MONTHYEARML24303A2212024-10-29029 October 2024 NEI SDP Realism Presentation for October 30, 2024 Public Meeting ML24291A0062024-10-17017 October 2024 NEI Slide Presentation: ACRS Regulatory Policies and Practices - Draft White Paper on Nth-of-a-Kind (Noak) Micro-Reactor Licensing and Deployment Considerations - Sc - October 17, 2024 ML24267A0032024-09-25025 September 2024 NEI Slides for ROP Public Meeting Sept 2024 ML24263A2592024-09-17017 September 2024 06 Jim Slider NEI September 2024 NRC Ai Public Workshop 09-17-2024 ML24249A2012024-09-0909 September 2024 NEI Presentation - Sept 9 Public Meeting - Flooding DGs - Final ML24249A1152024-09-0505 September 2024 Power Uprate September 5, 2024 Public Meeting Slides ML24243A1612024-08-30030 August 2024 Slide Presentations for High Burnup (Hbu) Workshop V ML24228A2102024-08-20020 August 2024 2024 NEI Early Warning System (EWS) Presentation - NEI Slides ML24229A0012024-08-19019 August 2024 NEI - Spent Fuel Management: Safety and Efficiency Improvements Through Technology and Performance Margins - NRC PIRTs Public Meeting Rev. 8.15.2024 Final ML24218A1832024-07-30030 July 2024 NEI 7-30-24 Trial Use RG 1.247 Path Forward Final ML24197A0652024-07-17017 July 2024 SDP Realism Public Meeting NEI Presentation ML24172A1952024-06-27027 June 2024 NEI Slides for 06-27-2024 Public Meeting Structures as IROFS at Fuel Cycle Facilities ML24178A0372024-06-26026 June 2024 NRC Power Uprate Review Preparation June 26, 2024 Public Meeting Slides ML24164A1972024-06-17017 June 2024 Public Meeting Slides - NRC Staff Comments and Observations on NEI 10-01, Rev 2 Industry Guideline for Developing a Plant Parameter Envelope in Support of an Early Site Permit ML24130A1972024-05-0909 May 2024 NEI Presentation Slides on Rapid and Large-Scale Nuclear Reactor Deployments for Remote Industrial Applications - May 14 2024 Public Meeting ML24129A1382024-05-0808 May 2024 NEI Slides on Centralized Inspections for May 9, 2024 Public Workshop ML24114A1142024-04-18018 April 2024 NEI Supplemental Information on NRC Comments on NEI 20-07, Draft Revision E - April 18 Meeting (Non-Proprietary) ML24103A1532024-04-12012 April 2024 NEI Supplemental Information on NRC Comments of NEI 20-07 Rev E (Non-Proprietary) - Slides ML24092A3132024-04-0303 April 2024 Public Mtg_2024-04-03 Pre-submittal Meeting with the Nuclear Energy Institute (NEI) to Discuss an Update to NEI 03-12, Security Plan Template (Revision 8)_NEI Slides ML24088A2252024-03-26026 March 2024 NEI Slides for Centralized Inspections March 2024 ROP Public Meeting ML24075A2092024-03-14014 March 2024 NEI Advanced Reactor Di&C Task Force Slides - Accident Monitoring Instrumentation ML24075A2102024-03-14014 March 2024 NEI Alan Campbell Slides - Non-Safety-Related with Special Treatment – Digital Considerations ML24082A1792024-03-14014 March 2024 RIC-2024 TH18 True Slides ML24086A5342024-03-14014 March 2024 RIC 2024 TH23 Slides - the Industry’S Innovation Imperative ML24067A2592024-03-13013 March 2024 RIC-2024 W14 Slides - NEI-BHoltzman an Industry Perspective on Advanced Reactor Construction Oversight ML24067A0062024-03-0808 March 2024 1 - NRC - Workshop3 - Non-LOCA Release Fractions Feedback - Final ML24067A0072024-03-0808 March 2024 2 - NRC - Workshop3 - Non-LOCA - FFRD - Final ML24067A0092024-03-0808 March 2024 3 - NRC - Worshop3 - CR Dose Presentation - Final ML24067A0102024-03-0808 March 2024 4 - NRC - Workshop3 - EQ Presentation - Final ML24067A0122024-03-0808 March 2024 6 - NRC - Workshop3 - Best Estimate Dose ML24067A0132024-03-0808 March 2024 7 - NRC - Workshop3 - Closing Remarks ML24067A2882024-03-0808 March 2024 1 (Revised)-NRC_Workshop3_Non-LOCA Release Fraction Feedback-Final ML24043A1162024-02-13013 February 2024 3- EQ Presentation Workshop 2 ML24043A1192024-02-13013 February 2024 1- Impacts on RG 1.183 for Workshop2 ML24043A1202024-02-13013 February 2024 2- CR Dose Presentation Workshop 2 ML24016A2372024-01-17017 January 2024 NEI Environmental Reviews Slides Public Meeting 1-17-24 ML24010A0202024-01-11011 January 2024 Public Meeting on SLR Efficiencies - NEI Presentation ML24008A0442024-01-0909 January 2024 NEI - Slides for NRC Workshop 1 on Revision to RG 1.183 R1 - Final - ML24008A044 ML23342A0262023-12-14014 December 2023 December 14, 2023, Presentation on NEI 23-01 Operator Cold Licensing Training Plan for Advanced Nuclear Reactors ML23347A1782023-12-13013 December 2023 12-14 NEI EPRI Presentation NRC Public Meeting 16-03 R1 ML23303A1922023-10-30030 