{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of | |||
AMERENUE (Callaway Plant Unit 2) | |||
AP1000 DESIGN CERTIFICATION AMENDMENT | |||
(10 C.F.R. Part 52) | |||
CALVERT CLIFFS NUCLEAR PROJECT, L.L.C. | |||
(Calvert Cliffs Nuclear Power Plant, Unit 3) | |||
DETROIT EDISON CO. | |||
(Fermi Nuclear Power Plant, Unit 3) | |||
DUKE ENERGY CAROLINAS, L.L.C. (William States Lee III Nuclear Station, Units 1 and 2) | |||
ENERGY NORTHWEST (Columbia Generating Station) | |||
ENTERGY NUCLEAR GENERATION CO. and ENTERGY NUCLEAR OPERATIONS, INC. (Pilgrim Nuclear Power Station) | |||
ENTERGY NUCLEAR OPERATIONS, INC. | |||
(Indian Point Nuclear Generating Station, Units 2 and 3) | |||
ESBWR DESIGN CERTIFICATION AMENDMENT | |||
(10 C.F.R. Part 52) | |||
FIRSTENERGY NUCLEAR OPERATING CO. | |||
(Davis-Besse Nuclear Power Station, Unit 1) | |||
FLORIDA POWER AND LIGHT CO. | |||
(Turkey Point, Units 6 and 7) | |||
LUMINANT GENERATION CO. L.L.C. (Comanche Peak Nuclear Power Plant, Units 3 and 4) | |||
NEXTERA ENERGY SEABROOK, L.L.C. | |||
(Seabrook Station, Unit 1) | |||
PACIFIC GAS AND ELECTRIC CO. (Diablo Canyon Power Plant, Units 1 and 2) | |||
) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
Docket No. 52-037-COL | |||
NRC-2010-0131 | |||
RIN 3150-A18 | |||
Docket No. 52-016-COL | |||
Docket No. 52-033-COL | |||
Docket Nos. 52-018-COL, 52-019-COL | |||
Docket No. 50-397-LR | |||
Docket No. 50-293-LR | |||
Docket Nos. 50-247-LR, 50-286-LR NRC-2010-0135 RIN-3150-AI85 | |||
Docket No. 50-346-LR | |||
Docket Nos. 52-040-COL, 52-035-COL | |||
Docket Nos. 52-034-COL, 52-035-COL | |||
Docket No. 50-443-LR | |||
Docket Nos. 50-275-LR, 50-323-LR | |||
PPL BELL BEND, L.L.C. (Bell Bend Nuclear Power Plant) | |||
PROGRESS ENERGY CAROLINAS, INC. | |||
(Shearon Harris Nuclear Power Plant, Units 2 and 3) | |||
PROGRESS ENERGY FLORIDA, INC. | |||
(Levy County Nuclear Power Plant, Units 1 and 2) | |||
SOUTH CAROLINA ELECTRIC AND GAS CO. and SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (also referred to as SANTEE COOPER) | |||
(Virgil C. Summer Nuclear Station, Units 1 and 2) | |||
SOUTHERN NUCLEAR OPERATING CO. | |||
(Vogtle Electric Generating Plant, Units 3 and 4) | |||
SOUTH TEXAS PROJECT NUCLEAR OPERATING CO. | |||
(South Texas Project, Units 3 and 4) | |||
TENNESSEE VALLEY AUTHORITY (Bellefonte Nuclear Power Plant, Units 3 and 4) | |||
TENNESSEE VALLEY AUTHORITY (Watts Bar, Unit 2) | |||
VIRGINIA ELECTRIC AND POWER CO. d/b/a DOMINION VIRGINIA POWER and OLD DOMINION ELECTRIC COOPERATIVE (North Anna, Unit 3) | |||
) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) | |||
) | |||
) ) ) | |||
) | |||
) Docket No. 52-039-COL | |||
Docket Nos. 52-022-COL, 52-023-COL Docket Nos. 52-029-COL, 52-030-COL | |||
Docket Nos. 52-027-COL, 52-028-COL | |||
Docket Nos. 52-025-COL, 52-026-COL Docket Nos. 52-012-COL, 52-013-COL | |||
Docket Nos. 52-014-COL, 52-015-COL | |||
Docket No. 50-391-OL | |||
Docket No. 52-017-COL | |||
ORDER The Commission is in receipt of a petition to suspend adjudicatory, licensing, and rulemaking activities, and requesting other relief, in the captioned matters. | |||
1 This order is to set a schedule for further briefing. Any supplements to the petition may be filed no later than 1 See generally Emergency Petition to Suspend All Pending Reactor Licensing Decisions and Related Rulemaking Decisions Pending Investigation of Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident (served in various dockets between April 14, and April 18, 2011) (Petition). The Commission received a corrected petition on April 18, 2011. Thursday, April 21, 2011. | |||
2 Any person may file an answer to the petition, or a brief amicus curiae, no later than Monday, May 2, 2011. This order is issued pursuant to my authority under 10 C.F.R. §§ 2.346 (a) and (j). | |||
