MONTHYEARML14029A4272013-10-31031 October 2013 G20130776 - Redacted, Owpsr Letter to NRC Dated 10/31/13 - New Information Regarding Seismic Hazards at the WPPSS-2/Columbia Generating Station Nuclear Power Plant Project stage: Other ML14007A0022014-01-0606 January 2014 NRR E-mail Capture - 10 CFR 2.206 Pre-Meeting Call and Requested Letter (G20130776; MF3031) Project stage: Request ML14050A3562014-02-0404 February 2014 G20130776/LTR-13-0866 - Transcript of 2/4/2014 Petition Review Board Conference Call with Charles Johnson, Oregon & Washington Physicians for Social Responsibility; 2.206 Petition Seismic Hazards at Columbia (TAC MF3031), Pages 1-33 Project stage: Other ML14035A5542014-02-0404 February 2014 NRR E-mail Capture - Reminder: PRB Pre-Meeting Phoncon on Tuesday, 2/4 Project stage: Request ML14050A3502014-02-25025 February 2014 G20130776/LTR-13-0866 - Memorandum to File and Transcript of 2/4/2014 Petition Review Board Conference Call with Charles Johnson, Oregon & Washington Physicians for Social Responsibility; 2.206 Petition Seismic Hazards at Columbia Project stage: Other ML14148A3582014-04-30030 April 2014 G20130776/LTR-13-0866 - Transcript of 4/30/2014 Petition Review Board Conference Call with Charles Johnson, Oregon & Washington Physicians for Social Responsibility; 2.206 Petition Seismic Hazards at Columbia Project stage: Other ML14121A0282014-04-30030 April 2014 NRR E-mail Capture - Testimony of Oregon and Washington Psr - Post-PRB Meeting for Columbia Seismic Concerns 2.206 Teleconference - 4/30/14 Project stage: Request ML14148A3392014-05-30030 May 2014 G20130776/LTR-13-0866 - Memorandum to File and Transcript of 4/30/2014 Petition Review Board Conference Call with Charles Johnson, Oregon & Washington Physicians for Social Responsibility; 2.206 Petition Seismic Hazards at Columbia Project stage: Other ML14162A4392014-06-0606 June 2014 G20130776/LTR-13-0866 - Correction Response, John Pearson, MD, Oregon & Washington Physicians for Social Responsibility; 2.206 Petition Seismic Hazards at Columbia Project stage: Other ML14148A3682014-06-0606 June 2014 G20130776/LTR-13-0866 - Response, John Pearson, MD, Oregon & Washington Physicians for Social Responsibility; 2.206 Petition Seismic Hazards at Columbia Project stage: Other 2014-02-04
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24296B1852024-10-16016 October 2024 NRR E-mail Capture - Final - Request for Additional Information - Columbia - Relief Request for Fourth Ten-Year Interval Inservice Testing - EPID: L-2024-LLR-0039 ML24291A1072024-10-16016 October 2024 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - Application to Revise TS to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements - EPID L-2024-LLA-0132 ML24215A3672024-08-0101 August 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station - License Amendment Request to Revise Emergency Plan - EPID L-2024-LLA-0011 ML24183A2392024-07-0101 July 2024 NRR E-mail Capture - LIC-109 Acceptance - Columbia Generating Station - Relief Request for the Fourth Ten-Year Interval Inservice Testing - EPID L-2024-LLR-0039 ML24169A0402024-06-14014 June 2024 NRR E-mail Capture - Final Request for Additional Information - Columbia Generating Station (Columbia) - Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs (L-2024-LLR-007 Through 0013) ML24103A2022024-04-0909 April 2024 EN 57068 - Transco Products Inc Part 21 Initial Notification of Unverified Critical Characteristics of Darmatt KM-1 Flat Board ML24060A1022024-02-28028 February 2024 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2023 Biological Monitoring Report ML24053A0092024-02-21021 February 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Relief Requests for the Fifth Ten-Year Interval Inservice Testing - EPIDs L-2024-LLR-0007 Through 00013 ML24008A0022024-01-0505 January 2024 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request for Application to Revise TS to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation - EPID L-2023-LLA-0170 ML23278A0042023-10-0404 October 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID L-2023-LLA-0128 ML23275A0092023-09-29029 September 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise Tech Specs to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling - EPID: L-2023-LLA-0128 ML23150A2502023-05-26026 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - License