| {{#Wiki_filter:February 1, 2018 | | {{#Wiki_filter:February 1, 2018 Mr. Brian H. Whitley, Director Regulatory Affairs Southern Nuclear Operating Company, Inc. |
| | | 42 Inverness Center Parkway, B022 Birmingham, AL 35242 |
| Mr. Brian H. Whitley, Director | |
| | |
| Regulatory Affairs | |
| | |
| Southern Nuclear Operating Company, Inc. | |
| 42 Inverness Center Parkway, B022 Birmingham, AL 35242 | |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4 - ISSUANCE OF AMENDMENTS AND GRANTING OF EXEMPTIONS REGARDING PIPE RUPTURE HAZARD AND FLOODING ANALYSIS (LAR-17-010) (EPID NO. | | VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4 ISSUANCE OF AMENDMENTS AND GRANTING OF EXEMPTIONS REGARDING PIPE RUPTURE HAZARD AND FLOODING ANALYSIS (LAR-17-010) (EPID NO. |
| L-2017-LLA-0143) | | L-2017-LLA-0143) |
|
| |
|
| ==Dear Mr. Whitley:== | | ==Dear Mr. Whitley:== |
|
| |
|
| In response to your application dated March 31, 2017, as supplemented and revised by letters dated August 21, October 9, November 1, December 1, and December 15, 2017, and January 3, 2018, titled, "Request for License Amendment and Exemption: Pipe Rupture Hazard and Flooding Analysis," and designated as License Amendment Request (LAR) 17-010, the U.S. | | In response to your application dated March 31, 2017, as supplemented and revised by letters dated August 21, October 9, November 1, December 1, and December 15, 2017, and January 3, 2018, titled, Request for License Amendment and Exemption: Pipe Rupture Hazard and Flooding Analysis, and designated as License Amendment Request (LAR) 17-010, the U.S. |
| Nuclear Regulatory Commission has granted the enclosed exemptions and issued the enclosed Amendments Nos. 107 and 106 to Combined License (COL) Nos. NPF-91 and NPF-92 for the Vogtle Electric Generating Plant Units 3 and 4, respectively. The application revises the COL Appendix C (and related plant-specific Tier 1 information) and associated Tier 2 information to address mitigation of fire protection system flooding of the Auxiliary Building identified during completion of the pipe rupture hazards analysis. | | Nuclear Regulatory Commission has granted the enclosed exemptions and issued the enclosed Amendments Nos. 107 and 106 to Combined License (COL) Nos. NPF-91 and NPF-92 for the Vogtle Electric Generating Plant Units 3 and 4, respectively. The application revises the COL Appendix C (and related plant-specific Tier 1 information) and associated Tier 2 information to address mitigation of fire protection system flooding of the Auxiliary Building identified during completion of the pipe rupture hazards analysis. |
| | | The exemptions allow a departure from elements of the certified information in Tier 1 of the AP1000 Certified Design Control Document, as specified in LAR-17-010. These exemptions are related to, and necessary for the granting of the amendments, which are being issued concurrently with these exemptions. |
| The exemptions allow a departure from elements of the certified information in Tier 1 of the AP1000 Certified Design Control Document, as specified in LAR-17-010. These exemptions are related to, and necessary for the granting of the amendments, which are being issued concurrently with these exemptions. | |
|
| |
|
| A copy of the related safety evaluation, which includes the evaluation of the amendments and exemptions, is also enclosed. The notice of issuance of the amendment and the exemption documents included in this letter will be published in the Federal Register. Sincerely, /RA/ William (Billy) Gleaves, Sr. Project Manager Licensing Branch 4 Division of New Reactor Licensing | | A copy of the related safety evaluation, which includes the evaluation of the amendments and exemptions, is also enclosed. The notice of issuance of the amendment and the exemption documents included in this letter will be published in the Federal Register. |
| | | Sincerely, |
| Office of New Reactors Docket Nos.: 52-025 52-026 | | /RA/ |
| | William (Billy) Gleaves, Sr. Project Manager Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors Docket Nos.: 52-025 52-026 |
|
| |
|
| ==Enclosures:== | | ==Enclosures:== |
| : 1. Amendment No. 107 to NPF-91 2. Amendment No. 106 to NPF-92 | | : 1. Amendment No. 107 to NPF-91 |
| | : 2. Amendment No. 106 to NPF-92 |
| : 3. Exemption for VEGP Unit 3 COL | | : 3. Exemption for VEGP Unit 3 COL |
| : 4. Exemption for VEGP Unit 4 COL | | : 4. Exemption for VEGP Unit 4 COL |
| : 5. Safety Evaluation | | : 5. Safety Evaluation cc: See next page |
| | |
