Category:Inspection Plan
MONTHYEARML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request ML24087A1822024-03-28028 March 2024 Notification of Target Set Inspection and Request for Information NRC Inspection Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 ML24052A1472024-02-28028 February 2024 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023006, 05000260/2023006 and 05000296/2023006 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 IR 05000259/20220062023-03-0101 March 2023 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022006, 05000260/2022006 and 05000296/2022006 ML23020A0602023-01-20020 January 2023 Long Term Steam Dryer Inspection Plan IR 05000259/20220052022-08-30030 August 2022 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022005, 05000260/2022005 and 05000296/2022005 ML22210A1342022-07-20020 July 2022 Requalification Inspection Notification Letter ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20224012022-03-0808 March 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000259/2022401; 05000260/2022401; 05000296/2022401 ML22091A1942022-03-0808 March 2022 2022 BFN POV Inspection Information Request IR 05000259/20210062022-03-0202 March 2022 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 (Report No. 05000259/2021006, 05000260/2021006 and 05000296/2021006 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) IR 05000259/20210052021-08-23023 August 2021 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2, and 3- Report Nos. 05000259/2021005, 05000260/2021005 and 5000296/2021005 IR 05000259/20200062021-03-0303 March 2021 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020006, 05000260/2020006 and 05000296/2020006 ML21047A4732021-02-16016 February 2021 Notification of Browns Ferry Nuclear Power Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2021010, 05000260/2021010, and 05000296/2021010 ML20338A3682020-12-0303 December 2020 Notification of Inspection and Request for Information ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information IR 05000259/20200052020-08-18018 August 2020 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020005, 05000260/2020005, and 05000296/2020005 ML20191A2232020-07-0909 July 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20190062020-03-0303 March 2020 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1,2,and 3 - NRC Report 05000259/2019006, 05000260/2019006, and 05000296/2019006 ML19108A1682019-04-18018 April 2019 EP Exercise Inspection RFI IR 05000259/20180062019-03-0404 March 2019 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2018006, 05000260/2018006 and 05000328/2018006 ML19030A6712019-01-25025 January 2019 U2 ISI RFI ML19024A4112019-01-24024 January 2019 Transmittal of RP Baseline Inspection Document Request 2019 ML18264A2052018-09-21021 September 2018 U1 ISI Emailed RFI Notification ML18059A1052018-02-28028 February 2018 EOC Assessment Letter ML18029A4672018-01-29029 January 2018 Notification of Browns Ferry Nuclear Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2018010, 05000260/2018010, and 05000296/2018010 ML18029A2552018-01-29029 January 2018 U3 RFI Email Request ML17236A1972017-08-24024 August 2017 Updated Inspection Plan ML17156A1612017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000259/20160062017-03-0101 March 2017 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Report 05000259/2016006, 05000260/2016006 and 05000296/2016006) IR 05000259/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Reports 05000259/2016005, 05000260/2016005 and 05000296/2016005 ML16243A2242016-08-30030 August 2016 Notification of Inspection and Request for Information ML16120A1182016-04-27027 April 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection - U.S. Nuclear Regulatory Commission Inspection Report Nos. 05000259/2016011, 05000260/2016011 and 05000296/2016011 IR 05000259/20150062016-03-0202 March 2016 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 NRC Inspection Reports 05000259/2015006, 05000260/2015006 and 05000296/2015006 ML16013A0812016-01-12012 January 2016 Browns Ferry Nuclear Plant, Unit 3 - Notification of Inspection and Request for Information ML15348A1802015-12-14014 December 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005 IR 05000259/20140012015-03-0404 March 2015 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 - NRC Inspection Reports 05000259/2014001, 05000260/2014001 and 05000296/2014001 IR 05000259/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 (NRC Inspection Reports 05000259/2014006, 05000260/2014006 and 05000296/2014006) ML14063A1092014-03-0404 March 2014 2013 Annual Assessment Letter for Browns Ferry ML14031A4122014-01-31031 January 2014 U3 2014002 ISI RFI Final - Copy ML13353A5852013-12-19019 December 2013 PIR Notification Letter 2014 ML13246A1842013-09-0303 September 2013 Mid Cycle Assessment Letter ML13084A0052013-03-25025 March 2013 Emergency Preparedness Inspection Notification and Request for Information 2024-09-24