Amendment Request to Clean-Up Operating License and Appendix a, Technical Specifications - EPID L-2023-LLA-0062 ML23124A2412023-05-0404 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia - Application to Revise TS to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position - EPID L-2023-LLA-0063 ML23124A0062023-05-0303 May 2023 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise Tech Specs to Adopt TSTF-541, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2023-LLA-0063 ML23065A0422023-02-23023 February 2023 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Biological Monitoring Report ML22343A1802022-12-0808 December 2022 February 2023 Emergency Preparedness Program Inspection - Request for Information ML22349A2002022-12-0101 December 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Priority Pollutant Discharge Monitoring Report ML22312A0042022-11-0707 November 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Fourth 10 Year ISI RR 4ISI-11 - EPID L-2022-LLR-0071 ML22301A1432022-10-28028 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Adopt TSTF-505 - EPID L-2022-LLA-0023 ML22256A2002022-09-13013 September 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22241A0182022-08-26026 August 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22235A1052022-08-22022 August 2022 August 2022 Emergency Preparedness Exercise Inspection Request for Information ML22210A0072022-07-28028 July 2022 NRR E-mail Capture - Draft - Additional Audit Question - Columbia Generating Station - Regulatory Audit Question for LAR to Revise TS to Adopt TSTF-505, Revision 2 ML22173A0682022-06-17017 June 2022 Email Concurrence on SE Input for Columbia Pltr LAR ML22166A4122022-06-15015 June 2022 NRR E-mail Capture - LIC-109 Acceptance Review of LAR for Columbia Generating Station - Application to Revise TS to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling - EPID L-2022-LLA-0081 ML22144A0342022-05-18018 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22075A3392022-03-15015 March 2022 NRR E-mail Capture - Columbia Generating Station - Audit Questions - Regulatory Audit of License Amendment Request to Adopt 50.69 - Categorization Process - EPID L-2021-LLA-0207 ML22067A0132022-03-0707 March 2022 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of License Amendment Request to Adopt TSTF-505, Revision 2, Provide RISK-INFORMED Extended Completion Times - RITSTF Initiative 4b - EPID L-2022-LLA-0023 A002515, NRR E-mail Capture - (External Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report2022-01-12012 January 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2021 Priority Pollutant Discharge Monitoring Report ML21348A1852021-12-14014 December 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors - EPID L-2021-LLA-0207 ML21335A0182021-11-30030 November 2021 NRR E-mail Capture - Columbia Generating Station - LIC-109 Acceptance of Requested Licensing Action - License Amendment Request to Change TS 3.4.11 Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML21216A0502021-08-0303 August 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia - License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO EPID L-2021-LLA-0259 ML21209A9792021-07-28028 July 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21162A3062021-06-11011 June 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Adopt TSTF-546, Revise APRM Channel Adjustment Surveillance Requirement - EPID L-2021-LLA-0084 ML21137A0012021-05-14014 May 2021 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21120A1182021-04-30030 April 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 ML21109A2762021-04-0808 April 2021 Email Request for Information for Columbia Generating Station'S PIR Inspection_Redacted ML21068A2842021-03-0404 March 2021 2021002 Inservice Inspection (ISI) Request for Information (RFI) ML21036A2932021-02-0404 February 2021 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2020 Biological Monitoring Report ML20357B1502020-12-22022 December 2020 NRR E-mail Capture - LIC-109 Acceptance Review - Columbia - License Amendment Request - Adoption of TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Rev. 2 - EPID L-2020-LLA-0259 ML20336A1852020-11-30030 November 2020 NRR E-mail Capture - Final - RAI - Columbia - One -Time Exemption from 10 CFR 73, App B, Sect VI, Subsection C.3.