IT IS SO ORDERED. For the Commission NRC SEAL | |||
/RA/ ___________________________ Annette L. Vietti-Cook Secretary of the Commission | |||
Dated at Rockville, Maryland, this 19th day of April, 2011 | |||
2 See, e.g., Petition at 4 n.2. | |||
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of ) | |||
) | |||
TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL | |||
) | |||
(Watts Bar Nuclear Plant, Unit 2) ) ) ) | |||
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing SCHEDULING ORDER OF THE SECRETARY REGARDING PETITIONS TO SUSPEND ADJUDICATORY, LICENSING AND RULEMAKING ACTIVITIES have been served upon the following persons by the Electronic Information Exchange. | |||
U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel | |||
Mail Stop: T-3F23 Washington, DC 20555-0001 | |||
Lawrence G. McDade, Chair Administrative Judge E-mail: lgm1@nrc.gov | |||
Paul B. Abramson | |||
Administrative Judge E-mail: paul.abramson@nrc.gov | |||
Gary S. Arnold | |||
Administrative Judge | |||
E-mail: gary.arnold@nrc.gov Hillary Cain | |||
E-mail: hillary.cain@nrc.gov | |||
U.S. Nuclear Regulatory Commission Office of the General Counsel | |||
Mail Stop: O-15D21 Washington, DC 20555-0001 | |||
Edward L. Williamson, Esq. | |||
E-mail: edward.williamson@nrc.gov David E. Roth, Esq. | |||
E-mail: david.roth@nrc.gov Andrea Jones, Esq. | |||
E-mail: axj4@nrc.gov Brian P. Newell, Paralegal E-mail: brian.newell@nrc.gov | |||
OGC Mail Center | |||
E-mail: OGCMailCenter@nrc.gov U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Mail Stop: O-16C1 Washington, DC 20555-0001 | |||
OCAA Mail Center E-mail: ocaamail@nrc.gov U.S. Nuclear Regulatory Commission Office of the Secretary of the Commission Mail Stop: O-16C1 Washington, DC 20555-0001 | |||
Hearing Docket E-mail: hearingdocket@nrc.gov | |||
Docket No. 50-391-OL SCHEDULING ORDER OF THE SECRETARY REGARDING PETITIONS TO SUSPEND ADJUDICATORY, LICENSING AND RULEMAKING ACTIVITIES 2 Morgan, Lewis & Bockius, LLP Counsel for Tennessee Valley Authority | |||
1111 Pennsylvania Ave., N.W. | |||
Washington, DC 20004 | |||
Kathryn M. Sutton, Esq. | |||
E-mail: ksutton@morganlewis.com Paul M. Bessette, Esq. | |||
E-mail: pbessette@morganlewis.com Raphael P. Kuyler, Esq. rkuyler@morganlewis.com Esther Park, Esq. | |||
esther.park@morganlewis.com Jonathan M. Rund, Esq. | |||
jrund@morganlewis.com Mary L. Freeze, Legal Secretary E-mail: mfreeze@morganlewis.com Lena M. Long, Legal Secretary | |||
llong@morganlewis.com Angela M. Perry, Legal Secretary | |||
angela.perry@morganlewis.com | |||
Tennessee Valley Authority Office of the General Counsel | |||
400 W. Summit Hill Drive, WT 6A-K | |||
Knoxville, TN 37902 | |||
Edward J. Vigluicci, Esq. | |||
E-mail: ejvigluicci@tva.gov Harriet A. Cooper, Esq. | |||
E-mail: hacooper@tva.gov Christopher Chandler, Esq. | |||
E-mail: ccchandler0@tva.gov | |||
Diane Curran, Esq. | |||
Southern Alliance for Clean Energy (SACE) | |||
Harmon, Curran, Spielberg & Eisenberg, LLP 1726 M Street N.W., Suite 600 Washington, DC 20036 | |||
E-mail: dcurran@harmoncurran.com | |||
[Original signed by Nancy Greathead] | |||
Office of the Secretary of the Commission | |||
Dated at Rockville, Maryland this 19 th day of April 2011}} |
Revision as of 14:06, 8 August 2018
ML111091162 | |
Person / Time | |
---|---|
Site: | Watts Bar ![]() |
Issue date: | 04/19/2011 |
From: | Vietti-Cook A L NRC/SECY |
To: | |
SECY RAS | |
References | |
09-893-01-OL-BD01, RAS 19974, 50-391-OL | |
Download: ML111091162 (5) | |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of
AMERENUE (Callaway Plant Unit 2)
AP1000 DESIGN CERTIFICATION AMENDMENT
CALVERT CLIFFS NUCLEAR PROJECT, L.L.C.