| cc: See next page | |
| | |
| ML18017A721 - Package *via e-mail NRO-008 OFFICE DNRL/LB4: LA DNRL/LB4: PM DNRL/LB4: PM NRR/DEI/SEB: BC NAME RButler WGleaves (c) Chandu Patel SSammadar* DATE 1/18/2018 1/18/2018 1/30/18 1/18/2018 OFFICE NRO/DEI/ICE:BC NRO/DSRA/SPSB:BC NRO/DCIP/HOIB:BC NAME IJung* ADias*
| |
| ARivera-Varona* DATE 1/16/2018 1/18/2018 1/19/2018 OFFICE NRO/DCIP/RPAC: BC NRO/DEI/MEB: BC NRR/DE/EENB: BC NAME MDudek* TLupold* TMartinez-Navedo*
| |
| DATE 1/18/18 1/19/2018 1/16/2018 OFFICE DNRL/LB4: BC OGC/NLO NRO/DNRL: D NAME JDixon-Herrity *AWilson FAkstulewicz (MMcCoppin for)
| |
| DATE 2/1/18 1/30/2018 2/1/18
| |
| | |
| Vogtle Units 3 & 4 Mailing List (Revised 01/29/2018) cc: Southern Nuclear Operating Company Mr. Barty Simonton Document Control Coordinator Team Leader 42 Inverness Center Parkway, Bin 237 Environmental Radiation Program Birmingham, AL 35242 Air Protection Branch Environmental Protection Division Office of the Attorney General 4244 International Parkway, Suite 120 40 Capitol Square, SW Atlanta, GA 30354-3906 Atlanta, GA 30334 George B. Taylor, Jr. Resident Manager 2100 East Exchange Pl Oglethorpe Power Corporation Atlanta, GA 30084-5336 Alvin W. Vogtle Nuclear Plant 7821 River Road Brian H. Whitley Waynesboro, GA 30830 Regulatory Affairs Director Southern Nuclear Operating Company Anne F. Appleby 42 Inverness Center Parkway, BIN B237 Olgethorpe Power Corporation Birmingham, AL 35242 2100 East Exchange Place Tucker, GA 30084 Mr. Michael Yox Site Regulatory Affairs Director County Commissioner Vogtle Units 3 & 4 Office of the County Commissioner 7825 River Road, Bin 63031 Burke County Commission Waynesboro, GA 30830 Waynesboro, GA 30830 Mr. Wayne Guilfoyle Commissioner District 8 Augusta-Richmond County Commission
| |
| | |
| 4940 Windsor Spring Rd Hephzibah, GA 30815
| |
| | |
| Gwendolyn Jackson
| |
| | |
| Burke County Library 130 Highway 24 South
| |
| | |
| Waynesboro, GA 30830 Mr. Reece McAlister
| |
| | |
| Executive Secretary Georgia Public Service Commission
| |
| | |
| Atlanta, GA 30334 Resident Inspector
| |
| | |
| Vogtle Plant Units 3 & 4
| |
| | |
| 8805 River Road
| |
| | |
| Waynesboro, GA 30830 Page 1 of 3 Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)
| |
| ALPUGH@southernco.com (Amanda Pugh) annacom@westinghouse.com (Michael J. Annacone) awc@nei.org (Anne W. Cottingham)
| |
| | |
| becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)
| |
| Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crenshjw@westinghouse.com (John Crenshaw) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant)
| |
| | |
| fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis) G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams)
| |
| | |
| james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik)
| |
| | |
| jenmorri@southernco.com (Jennifer Buettner)
| |
| JHaswell@southernco.com (Jeremiah Haswell)
| |
| | |
| jim@ncwarn.org (Jim Warren)
| |
| John.Bozga@nrc.gov (John Bozga) Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) jtgasser@southernco.com (Jeff Gasser) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kdfili@southernco.com (Karen Fili)
| |
| Page 2 of 3 Vogtle Units 3 & 4 Mailing List
| |
| | |
| kmstacy@southernco.com (Kara Stacy)
| |
| KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler)
| |
| | |
| markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier)
| |
|
| |
|
| media@nei.org (Scott Peterson) Melissa.Smith@Hq.Doe.Gov (Melissa Smith)
| | ML18017A721 - Package *via e-mail NRO-008 OFFICE DNRL/LB4: LA DNRL/LB4: PM DNRL/LB4: PM NRR/DEI/SEB: BC NAME RButler WGleaves (c) Chandu Patel SSammadar* |
| Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price)
| | DATE 1/18/2018 1/18/2018 1/30/18 1/18/2018 OFFICE NRO/DEI/ICE:BC NRO/DSRA/SPSB:BC NRO/DCIP/HOIB:BC NAME IJung* ADias* ARivera-Varona* |
| | DATE 1/16/2018 1/18/2018 1/19/2018 OFFICE NRO/DCIP/RPAC: BC NRO/DEI/MEB: BC NRR/DE/EENB: BC NAME MDudek* TLupold* TMartinez-Navedo* |
| | DATE 1/18/18 1/19/2018 1/16/2018 OFFICE DNRL/LB4: BC OGC/NLO NRO/DNRL: D NAME JDixon-Herrity *AWilson FAkstulewicz (MMcCoppin for) |
| | DATE 2/1/18 1/30/2018 2/1/18 |
|
| |
|
| mlgraves@southernco.com (Michelle Graves)
| | Vogtle Units 3 & 4 Mailing List (Revised 01/29/2018) cc: |
| MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)
| | Southern Nuclear Operating Company Mr. Barty Simonton Document Control Coordinator Team Leader 42 Inverness Center Parkway, Bin 237 Environmental Radiation Program Birmingham, AL 35242 Air Protection Branch Environmental Protection Division Office of the Attorney General 4244 International Parkway, Suite 120 40 Capitol Square, SW Atlanta, GA 30354-3906 Atlanta, GA 30334 George B. Taylor, Jr. |
| Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)
| | Resident Manager 2100 East Exchange Pl Oglethorpe Power Corporation Atlanta, GA 30084-5336 Alvin W. Vogtle Nuclear Plant 7821 River Road Brian H. Whitley Waynesboro, GA 30830 Regulatory Affairs Director Southern Nuclear Operating Company Anne F. Appleby 42 Inverness Center Parkway, BIN B237 Olgethorpe Power Corporation Birmingham, AL 35242 2100 East Exchange Place Tucker, GA 30084 Mr. Michael Yox Site Regulatory Affairs Director County Commissioner Vogtle Units 3 & 4 Office of the County Commissioner 7825 River Road, Bin 63031 Burke County Commission Waynesboro, GA 30830 Waynesboro, GA 30830 Mr. Wayne Guilfoyle Commissioner District 8 Augusta-Richmond County Commission 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Resident Inspector Vogtle Plant Units 3 & 4 8805 River Road Waynesboro, GA 30830 Page 1 of 3 |
| Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi) rjarrett@southernco.com (Robyn Jarrett)
| |
| RJB@NEI.org (Russell Bell)
| |
| Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)
| |
| Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger)
| |
|
| |
|
| stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)
| | Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman) |
| TomClements329@cs.com (Tom Clements) Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino)
| | ALPUGH@southernco.com (Amanda Pugh) annacom@westinghouse.com (Michael J. Annacone) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley) |
| | Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crenshjw@westinghouse.com (John Crenshaw) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis) |
| | G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner) |
| | JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren) |
| | John.Bozga@nrc.gov (John Bozga) |
| | Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) jtgasser@southernco.com (Jeff Gasser) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kdfili@southernco.com (Karen Fili) |
| | Page 2 of 3 |
|
| |
|
| weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert) | | Vogtle Units 3 & 4 Mailing List kmstacy@southernco.com (Kara Stacy) |
| | KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson) |
| | Melissa.Smith@Hq.Doe.Gov (Melissa Smith) |
| | Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price) mlgraves@southernco.com (Michelle Graves) |
| | MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte) |
| | Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell) |
| | Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi) rjarrett@southernco.com (Robyn Jarrett) |
| | RJB@NEI.org (Russell Bell) |
| | Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton) |
| | Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller) |
| | TomClements329@cs.com (Tom Clements) |
| | Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert) |
| Page 3 of 3}} | | Page 3 of 3}} |
Letter Sequence Other |
---|
EPID:L-2017-LLA-0143, COL Docs - Draft RAI No.2 on Vogtle LAR-17-010 Pipe Rupture Hazard and Flooding Analysis (Approved, Closed) |
|
|
|
---|
Category:Exemption from NRC Requirements
MONTHYEARML24102A2662024-09-11011 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - FRN ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter ML24102A2652024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Exemption NL-24-0097, Exemption Request: Final Safety Analysis Report Update Schedule2024-03-22022 March 2024 Exemption Request: Final Safety Analysis Report Update Schedule ML24044A0732024-02-28028 February 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - January 2024 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23093A1012023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - Letter ML23093A1032023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - Exemption ML23094A1142023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Exemption ML23094A1192023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Letter ML23096A1902023-08-0101 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - Cover Letter ML23096A1952023-08-0101 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - Exemption ML22284A1322022-11-22022 November 2022 Exemption - Vogtle LAR-22-003 U4 Electrical ITAAC Consolidation Amendment NL-22-0583, Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment2022-08-12012 