(l)(1) Regarding Annual Force-On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20325A0402020-11-19019 November 2020 NRR E-mail Capture - Draft - RAI - Columbia - One -Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force -On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20314A0452020-11-0606 November 2020 NMFS to Energy Northwest, Entrainment Study Results for Columbia Generating Station ML20297A3032020-10-22022 October 2020 NRR E-mail Capture - LIC-109 Acceptance Review of License Amendment Request for Columbia - Application to Revise Tech Specs to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements - EPID L-2020-LLA-0212 ML20267A5162020-09-23023 September 2020 NRR E-mail Capture - Columbia Generating Station - Final - Request for Additional Information - Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-09 - EPID L-2020-LLR-0068 ML20265A3242020-09-20020 September 2020 Email 9-20-2020 - Req_ Kick-Off Call Columbia Generating Station RFI Provided for Roll-Back EP Program Inspection (Week of Nov 2 2020) ML20245E2822020-08-31031 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20239A9702020-08-26026 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20149K4362020-05-26026 May 2020 NRR E-mail Capture - Formal RAIs for Columbia (COVID-19) QA Plan Change Surveillance, Request Response by Tuesday June 2, 2020 ML20136A0112020-05-14014 May 2020 NRR E-mail Capture - Acceptance Columbia Relief Request ISI Reactor Pressure Vessel Feedwater Nozzles, 4ISI-09 2024-08-01
[Table view] |
Text
NRR-PMDAPEm Resource From: Lyon, Fred Sent: Monday, January 06, 2014 2:11 PM To: johnsonc20@gmail.com Cc: washpsr@gmail.com; Banic, Merrilee
Subject:
10 CFR 2.206 Pre-Meeting Call and Requested Letter (G20130776; MF3031)
Attachments: 10-4-13 EN letter to NRC re USACE Dam Analysis.pdf; cgs-seismic 2 206(v3).docx Mr. Johnson, as you requested, attached is the EN letter to NRC requesting USACE assistance. It is publicly available.
Energy Northwest is requesting that the USACE perform dam failure analyses for all upstream dams listed in FSAR Table 2.4-1. Additionally, Energy Northwest is requesting that the USACE perform dam failure analyses for the following upstream dams, which are not addressed in FSAR Table 2.4-1:
Noxon Rapids Revelstoke Post Falls Middle Channel O Sullivan North Corra Linn In addition, I spoke with Merrilee regarding additional participants on the pre-meeting call with the Petition Review Board. Petitioners have had other participants on the phoncon, and the POC (thats you) typically coordinates them, e.g., names, sequence, time allotment. The phoncon is limited to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, with about 45-50 minutes total for the petitioners; the rest for NRC comments.
Ill need to know about how many participants you expect, so that I know the number of telephone lines to reserve. It was good to finally make contact with you.
Ive also been informed that I can provide you with the NRCs Determination of Immediate Safety Concerns, which Ive attached, regarding your 10/31/13 letter. It provides the NRCs reasoning for not immediately shutting down Columbia while your petition is considered. The determination was approved by the Deputy Director of the NRC Office of Nuclear Reactor Regulation, Jennifer Uhle, on December 23, 2013.
Thanks, Fred Lyon, NRR project manager for Columbia Generating Station, et al.
1
Hearing Identifier: NRR_PMDA Email Number: 988 Mail Envelope Properties (Fred.Lyon@nrc.gov20140106141100)
Subject:
10 CFR 2.206 Pre-Meeting Call and Requested Letter (G20130776; MF3031)
Sent Date: 1/6/2014 2:11:23 PM Received Date: 1/6/2014 2:11:00 PM From: Lyon, Fred Created By: Fred.Lyon@nrc.gov Recipients:
"washpsr@gmail.com" <washpsr@gmail.com>
Tracking Status: None "Banic, Merrilee" <Merrilee.Banic@nrc.gov>
Tracking Status: None "johnsonc20@gmail.com" <johnsonc20@gmail.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 1607 1/6/2014 2:11:00 PM 10-4-13 EN letter to NRC re USACE Dam Analysis.pdf 126333 cgs-seismic 2 206(v3).docx 115296 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Columbia Generating Station Seismic Hazard Considerations Determination of Immediate Safety Concerns G20130776
Background:
- Seismic designs at US nuclear power plants are developed in terms of seismic ground motion spectra, which are called the Safe Shutdown Earthquake ground motion response spectra (SSE).