(Calvert Cliffs Nuclear Power Plant, Unit 3)
DETROIT EDISON CO.
(Fermi Nuclear Power Plant, Unit 3)
DUKE ENERGY CAROLINAS, L.L.C. (William States Lee III Nuclear Station, Units 1 and 2)
ENERGY NORTHWEST (Columbia Generating Station)
ENTERGY NUCLEAR GENERATION CO. and ENTERGY NUCLEAR OPERATIONS, INC. (Pilgrim Nuclear Power Station)
ENTERGY NUCLEAR OPERATIONS, INC.
(Indian Point Nuclear Generating Station, Units 2 and 3)
ESBWR DESIGN CERTIFICATION AMENDMENT
FIRSTENERGY NUCLEAR OPERATING CO.
(Davis-Besse Nuclear Power Station, Unit 1)
FLORIDA POWER AND LIGHT CO.
(Turkey Point, Units 6 and 7)
LUMINANT GENERATION CO. L.L.C. (Comanche Peak Nuclear Power Plant, Units 3 and 4)
NEXTERA ENERGY SEABROOK, L.L.C.
(Seabrook Station, Unit 1)
PACIFIC GAS AND ELECTRIC CO. (Diablo Canyon Power Plant, Units 1 and 2)
) )
)
)
) ) )
)
)
)
) ) )
)
)
) ) )
)
)
)
) ) )
)
)
) ) )
)
)
)
) ) )
)
)
) ) )
)
)
) ) )
)
Docket No. 52-037-COL
RIN 3150-A18
Docket No. 52-016-COL
Docket No. 52-033-COL
Docket Nos. 52-018-COL, 52-019-COL
Docket No. 50-397-LR
Docket No. 50-293-LR
Docket Nos. 50-247-LR, 50-286-LR NRC-2010-0135 RIN-3150-AI85
Docket No. 50-346-LR
Docket Nos. 52-040-COL, 52-035-COL
Docket Nos. 52-034-COL, 52-035-COL
Docket No. 50-443-LR
Docket Nos. 50-275-LR, 50-323-LR
PPL BELL BEND, L.L.C. (Bell Bend Nuclear Power Plant)
PROGRESS ENERGY CAROLINAS, INC.
(Shearon Harris Nuclear Power Plant, Units 2 and 3)
PROGRESS ENERGY FLORIDA, INC.
(Levy County Nuclear Power Plant, Units 1 and 2)
SOUTH CAROLINA ELECTRIC AND GAS CO. and SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (also referred to as SANTEE COOPER)
(Virgil C. Summer Nuclear Station, Units 1 and 2)
SOUTHERN NUCLEAR OPERATING CO.
(Vogtle Electric Generating Plant, Units 3 and 4)
SOUTH TEXAS PROJECT NUCLEAR OPERATING CO.
(South Texas Project, Units 3 and 4)
TENNESSEE VALLEY AUTHORITY (Bellefonte Nuclear Power Plant, Units 3 and 4)
TENNESSEE VALLEY AUTHORITY (Watts Bar, Unit 2)
VIRGINIA ELECTRIC AND POWER CO. d/b/a DOMINION VIRGINIA POWER and OLD DOMINION ELECTRIC COOPERATIVE (North Anna, Unit 3)
) )
)
)
) ) )
)
)
) ) )
)
)
)
) ) )
)
)
) ) )
)
)
)
) ) )
)
) Docket No. 52-039-COL
Docket Nos. 52-022-COL, 52-023-COL Docket Nos. 52-029-COL, 52-030-COL
Docket Nos. 52-027-COL, 52-028-COL
Docket Nos. 52-025-COL, 52-026-COL Docket Nos. 52-012-COL, 52-013-COL
Docket Nos. 52-014-COL, 52-015-COL
Docket No. 50-391-OL
Docket No. 52-017-COL
ORDER The Commission is in receipt of a petition to suspend adjudicatory, licensing, and rulemaking activities, and requesting other relief, in the captioned matters.