[Table view] Category:Letter
MONTHYEARML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) ML24190A1292024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints ML24185A1512024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) ML24176A1022024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 ML24141A2462024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual CNL-24-036, – 10 CFR 50.46 Annual Report2024-04-25025 April 2024 – 10 CFR 50.46 Annual Report ML24116A2522024-04-25025 April 2024 Site Emergency Plan Implementing Procedure Revision ML24115A1652024-04-24024 April 2024 Breaker Trip Automatically Started an Emergency Diesel Generator 05000296/LER-2024-001, Primary Containment Isolation Valve Inoperable Due to Incorrect Motor Operated Valve Setup2024-04-22022 April 2024 Primary Containment Isolation Valve Inoperable Due to Incorrect Motor Operated Valve Setup CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A2302024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 2024-09-03
[Table view] |
See also: IR 05000259/2018010
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257
January 29, 2018
Mr. J. W. Shea
Vice President, Nuclear Licensing
Tennessee Valley Authority
1101 Market Street, LP 3D-C
Chattanooga, TN 37402-2801
SUBJECT: NOTIFICATION OF BROWNS FERRY NUCLEAR PLANT DESIGN BASES ASSURANCE INSPECTION - U.S. NUCLEAR REGULATORY COMMISSION INSPECTION REPORT 05000259/2018010, 05000260/2018010, AND
05000296/2018010
Dear Mr. Shea,
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC) Region II staff will conduct a Design Bases Assurance Inspection (DBAI) at your Browns Ferry Nuclear Plant during the weeks of April 30 and May 14, 2018. Mr. Geoffrey Ottenberg, a Senior
Reactor Inspector from the NRC's Region II office, will lead the inspection team. The inspection will be conducted in accordance with Inspection Procedure 71111.21M, "Design Bases
Assurance Inspection (Teams)," dated December 8, 2016 (ADAMS ML16238A320).
The inspection will evaluate the capability of components that have been modified and risk-
significant/low-margin components to function as designed and to support proper system operation. The inspection will also include a review of selected operator actions, operating
experience, and modifications.
During a telephone conversation on January 23, 2018, with Mr. Justin Garner, we confirmed
arrangements for an information-gathering site visit and the two-week onsite inspection. The
schedule is as follows:
- Information-gathering visit: Week of April 9, 2018
- Onsite weeks: Weeks of April 30 and May 14, 2018
The purpose of the information-gathering visit is to meet with members of your staff to identify
components that have been modified, risk-significant components and operator actions. Information and documentation needed to support the inspection will also be identified. Mr. Scott Freeman, a Region II Senior Risk Analyst, will support Mr. Ottenberg during the
information-gathering visit to review probabilistic risk assessment data and identify components to be examined during the inspection. Additionally, during the onsite weeks, time will be needed
on the plant-referenced simulator in order to facilitate the development of operator action-based scenarios.
J. Shea 2 The enclosure lists documents that will be needed prior to the information-gathering visit. Please provide the referenced information to the Region II Office by April 2, 2018. Additional
documents will be requested following the information-gathering visit. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for inspection preparation. The additional information will be needed in the Region II office by
April 20, 2018, to support the inspection team's preparation week. During the information-
gathering trip, Mr. Ottenberg will also discuss the following inspection support administrative
details: (1) availability of knowledgeable plant engineering and licensing personnel to serve as
points of contact during the inspection; (2) method of tracking inspector requests during the inspection; (3) licensee computer access; (4) working space; (5) arrangements for site access; and (6) other applicable information.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at
http://www.nrc.gov/reading-rm/adams.html
and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."
