MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-23-035, Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-03-0909 March 2023 Supplement to License Amendment Request to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling GO2-23-019, Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-012023-02-0808 February 2023 Emergency Plan - Summary of Changes and Analysis for Revision 68 of the EP-01 GO2-22-131, Guarantee of Payment of Deferred Premium2022-12-19019 December 2022 Guarantee of Payment of Deferred Premium GO2-22-122, Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-11-28028 November 2022 Response to Request for Additional Information Related to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-076, Status of License Renewal Commitments2022-10-31031 October 2022 Status of License Renewal Commitments GO2-22-110, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor2022-10-17017 October 2022 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactor GO2-22-096, Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-10-0404 October 2022 Supplement to License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-085, Docket No. 50-397, Evacuation Time Estimate Analysis2022-08-30030 August 2022 Docket No. 50-397, Evacuation Time Estimate Analysis GO2-22-075, Response to Request for Additional Information Related to Revised Pressure-Temperature Limit Curves2022-07-11011 July 2022 Response to Request for Additional Information Related to Revised Pressure-Temperature Limit Curves GO2-22-072, Summary of Changes and Analysis for Revision 57 of PPM 13.14.4 - Emergency Equipment Maintenance and Testing2022-07-11011 July 2022 Summary of Changes and Analysis for Revision 57 of PPM 13.14.4 - Emergency Equipment Maintenance and Testing GO2-22-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process2022-05-25025 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Colling Using the Consolidated Line Item Improvement Process GO2-22-062, Registration of Spent Fuel Cask Use2022-05-19019 May 2022 Registration of Spent Fuel Cask Use GO2-22-049, Supplement to Licensing Amendment Request to Adopt 10CFR50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Rectors2022-05-10010 May 2022 Supplement to Licensing Amendment Request to Adopt 10CFR50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Rectors GO2-22-054, Independent Spent Fuel Storage Installation, 2021 Annual Radiological Environmental Operating Report2022-05-0909 May 2022 Independent Spent Fuel Storage Installation, 2021 Annual Radiological Environmental Operating Report GO2-22-056, Registration of Spent Fuel Cask Use2022-04-21021 April 2022 Registration of Spent Fuel Cask Use GO2-22-055, 2021 Annual Environmental Operating Report2022-04-20020 April 2022 2021 Annual Environmental Operating Report GO2-22-048, 2021 Annual Radioactive Effluent Release Report2022-04-15015 April 2022 2021 Annual Radioactive Effluent Release Report GO2-22-045, Registration of Spent Fuel Cask Use2022-04-0606 April 2022 Registration of Spent Fuel Cask Use GO2-22-044, Level of Financial Protection - Annual Reporting Requirement2022-03-21021 March 2022 Level of Financial Protection - Annual Reporting Requirement GO2-22-038, Docket No. 50-397, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462022-03-0909 March 2022 Docket No. 50-397, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 GO2-22-031, Response to Audit Plan and Online Reference Portal Request2022-02-15015 February 2022 Response to Audit Plan and Online Reference Portal Request GO2-22-011, Docket No. 72-35; Independent Spent Fuel Storage Installation, 2021 Annual Effluent Release Report2022-02-0808 February 2022 Docket No. 72-35; Independent Spent Fuel Storage Installation, 2021 Annual Effluent Release Report GO2-22-001, License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-02-0303 February 2022 License Amendment Request to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GO2-22-012, Independent Spent Fuel Storage Installation - Biennial 50.59/72.48 Report2022-01-24024 January 2022 Independent Spent Fuel Storage Installation - Biennial 50.59/72.48 Report 2024-01-08
[Table view] |
Text
ENERGY MNORTHWEST Peopie
- 99352-0968 January 31, 2007 G02-07-021 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397 LICENSE AMENDMENT 199 SAFETY EVALUATION CORRECTIONS
Reference:
Letter dated November 27, 2006, B Benney (NRC) to JV Parrish (Energy Northwest), "Columbia Generating Station -Issuance of Amendment Re: Alternative Source Term (TAC No. MC4570)"
Dear Sir ,
or Madam:.As documented inithe reference above, Energy} Northwest (EN) received'amendment 199 to th e Columbia-Generating Station Operating License on November 27, 2006.Energy Northwest has reviewed the safety evaluation for this amendment.
This letter identifies corrections that Energy Northwest believes should be made to the safety evaluation.
A detailed list is provided in the attachment to this letter so the issues can be addressed by the NRC staff.There are no new commitments being made. If you have any questions or require additional information, please contact Greg Cullen at (509) 377-6105.Respectfully, WS Ox or Vice President, Technical Services Mail Drop PE04..
Attachment:
License Amendment.
199 Safety Evaluation, Corrections cc:-BS Mallett -
I. N ..Sherman"-.BPAi1399
.CF Lyon'- NRC"NRR W.' .' WA Winston & Strawnh-, NfRC Senior Resident Inspector/988C LICENSE AMENDMENT 199 SAFETY EVALUATION CORRECTIONS Attachment Page 1 of 1 The following is a list of Energy Northwest identified issues associated with the safety evaluation (SE) to Amendment 199 of the Columbia Generating Station (CGS)Operating License and their proposed corrections:
- 1. SE Section 3.1.1.2.1
-the 1st sentence incorrectly refers to leakage as a percent of atmospheric content by "weight." The reference in the 4th paragraph of 3.1.1.2.2 correctly reflects "volume." The word "weight" should be changed to"volume" in the 1st sentence. (Reference Energy Northwest letter to the NRC G02-04-170, dated September 30, 2004, section 4.4.1, pg 36 of 91.)2. SE Section 3.1.1.2.2
-the 2nd paragraph, 3rd sentence incorrectly refers to main steam piping between the two "condensate demineralizers." The words"condensate demineralizers" should be changed to "Main Steam Isolation Valves (MSIVs)." (Reference G02-04-170, section 4.4.3, pg 42 of 91.)3. SE Section 3.1.1.2.3
-the last paragraph refers to a LOCA calculation LM-0646, Revision 1. This is not a calculation number recognized by CGS staff. The calculation number should be changed to NE-02-04-05. (Reference G02-04-170, Attachment 5, item 5.)4. SE Section 3.6 -the 1st paragraph, 2nd sentence is incomplete and unclear.The sentence should be completed.
- 5. SE Section 4.15.4 -the 1st and 2nd sentence of the last paragraph related to TID-14844 appears to be out of place and unrelated to the rest of the section (i.e., deletion of the requirement to suspend fuel handling on loss of offsite, onsite, or DC power). Equipment qualification issues were discussed in section 3.6. This information should be deleted from section 4.15.4.6. SE Table 1 -the Fuel Handling Accident section references "Release location" with two SGT configuration subcategories and two different release paths. There is only one release location regardless of SGT configuration at CGS. The release point for both should be changed to the point on the Reactor Building Wall closest to the Local Intake. (Reference G02-04-170, section 4.7.4, pg 67 of 91.)7. SE Table 1 -the Fuel Handling Accident (FHA) section references "Atmospheric Dispersion Factors X/Q values sec/m 3 and indicates that Submittal Table 4.4-2 and 4.4-3 provide the source of the information for the FHA dispersion factor.Table 4.4-2 and 4.4-3 apply to the LOCA event. The submittal table should be changed to Table 4.7-1. (Reference G02-04-170, pg 64 of 91.)