Letter Sequence Acceptance Review |
---|
|
|
|
|
---|
Category:Letter
MONTHYEARML24289A1252024-10-22022 October 2024 – Authorized Alternative to Requirements of the ASME OM Code PLA-8145, Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-81452024-10-21021 October 2024 Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-8145 ML24291A1562024-10-16016 October 2024 Missed Annual Inventory Required by 40 CFR 266, Subpart in PLE 0026645 PLA-8148, Registration for the Use of Spent Fuel Storage Casks 311, 308, and 3102024-10-15015 October 2024 Registration for the Use of Spent Fuel Storage Casks 311, 308, and 310 PLA-8141, Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-81412024-09-18018 September 2024 Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-8141 PLA-8142, Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-81422024-09-18018 September 2024 Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-8142 ML24260A2312024-09-17017 September 2024 Senior Reactor and Reactor Operator Initial License Examinations 05000387/LER-2024-002, B Diesel Generator Inoperable Due to Failed Excitation System Linear Reactor2024-09-16016 September 2024 B Diesel Generator Inoperable Due to Failed Excitation System Linear Reactor ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24233A2192024-09-0303 September 2024 – Authorized Alternative to Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code IR 05000387/20240052024-08-29029 August 2024 Updated Inspection Plan for Susquehanna Steam Electric Station, Units 1 and 2 (Report 05000387/2024005 and 05000388/2024005) 05000387/LER-2023-004-01, Manual Reactor Scram Due to Degraded Main Condenser Vacuum2024-08-26026 August 2024 Manual Reactor Scram Due to Degraded Main Condenser Vacuum 05000387/LER-2024-001-01, Main Steam Isolation Valve Leakage Due to Valve Body Seat Wear2024-08-21021 August 2024 Main Steam Isolation Valve Leakage Due to Valve Body Seat Wear IR 05000387/20240022024-08-12012 August 2024 Integrated Inspection Report 05000387/2024002 and 05000388/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification PLA-8117, 23rd Refueling Outage Owners Activity Report (PLA-8117)2024-07-23023 July 2024 23rd Refueling Outage Owners Activity Report (PLA-8117) ML24197A0982024-07-15015 July 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000387/2024010 and 05000388/2024010 ML24127A2262024-05-29029 May 2024 Issuance of Amendment Nos. 288 and 272 Adoption of TSTF-563 PLA-8126, Response to Request for Confirmation of Information Regarding Relief Request 1RR062024-05-29029 May 2024 Response to Request for Confirmation of Information Regarding Relief Request 1RR06 PLA-8122, Annual Radiological Environmental Operating Report (PLA-8122)2024-05-28028 May 2024 Annual Radiological Environmental Operating Report (PLA-8122) PLA-8123, Main Steam Isolation Valve Leakage2024-05-23023 May 2024 Main Steam Isolation Valve Leakage PLA-8115, Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115)2024-05-23023 May 2024 Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115) IR 05000387/20240012024-05-13013 May 2024 Integrated Inspection Report 05000387/2024001 and 05000388/2024001 IR 05000387/20244042024-05-0707 May 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000387/2024404 and 05000388/2024404 PLA-8094, Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-80942024-04-22022 April 2024 Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-8094 PLA-8095, 2023 Annual Radiological Environmental Operating Report (PLA-8095)2024-04-22022 April 2024 2023 Annual Radiological Environmental Operating Report (PLA-8095) ML24082A1372024-04-22022 April 2024 Issuance of Amendment Nos. 287 and 271 Adoption of TSTF-568, Revision 2 and Associated Technical Specification Changes PLA-8101, Re 2023 Annual Report of Radiation Exposure2024-04-22022 April 2024 Re 2023 Annual Report of Radiation Exposure PLA-8113, Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113)2024-04-11011 April 2024 Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113) PLA-8102, Annual Environmental Operating Report (Nonradiological) PLA-81022024-04-11011 April 2024 Annual Environmental Operating Report (Nonradiological) PLA-8102 PLA-8112, Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-81122024-04-0909 April 2024 Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-8112 PLA-8110, Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110)2024-04-0404 April 2024 Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110) PLA-8100, Property Insurance Program (PLA-8100)2024-04-0101 April 2024 Property Insurance Program (PLA-8100) ML24092A4022024-04-0101 April 2024 Annual Financial Report (PLA-8098) PLA-8109, Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109)2024-03-21021 March 2024 Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109) ML24067A2512024-03-19019 March 2024 Authorized Alternative to Requirements of the ASME Code PLA-8107, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance2024-03-19019 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance ML24044A2532024-03-14014 March 2024 Associated Independent Spent Fuel Storage Installation – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0077 (Security Notifications, Reports, and Recordkeeping & Suspicious Activity Reporting)) IR 05000387/20240112024-02-29029 February 2024 Commercial Grade Dedication Inspection Report 05000387/2024011 and 05000388/2024011 IR 05000387/20230062024-02-28028 February 2024 Annual Assessment Letter for Susquehanna Steam Electric Station, Units 1 and 2 (Reports 05000387/2023006 and 05000388/2023006) ML24039A1882024-02-27027 February 2024 Issuance of Amendment Nos. 286 and 270 Changes to Technical Specifications for Control Rods ML24037A3072024-02-22022 February 2024 Summary of Regulatory Audit in Support of Relief Request 5RR-02 PLA-8099, Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099)2024-02-13013 February 2024 Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099) IR 05000387/20230042024-02-0707 February 2024 Integrated Inspection Report 05000387/2023004 and 05000388/2023004 PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) IR 05000387/20230102023-12-11011 December 2023 Fire Protection Team Inspection Report 05000387/2023010 and 05000388/2023010 PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8088, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088)2023-12-0505 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088) 2024-09-06
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 May 27,2010 Mr. Timothy S. Rausch Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard Berwick, PA 18603-0467 SUSQUEHANNA STEAM ELECTRIC STATION, UNIT NOS. 1 AND 2 -PPL SUSQUEHANNA, LLC RE: CYBER SECURITY PLAN LICENSE AMENDMENT REQUEST (TAC NOS. ME2649 AND ME2650)
Dear Mr. Rausch:
By letter dated November 16, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No.