Thank you for your cooperation in this matter. If you have any questions, regarding the
information requested or the inspection, please contact Mr. Ottenberg at 404-997-4658 or
contact me at 404-997-4629.
Sincerely,
/RA/
Marvin D. Sykes, Chief Engineering Branch 1
Division of Reactor Safety
Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68
Enclosure:
Notification of Browns Ferry Nuclear Plant
Design Bases Assurance Inspection (Teams)
cc: Distribution via Listserv
____MLXXXXXXXXX__________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE GKO MDS1 NAME G. Ottenberg M. Sykes DATE 1/29/18 1/29/2018 E-MAIL COPY? YES NO YES NO
Enclosure INFORMATION REQUEST FOR BROWNS FERRY NUCLEAR PLANT DESIGN BASES ASSURANCE INSPECTION (TEAMS)
Please provide the information electronically in ".pdf" files, Excel, or other searchable format on CDROM (or FTP site, SharePoint, etc.). The CDROM (or website) should be indexed and
hyperlinked to facilitate ease of use. The requested items below, identified with an asterisk (*),
should have a date range from November 1, 2016, until present.
1. *List and brief description of
permanent and field work completed plant modifications including permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability analyses, calculations, and commercial grade
dedications. Include an index of systems (system numbers/designators and corresponding
names), the safety classification for each modification, and type of modification.
2. From your most recent probabilistic safety analysis (PSA)
excluding external events and
fires: a. Two risk rankings of components from your site-specific PSA: one sorted by Risk Achievement Worth (RAW), and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
c. A list of the top 500 LERF contributors
3. From your most recent PSA
including external events and fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by RAW, and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
4. Risk ranking of operator actions from your site-specific PSA sorted by RAW and human reliability worksheets for these items
5. List of time-critical operator actions with a brief description of each action
6. *List of components with low-design margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design-required output, heat exchangers close to
rated design heat removal, and motor-operated valve risk-margin rankings, etc.) and associated evaluations or calculations
7. *List and brief description of Root Cause Evaluations performed 8. *List and brief description of common-cause component failures that have occurred
9. List and brief description of equipment currently in degraded or nonconforming status as described in NRC Inspection Manual Chapter 0326, issued December 3, 2015 10. *List and brief description of Operability Determinations and Functionality Assessments
2 11. *List and reason for equipment that has been classified in maintenance rule (a)(1) status
12. *List of equipment on the site's Station Equipment Reliability Issues List, including a description of the reason(s) why each component is on that list, and summaries (if
available) of your plans to address the issue(s) along with dates added or removed from
the issues list
13. List of current "operator work arounds/burdens"
14. Copy of Updated Final Safety Analysis Report
15. Copy of Technical Specification(s)
16. Copy of Technical Specifications Bases
17. Copy of Technical Requirements Manual(s)
18. Copy of the Quality Assurance Program Manual
19. Copy of Corrective Action Program Procedure(s)
20. Copy of Operability Determination Procedure(s)
21. Copy of procedures addressing the following: Modifications, design changes, set point changes, equivalency evaluations or suitability analyses, commercial grade dedications, post-modifications testing, 10 CFR 50.59 screenings and evaluations, and UFSAR updates.
22. List of motor operated valves and air operated valves in the valve program, and their associated design margin and risk ranking
23. Primary AC and DC calculations for safety-related buses
24. One-line diagram of electrical plant (Electronic only)
25. Index and legend for electrical plant one-line diagrams
26. Piping and instrumentation diagrams (P&IDs) for safety-related systems (Electronic)
27. Index and legend for P&IDs
28. Index (procedure number, title, and current revision) of station Emergency Operating Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures
29. Copies of corrective action documents generated from previous CDBI
30. Copy of any self-assessments performed, and corrective action documents generated, in preparation for current DBAI
31. Contact information for a person to discuss PSA information prior to and during the information-gathering trip (Name, title, phone number, and e-mail address)