August 2022 Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment ML21279A1922021-11-23023 November 2021 Draft Federal Register Notice Regarding Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21320A0442021-11-23023 November 2021 FRN Exemption from the Requirements of 73.55(a)(4) and 73.56(a)(3) (EPID L-2021-LLE-0049)_Rev.1 ML21306A0022021-11-0404 November 2021 Request for Exemption: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load - Draft ML21299A0272021-10-31031 October 2021 Southern Nuclear Operating Company (SNC) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Draft Request for Exemption: Protected Area Declaration ML21237A2382021-10-15015 October 2021 Exemption Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2392021-10-15015 October 2021 Exemption Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21179A1762021-08-0505 August 2021 FRN for Issuance of Exemption - Farley and Vogtle FSAR Update Exemption - Rev 1 ML21179A1852021-08-0404 August 2021 Exemption - Farley and Vogtle - FSAR Update Exemption - Rev 1 ML21179A2042021-08-0404 August 2021 LTR - Farley and Vogtle - Exemption Transmittal Letter - FSAR Update Exemption - Rev 1. Exemptions from the Requirements of 10 CFR Part 50, Section 50.71(e)(4), Final Safety Analysis Report Update Schedule ML21071A0532021-07-30030 July 2021 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (Exemption) ML21189A1552021-07-0808 July 2021 Enclosure 1: Request for Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21189A1562021-07-0808 July 2021 Enclosure 2: Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test NL-21-0543, Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2021-06-0909 June 2021 Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule ML20329A3922020-12-0404 December 2020 Exemption from Annual Force-On-Force Exercise Requirement of 10 Cfr Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(I)(1) (EPID L 2020 Lle 0216 (Covid 19)) ML20315A3742020-12-0404 December 2020 Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(I)(1) (EPID L-2020-LLE-0183 (COVID-19)) NL-20-1254, Request for One-Time Exemptions from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic2020-11-0606 November 2020 Request for One-Time Exemptions from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic ML20132A0772020-08-0303 August 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) NL-20-0620, SNC Requests a Temporary Exemption from the Quarterly Fire Brigade Drills and Annual Live Fire Fighting Training Requirements of the Regulation2020-05-22022 May 2020 SNC Requests a Temporary Exemption from the Quarterly Fire Brigade Drills and Annual Live Fire Fighting Training Requirements of the Regulation ML20126G2662020-05-14014 May 2020 Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI ML20059N7872020-05-12012 May 2020 Exemption - LAR-19-010: Auxiliary Building Room Heatup ML20059N7902020-05-12012 May 2020 Exemption - LAR-19-010: Auxiliary Building Room Heatup ML20066G9042020-03-0606 March 2020 Request for Exemption from 10 CFR Part 50, Appendix E Exercise Requirements ND-20-0204, Enclosure 1 - Vogtle Electric Generating Plant (VEGP) Unit 4, Exemption Request 10 CFR Part 50, Appendix E Exercise Requirements2020-03-0606 March 2020 Enclosure 1 - Vogtle Electric Generating Plant (VEGP) Unit 4, Exemption Request 10 CFR Part 50, Appendix E Exercise Requirements ML19350C6272020-01-28028 January 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) ML19350C6612020-01-28028 January 2020 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19361A1092020-01-13013 January 2020 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-003) ML19361A1192020-01-13013 January 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 19-003) ML19337A7412019-12-27027 December 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-002) Exemption from Regulations Set Forth in Appendix D of 10CFR52 ML19337B1392019-12-27027 December 2019 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-002) Exemption from Regulations Set Forth in Appendix D of 10CFR52 ML19164A2652019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) ML19164A2662019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) NL-19-0801, Quality Assurance Topical Report Submittal, Request for Schedular Exemption - 10 CFR 50.54(a)(3)2019-10-31031 October 2019 Quality Assurance Topical Report Submittal, Request for Schedular Exemption - 10 CFR 50.54(a)(3) ML19238A3512019-09-27027 September 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 LAR 19-004 ML19239A0892019-09-27027 September 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 LAR 19-004 ND-19-0782, Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015)2019-08-0909 August 2019 Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015) 2024-09-09
