Pursuant to the Boards March 11, 2013 Memorandum and Order (Requiring Update of Staff's Project Schedule) in the Matter of NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1),
Pursuant to the Boards March 11, 2013 Memorandum and Order (Requiring Update of Staff's Project Schedule) in the Matter of NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1),
the Staff informs the Board that the schedule for publishing the Final Supplemental Environmental Impact Statement has been delayed to June 2014. As previously noted, the Staff is currently unable to project a date for completion of the safety review.
the Staff informs the Board that the schedule for publishing the Final Supplemental Environmental Impact Statement has been delayed to June 2014. As previously noted, the Staff is currently unable to project a date for completion of the safety review.
Sincerely, Signed (electronically) by
Sincerely, Signed (electronically) by Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: November 7, 2013
_______________________________
Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: November 7, 2013


UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of                                        )
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of                                        )

Latest revision as of 00:22, 6 February 2020

NRC Staff'S November 2013 Status Update Letter in the Matter of Seabrook Station, Unit 1
ML13311A792
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 11/07/2013
From: Harris B
NRC/OGC
To: Kennedy M, Paul Ryerson, Richard Wardwell
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-443-LR, ASLBP 10-906-02-LR-BD01, RAS 25320
Download: ML13311A792 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 November 7, 2013 Administrative Judge Administrative Judge Paul S. Ryerson, Chair Dr. Richard E. Wardwell Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Dr. Michael F. Kennedy Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of NEXTERA ENERGY SEABROOK, LLC (Seabrook Station, Unit 1)

Docket No. 50-443-LR

Dear Administrative Judges:

Pursuant to the Boards March 11, 2013 Memorandum and Order (Requiring Update of Staff's Project Schedule) in the Matter of NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1),

the Staff informs the Board that the schedule for publishing the Final Supplemental Environmental Impact Statement has been delayed to June 2014. As previously noted, the Staff is currently unable to project a date for completion of the safety review.

Sincerely, Signed (electronically) by Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: November 7, 2013

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

NEXTERA ENERGY SEABROOK, LLC ) Docket No. 50-443-LR

)

(Seabrook Station, Unit 1) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing letter from Brian G. Harris to the Board, dated November 7, 2013, have been submitted through the E-filing System this 7th day of November, 2013.

/Signed (electronically) by/

Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: November 7, 2013