- Each nuclear power plant is designed to a ground motion level that is appropriate for the geology and tectonics in the region surrounding the plant location.
- Currently operating nuclear power plants developed their SSEs based on a deterministic or scenario earthquake that accounts for the largest earthquake expected in the area around the plant.
- The SSE for operating nuclear power plants in the U.S. is based on that earthquake which produces the maximum vibratory ground motion for which key structures, systems, and components are designed to remain functional.
- Due to code requirements and design standards, nuclear power plants are designed and built to have seismic margins generally well beyond the SSE level.
Evaluation:
- The seismic design for the Columbia Generating Station (CGS) plant is represented by the SSE ground motion response spectrum, as shown in Figure 1 below (solid curve).
o The CGS SSE spectrum is anchored at an acceleration level of 0.25 g, but is much higher (up to 0.6 g) over the important frequency range of 2 to 10 Hz where plant structures and systems are most sensitive to earthquake ground motions.
- Since the CGS operating license was issued in 1984, the licensee has reevaluated the seismic hazards for the plant as part of the Individual Plant Examination of External Events (IPEEE) program in the early-to mid-1990s.
o Under the IPEEE program, the licensee conducted a full probabilistic seismic hazard analysis for the region around the CGS plant, including an evaluation of earthquake activity in the Columbia Basin (including the Yakima fold belt) and the Cascadia subduction zone.
o The licensee evaluated the impact on the CGS plant from potential seismic ground motions from several regional seismic sources over a wide range of hazard levels (the 1/10,000 mean hazard levels are shown as circles in Figure 1 below).
o The licensee evaluated the seismic capacity or ruggedness of the CGS plant and determined that the risk of core damage from a seismic event is very low (2x10-5
2 per year).
- The Department of Energy (DOE) evaluated the seismic hazards for the seismic design of the Waste Treatment and Immobilization Plant (WTP) at the Hanford site in 1995, 2005, and 2007.
o The most recent WTP seismic design spectra are shown below as the dashed (2005) and dotted (2007) curves.
o The most recent seismic hazard evaluation for the design of the WTP in 2007 is very similar to the CGS seismic design or SSE.
o In its letter to the Chairman dated October 31, 2013, the Oregon and Washington Physicians for Social Responsibility (OWPSR) mistakenly compares the 3 to 5 Hz spectral acceleration level of 0.8g for the WTP 2005 seismic design with the CGS SSE 20 Hz and greater spectral acceleration value of 0.25g.
- Under Fukushima Near-Term Task Force Recommendation 2.1 (NTTF R2.1), the licensee (Energy Northwest) is currently reevaluating (along with DOE) the seismic hazards for the region surrounding the Hanford site using the latest data, models and methods, consistent with current NRC regulatory guidance.
o NTTF R2.1 specifies that the licensee will need to evaluate all of the potential seismic sources (including the Umtanum and Yakima Ridge faults) in the site region.
o All of the issues raised in the letter from OWPSR are known and are being evaluated as part of the seismic hazard reevaluation being conducted by DOE and Energy Northwest.
o If the reevaluated hazard is greater than the CGS plant seismic design or SSE, the licensee will perform a complete seismic risk evaluation for the plant as well as important interim actions while the risk evaluation is ongoing.
o The reevaluated hazard evaluation is due to the NRC in March 2015.
==
Conclusion:==
Based on the information discussed above, the NRC staff concludes that there is no immediate safety concern at CGS; however, the NRC will review the seismic hazard and risk evaluations conducted by Energy Northwest for potential regulatory action as part of its evaluation for NTTF R2.1.
3 Figure 1: SSE GROUND MOTION RESPONSE SPECTRUM Principal Contributors: Yong Li, NRR/DE/EMCB Cliff Munson, NRO/DSEA Date: December 18, 2013