[Table view] Category:Letter
MONTHYEARNL-24-0385, Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator2024-10-31031 October 2024 Request for Action Matrix Deviation Due to Recent Events Impacting the Unplanned Scram with Complications Performance Indicator IR 05000424/20240032024-10-30030 October 2024 – Integrated Inspection Report 05000424/2024003 and 05000425/2024003 NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 NL-24-0386, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information2024-10-28028 October 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks Response to Request for Additional Information NL-24-0366, Core Operating Limits Report, Cycle 26, Version 12024-10-25025 October 2024 Core Operating Limits Report, Cycle 26, Version 1 ML24297A6482024-10-23023 October 2024 5 to the Updated Final Safety Analysis Report, Technical Specification Bases Changes, Technical Requirements Manual Changes, Summary Report and Revised NRC Commitments Report ML24269A2502024-09-26026 September 2024 Acknowledgement of the Withdrawal of the Requested Exemption and License Amendment Request to Remove Tier 1 and Tier 2* Requirements NL-24-0369, Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements2024-09-25025 September 2024 Withdrawal of License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2 Requirements NL-24-0350, Core Operating Limits Report, Cycle 24, Version 22024-09-25025 September 2024 Core Operating Limits Report, Cycle 24, Version 2 ML24243A0072024-09-10010 September 2024 – Correction of Amendment Nos. 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-14483 ML24102A2642024-09-0909 September 2024 – Exemption Request Regarding Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0013) - Letter NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A2942024-09-0606 September 2024 Correction of Amendment Nos. 218 and 201 Regarding Revision to Technical Specifications to Use Online Monitoring Methodology 05200025/LER-2024-002, Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve2024-09-0505 September 2024 Manual Reactor Protection System and Automatic Safeguards Actuation Due to an Unexpected Change in Position of a Main Feedwater Pump Minimum Flow Control Valve IR 05000424/20240052024-08-26026 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 and 2 - Report 05000424/2024005 and 05000425/2024005 ML24235A1952024-08-22022 August 2024 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 and 4 - Report 05200025/2024005 and 05200026/2024005 IR 05000424/20244012024-08-15015 August 2024 4 - Security Baseline Inspection Report 05000424-2024401, 05000425-2024401, 05200025-2024402, and 05200026-2024403 - Cover Letter NL-24-0299, Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information2024-08-14014 August 2024 Exemption Request: Final Safety Analysis Report Update Schedule, Response to Request for Additional Information 05000425/LER-2024-001, Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod2024-08-0909 August 2024 Manual Actuation of the Reactor Protection System Due to a Rod Control Fuse Opening Causing a Misaligned Shutdown Rod ML24218A1842024-08-0707 August 2024 Examination Report and Cover Letter 05200026/LER-2024-001, Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal2024-08-0606 August 2024 Manual Reactor Protection System Actuation Due to Procedure Not Optimally Sequenced to Reset the Rapid Power Reduction Signal ML24212A1442024-08-0101 August 2024 Integrated Inspection Report 05200025/2024002 and 05200026/2024002 IR 05000424/20240022024-07-29029 July 2024 Integrated Inspection Report 05000424/2024002 and 05000425/2024002 IR 05000424/20244042024-07-26026 July 2024 Material Control and Accounting Program Inspection Report 05000424/2024404 and 05000425/2024404 (Cover Letter) NL-24-0282, License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements2024-07-25025 July 2024 License Amendment Request and Exemption Request: Remove Tier 1 and Tier 2* Requirements NL-24-0126, – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.62024-07-25025 July 2024 – Units 3 and 4, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Action a and SR 3.7.6.6 ML24204A0722024-07-23023 July 2024 Issuance of Amendment No. 225, Regarding LAR to Revise TS 3.7.9 for a one-time Change to Support Nuclear