October 2023 NEI Slides for SLR Public Meeting - Oct 31 2023 ML23324A2392023-10-24024 October 2023 S1P6 - Hilary Lane - NRC AMT Workshop - Oct. 2023 ML23261C3792023-09-27027 September 2023 NEI 22-04 Pre-Submittal Meeting with NRC - September 27, 2023 ML23258A1992023-09-20020 September 2023 NEI 99-02 Draft Rev. 8 Update for Sept 2023 ROP Public Meeting ML23242A0782023-08-30030 August 2023 Hbu Workshop IV Industry Presentation: Drive to Deploy ATF with Increased Enrichment and Higher Burnup ML23242A1662023-08-30030 August 2023 the Future of Nuclear Power: 2023 Baseline Survey (Slides) ML23230A0142023-08-22022 August 2023 Industry Slide Presentation for 8-22-23 Meeting on ARCAP-TICAP and DG-1404 Guidance Documents ML23228A0042023-08-18018 August 2023 NEI Slides for Public Meeting to Discuss Possible Efficiencies on the Subsequent License Renewal Review - August 18, 2023 ML23191A0162023-07-11011 July 2023 NEI Comments on Risk-Informed Process for Evaluation (RIPE) DORL TSG - 7/11/23 Public Meeting Slides from NEI ML23191A0632023-07-0707 July 2023 NEI Cybersecurity Presentation for July 2023 ROP Public Meeting 2024-09-09
[Table view] |
Text
Transition of Non-Pilot Licensees to NFPA 805 NRC Public Meeting April 14, 2011
Purpose Discuss sequenced approach to LAR submittals Provide industry considerations that factored into sequencing Provide projected results and need for implementing sequenced approach Provide suggestions on LAR review approach and adjustment to monthly status meetings to support reviews
Sequenced NFPA 805 Application Current non-pilot plant submittals
- 23 LARs (33 units) by June 29, 2011
- LIC 109 reviews extended to 60 days
- Pilot reviews took over 2 years when originally estimated for only 6 months
- Review and SE issuance for 23 submittals will require multiple review teams to support a 2 year review timeframe
- the staff and the industry have underestimated the complexity and resources necessary to address the technical issues associated with review and approval of LARs for use of NFPA 805.
Sequenced NFPA 805 Application Impact of current submittal approach
- Opportunity lost to apply lessons learned or improvements in FPRA methodology
- Multiple review teams will result in inconsistent reviews
- Review period beyond 2 years places undue burden on licensees
- Risk of losing knowledgeable support
- Additional significant financial cost
Sequenced NFPA 805 Application Introduction of staggered approach
- NEI letters to NRC recommending staggered approach to LAR submittals
- ACRS Letter issued February 17, 2011
- SECY 11-0033 issued March 4, 2011
Sequenced NFPA 805 Application Benefits of sequenced submittals
- Allow application of any improvements developed in the FPRA methodology
- Incorporate lessons learned
- Pil Pilott iinformation f ti
- RAIs from early submittals
- More consistent reviews by limiting the number of required review teams
- Stable, predictable and efficient transition
Industry Considerations for Sequencing Management of fleet stations
- Internal resource utilization
- Incorporation of lessons learned
- Program consistency Station designs Fire PRA
- Status
- Approach
- Peer Review
Industry Considerations for Sequencing Fire PRA methodology improvements Other significant licensee applications
- License Renewal
- Risk informed applications
- EPU Outage and modification schedules Industry and vendor resources License Commitments FAQ closure
Projected Industry Submittals under Sequenced Approach Fiscal Year 2011 - 7 to 9 Fiscal Year 2012 - 10 to 12 Fiscal Year 2013 - 9 to 11
Enforcement Policy Revision SECY-11-0033 recommends staggered submittals and reviews of LARs Staff to submit policy paper recommending changes to Enforcement Policy Enforcement policy revision required now to preclude expending industry and staff resources on applications
LAR Review Approach Process reviewed and approved (NEI 04-02, FAQs, SE and LAR templates)
Suggest NRC review teams organized by subject matter experts/LAR sections Maximize M i i use off electronic l t i audit dit site it Sample review of items where licensee state compliance with NFPA 805 without conditions Industry will provide a matrix of sections requesting specific approval
Monthly Status Meetings Adjust monthly FAQ public meeting
- High level status of LAR reviews
- RAIs with generic applications
- Need for new FAQs Benefits
- Timely recognition and response to generic issues
- Maintain consistency in reviews and responses