer Fuel to Frac Tanks and Clean T-44 06/12/2013

00457542 Perform Elec PM 07/07/2013

Inspection Type Designation Description or Title Revision or

Procedure Date

00487027 OPS-FIR, 0268 3-Year Fire Protection System Flow Test 12/01/2015

00532393 EPRO - MRE, UPTI Inspection 01/22/2018

00552645 Const - T-45A, Clean and Inspect T-45A Day Tank 01/19/2018

490719 0135 Torus Painted Surface Internal Insp. 05/09/2015

490906 0140 Drywell Interior Surface Inspection 05/09/2015

500121 PM 4159 Leak Detection PM 3 ARs 5 WOs 05/10/2016

533733 0140 Drywell Interior Surface Inspection 05/10/2017

537441 CPF: Hydrant FP-192 AND FP-27; Install New Valves 04/22/2017

537441 CPF: Hydrant FP-192 and FP-27, Install New Valves 03/17/2017

700005790-0020 Perform UT and Visual Inspection of Tank, Inspect LIS-7259 06/08/2017

700009412 12 EDG G-3B Electrical Control Panel Bolt Broken 02/13/2019

700013462 Performed PM 4858-59 for 1R XFMR X03 10/26/2017

700017270 Walk Down Found No Problems in Air and AN2 Systems within 04/14/2019

LR Scope

700020823 0140 Drywell Interior Surface Inspection 05/10/2019

700023986 PM 4159 Leak Reduced to Less than Champagne Bubbles 05/29/2018

700031848 PM 4954 Air Dryers Leak Shows Elbow Needs to Be Replaced 09/07/2018

QIM 501000016607 Written

700047082 Walked Down Found No Problems in Air and AN2 Systems 12/13/2019

within LR Scope

700058662 PM 4953 Compressors Results All SAT 01/28/2020

700059432 1362 Test All Results SAT 09/10/2019

700062663 1362 Test All Results Were SAT 03/13/2020

700067605 Graphitic Corrosion Inspection Results Form 3839 01/08/2020

QF0571 Troubleshooting Plan for QIM 501000039968 10 Particles 04/23/2020

Greater than 40 Microns

8