Service Cooling Water Transfer Pump Repairs - Emergency Circumstances NL-24-0286, Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair2024-07-20020 July 2024 Emergency Request to Revise Technical Specification 3.7.9 for a One-Time Change to Support a Unit 1 Nuclear Service Cooling Water Transfer Pump Repair NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24191A4562024-07-19019 July 2024 Request for Relief and Alternative Requirements for Squib (Explosively Actuated) Valves First Test Interval ML24194A0342024-07-12012 July 2024 Review of the Refueling Outage 1R24 Steam Generator Tube Inspection Report ML24191A3792024-07-10010 July 2024 – Initial Test Program and Operational Programs Inspection Report 05200026/2024011 NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0087, License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks2024-06-21021 June 2024 License Amendment Request: Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Air Storage Tanks NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) NL-24-0243, Registration of Spent Fuel Cask Use2024-06-18018 June 2024 Registration of Spent Fuel Cask Use ML24163A0632024-06-12012 June 2024 2024 Licensed Operator Re-qualification Inspection Notification Letter Vogtle, Units 3 & 4 ML24155A1772024-06-0505 June 2024 Regulatory Audit in Support of Review of the LAR to Revise Emergency Diesel Generator Frequency and Voltage Ranges for Technical Specification 3.8.1, Surveillance Requirements NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24094A1402024-05-16016 May 2024 Staff Response to Request for Revision to NRC Staff Assessment of Updated Seismic Hazard Information and Latest Understanding of Seismic Hazards at the Vogtle Plant Site Following the NRC Process for the Ongoing Assessment of Natural Hazard ML24130A2412024-05-13013 May 2024 Integrated Inspection Report 05200025/2024001 and 05200026/2024001 ML24120A1812024-05-13013 May 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage IR24 Steam Generator Tube Inspection Report – Enclosure 2 ML24101A2112024-05-11011 May 2024 Expedited Issuance of Amendment No. 198 Change to Technical Specification 5.5.13, Ventilation Filter Testing Program (VFTP) NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 ML24127A2372024-05-0909 May 2024 Initial Test Program and Operational Programs Inspection Report 05200026/2024010 NL-24-0194, Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1)2024-05-0707 May 2024 Revised Request for Relief and Alternative Requirements for Squib Valves First Test Interval (V34-IST-ALT-03-R1) ML24120A2832024-04-30030 April 2024 Project Manager Reassignment 2024-09-09
[Table view] Category:License-Combined License (COL) (New/Renewal/Amendments) DKT 52
MONTHYEARML23243B0542023-12-19019 December 2023 VEGP Unit 4 Amendment No. 193 - Enclosure 2 ML23243A9682023-12-19019 December 2023 VEGP Unit 3 Amendment No. 197 - Enclosure 1 ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action ML23159A0972023-07-31031 July 2023 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 23-001) ML23072A2722023-05-0101 May 2023 Enclosure 1 - LAR 22-005 Amendment No. 191 Vogtle Unit 3 ML23072A2732023-05-0101 May 2023 Enclosure 2 - LAR 22-005 Amendment No. 188 Vogtle, Unit 4 ML23072A2762023-05-0101 May 2023 Attachment to Enclosure 2 - VEGP U4 Amendment 188 LAR-22-005 ML23037A0892023-02-0808 February 2023 Amendment - Vogtle Unit 3 Amendment No. 190, Tech Spec Exceptions for In-Containment Refueling Water Storage Tank Operability Prior to Initial Criticality (Exigent Circumstances) ML20290A2822022-08-0303 August 2022 Finding That Acceptance Criteria in the Combined License Are Met (10 CFR 103g - Finding) ML21237A2342021-10-15015 October 2021 Amendment Unit 3 - Vogtle Electric Generating Plant LAR 21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2352021-10-15015 October 2021 Attachment Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2372021-10-15015 October 2021 Attachment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2362021-10-15015 October 2021 Amendment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 ML20314A0132020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-005) ML20314A0142020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 184 (LAR-20-005) ML20314A0102020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-005) ML20314A0112020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 186 (LAR-20-005) ML20247J4612020-10-14014 October 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 4 (LAR 20-004) ML20247J4592020-10-14014 