ML093290097), PPL Susquehanna, LLC (the licensee) submitted a license amendment request (LAR) for the Renewed Facility Operating Licenses for Susquehanna Steam Electric Station, Unit Nos. 1 and 2 (SSES 1 and 2). The proposed LAR includes the cyber security plan, proposed changes to Section 2 of the Renewed Facility Operating License, and a proposed Cyber Security Plan Implementation Schedule. The proposed cyber security plan has been submitted in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Section 73.54. The purpose of this letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) staff has completed an initial review of the LAR. In accordance with the Office of Nuclear Reactor Regulation Office Instruction L1C-109, "Acceptance Review Procedures," (ADAMS Accession No. ML091810088), Section 3.1.3, the NRC staff has decided to forgo the traditional acceptance review due to the complexity and "first-of-a-kind" nature of this application. While the NRC staff has docketed your application, we are not rendering a judgment as to the acceptability of the submittal within the context of an acceptance review. The cyber security plan submittal prepared for the SSES 1 and 2 is based on an earlier version of Nuclear Energy Institute (I\lEI) guidance. The NRC staff had significant generic concerns with this guidance. As a result of NRC staff discussions with NEI and the Executive Task Force of the industry Nuclear Security Working Group (NSWG), NEI and NSWG committed to representing operating power reactor licensees in resolving these generic concerns. Through numerous interactions, the NRC staff has communicated their generic concerns with the NEI guidance. The security-related nature of the information required these interactions to be conducted in closed meetings not open to the public. A publicly available list of the specific issues discussed with NEI and NSWG was communicated to the licensees via e-mail dated March 9, 2010 (ADAMS Accession No. ML100680284).
T. Rausch -2By letter dated April 28, 2010 (ADAMS Accession No. ML101180434), NEI submitted Revision 6 to NEI 08-09, "Cyber Security Plan for Nuclear Power Reactors," (ADAMS Accession No. ML101180437), which contains changes that address the NRC staff concerns associated with previous versions. Based on a technical review of the document, the Office of Nuclear Security and Incident Response, in its letter dated May 5,2010 (ADAMS Accession No. ML101190371), concluded that submission of a cyber security plan using the template provided in NEI 08-09, Revision 6, dated April 2010, would be acceptable for use by licensees to comply with the requirements of 10 CFR 73.54, with the exception of the definition of "cyber attack." Therefore, to resolve the NRC staff's concerns with the requested LAR, the licensee is requested to review the list of generic issues provided to the industry cyber security writing team and forwarded to all licensees via e-mail dated March 9, 2010, and provide a revised submittal. For those generic issues that will not be addressed in the revised submittal, please provide additional information or justification in the revised submittal. For any changes to the Cyber Security Plan proposed in the LAR, the licensee is requested to indicate that the revised submittal supersedes, in its entirety, the previous submittal (or indicate what portions are superseded). As an alternative to, and a potentially less resource intensive method than addressing the individual issues, the licensee may submit a revised Cyber Security Plan consistent with Regulatory Guide (RG) 5.71 1 or submit a revised Cyber Security Plan consistent with I\IEI08-09, Revision 6. However, if this option is exercised, the NRC staff expects that the existing application will be withdrawn and the revised application resubmitted at the same time. The NRC staff requests that the licensee's response or revised application be submitted within 60 days of the date of this letter. Please contact me if circumstances result in the need to revise the requested response date. Following receipt and review of your response, you will be advised by separate correspondence if any further information is needed to support the NRC staff's detailed technical review.
1 In January 2010, the NRC staff issued RG 5.71, "Cyber Security Programs for Nuclear Facilities" (ADAMS Accession No.
ML090340159). This guidance provides an approach that the NRC staff deems acceptable for complying with the Commission's regulations regarding the protection of digital computers, communications systems, and networks from a cyber security attack.
T. Rausch -3If you have any questions regarding this matter, please contact me at (301) 415-1030.
Sincerely, Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388 cc: Distribution via Listserv T. Rausch -If you have any questions regarding this matter, please contact me at (301) 415-1030.
Sincerely, Ira! Richard V. Guzman, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.
50-387 and 50-388 cc: Distribution via Listserv Distribution:
PUBLIC LPL1-1 r/f RidsNrrDorlLpL 1-1 RidsNrrPMSusquehanna RidsOgcMailCenter RidsN rrDorl DprResource RidsNrrLASLittle RidsAcrsAcnwMailCenter RidsRegion1 MailCenter CErlanger, NSIR PPederson, NSIR RidsNrrDirsltsb ADAMS Accession No ML101470262 OFFICE LPL 1-1/PM LPL 1-'I/LA LPL 1-1/BC NAME RGuzman SUttle NSalgado DATE 5/27/10 5/27/10 5/27/10 OFFICIAL RECORD