1 This order is to set a schedule for further briefing. Any supplements to the petition may be filed no later than 1 See generally Emergency Petition to Suspend All Pending Reactor Licensing Decisions and Related Rulemaking Decisions Pending Investigation of Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident (served in various dockets between April 14, and April 18, 2011) (Petition). The Commission received a corrected petition on April 18, 2011. Thursday, April 21, 2011.
2 Any person may file an answer to the petition, or a brief amicus curiae, no later than Monday, May 2, 2011. This order is issued pursuant to my authority under 10 C.F.R. §§ 2.346 (a) and (j).
IT IS SO ORDERED. For the Commission NRC SEAL
/RA/ ___________________________ Annette L. Vietti-Cook Secretary of the Commission
Dated at Rockville, Maryland, this 19th day of April, 2011
2 See, e.g., Petition at 4 n.2.
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
TENNESSEE VALLEY AUTHORITY ) Docket No. 50-391-OL
)
(Watts Bar Nuclear Plant, Unit 2) ) ) )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing SCHEDULING ORDER OF THE SECRETARY REGARDING PETITIONS TO SUSPEND ADJUDICATORY, LICENSING AND RULEMAKING ACTIVITIES have been served upon the following persons by the Electronic Information Exchange.
U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23 Washington, DC 20555-0001
Lawrence G. McDade, Chair Administrative Judge E-mail: lgm1@nrc.gov
Paul B. Abramson
Administrative Judge E-mail: paul.abramson@nrc.gov
Gary S. Arnold
Administrative Judge
E-mail: gary.arnold@nrc.gov Hillary Cain
E-mail: hillary.cain@nrc.gov
U.S. Nuclear Regulatory Commission Office of the General Counsel
Mail Stop: O-15D21 Washington, DC 20555-0001
Edward L. Williamson, Esq.
E-mail: edward.williamson@nrc.gov David E. Roth, Esq.
E-mail: david.roth@nrc.gov Andrea Jones, Esq.
E-mail: axj4@nrc.gov Brian P. Newell, Paralegal E-mail: brian.newell@nrc.gov
OGC Mail Center
E-mail: OGCMailCenter@nrc.gov U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Mail Stop: O-16C1 Washington, DC 20555-0001
OCAA Mail Center E-mail: ocaamail@nrc.gov U.S. Nuclear Regulatory Commission Office of the Secretary of the Commission Mail Stop: O-16C1 Washington, DC 20555-0001
Hearing Docket E-mail: hearingdocket@nrc.gov
Docket No. 50-391-OL SCHEDULING ORDER OF THE SECRETARY REGARDING PETITIONS TO SUSPEND ADJUDICATORY, LICENSING AND RULEMAKING ACTIVITIES 2 Morgan, Lewis & Bockius, LLP Counsel for Tennessee Valley Authority
1111 Pennsylvania Ave., N.W.
Washington, DC 20004
Kathryn M. Sutton, Esq.
E-mail: ksutton@morganlewis.com Paul M. Bessette, Esq.
E-mail: pbessette@morganlewis.com Raphael P. Kuyler, Esq. rkuyler@morganlewis.com Esther Park, Esq.
esther.park@morganlewis.com Jonathan M. Rund, Esq.
jrund@morganlewis.com Mary L. Freeze, Legal Secretary E-mail: mfreeze@morganlewis.com Lena M. Long, Legal Secretary
llong@morganlewis.com Angela M. Perry, Legal Secretary
angela.perry@morganlewis.com
Tennessee Valley Authority Office of the General Counsel
400 W. Summit Hill Drive, WT 6A-K
Knoxville, TN 37902
Edward J. Vigluicci, Esq.
E-mail: ejvigluicci@tva.gov Harriet A. Cooper, Esq.
E-mail: hacooper@tva.gov Christopher Chandler, Esq.
E-mail: ccchandler0@tva.gov
Diane Curran, Esq.
Southern Alliance for Clean Energy (SACE)
Harmon, Curran, Spielberg & Eisenberg, LLP 1726 M Street N.W., Suite 600 Washington, DC 20036
E-mail: dcurran@harmoncurran.com
[Original signed by Nancy Greathead]
Office of the Secretary of the Commission
Dated at Rockville, Maryland this 19 th day of April 2011