October 2020 Amendment 185 - Vogtle Electric Generating Plant Unit 3 (LAR 20-004) ML20237F4922020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 184 (LAR-20-003) ML20237F4942020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 182 (LAR-20-003) ML20237F4932020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-003) ML20237F4912020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-003) ML20196L6772020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 183 for LAR-20-002 ML20196L6782020-08-11011 August 2020 Amendment 181 - Vogtle Electric Generating Plant Unit 4 for LAR 20-002 ML20196L6792020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 4 for Amendment 181 for LAR-20-002 ML20132A0762020-08-0404 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ML20059N7792020-05-12012 May 2020 Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20059N7822020-05-12012 May 2020 Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1632020-05-12012 May 2020 Attachment to Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1622020-05-12012 May 2020 Attachment to Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20120A0072020-04-30030 April 2020 Attachment for Amendment 178 Cyber Security Plan Changes (LAR-19-020) ML20106F1592020-04-30030 April 2020 Attachment for Amendment 179 Cyber Security Plan Changes (LAR-19-020) ML20057E1172020-04-30030 April 2020 Amendment 178 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20057E1062020-04-30030 April 2020 Amendment 179 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20064E6682020-03-23023 March 2020 Enclosure 4: Supplemental Attachment to License Amendment No. 148 for COL No. NPF-91 ML20064E6802020-03-23023 March 2020 Enclosure 5: Supplemental Attachment to License Amendment No. 147 for COL No. NPF-92 ML20064E5722020-03-23023 March 2020 Supplemental Attachment to License Amendment No. 36 for COL No. NPF-92 ML20064E6122020-03-23023 March 2020 Enclosure 2: Supplemental Attachment to License Amendment No. 125 for COL No. NPF-91 ML20064E6282020-03-23023 March 2020 Enclosure 3: Supplemental Attachment to License Amendment No. 124 for COL No. NPF-92 ML20013G6882020-02-0303 February 2020 Amendment - Vogtle Electric Generating Plant Unit 4 ML19350C7002020-01-28028 January 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015).d ML19350C7142020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19350C6862020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) 2023-07-31
[Table view] |
Text
February 1, 2018 Mr. Brian H. Whitley, Director Regulatory Affairs Southern Nuclear Operating Company, Inc.
42 Inverness Center Parkway, B022 Birmingham, AL 35242
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4 ISSUANCE OF AMENDMENTS AND GRANTING OF EXEMPTIONS REGARDING PIPE RUPTURE HAZARD AND FLOODING ANALYSIS (LAR-17-010) (EPID NO.
L-2017-LLA-0143)
Dear Mr. Whitley:
In response to your application dated March 31, 2017, as supplemented and revised by letters dated August 21, October 9, November 1, December 1, and December 15, 2017, and January 3, 2018, titled, Request for License Amendment and Exemption: Pipe Rupture Hazard and Flooding Analysis, and designated as License Amendment Request (LAR)17-010, the U.S.
Nuclear Regulatory Commission has granted the enclosed exemptions and issued the enclosed Amendments Nos. 107 and 106 to Combined License (COL) Nos. NPF-91 and NPF-92 for the Vogtle Electric Generating Plant Units 3 and 4, respectively. The application revises the COL Appendix C (and related plant-specific Tier 1 information) and associated Tier 2 information to address mitigation of fire protection system flooding of the Auxiliary Building identified during completion of the pipe rupture hazards analysis.
The exemptions allow a departure from elements of the certified information in Tier 1 of the AP1000 Certified Design Control Document, as specified in LAR-17-010. These exemptions are related to, and necessary for the granting of the amendments, which are being issued concurrently with these exemptions.
A copy of the related safety evaluation, which includes the evaluation of the amendments and exemptions, is also enclosed. The notice of issuance of the amendment and the exemption documents included in this letter will be published in the Federal Register.
Sincerely,
/RA/
William (Billy) Gleaves, Sr. Project Manager Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors Docket Nos.: 52-025 52-026
Enclosures:
- 1. Amendment No. 107 to NPF-91
- 2. Amendment No. 106 to NPF-92
- 3. Exemption for VEGP Unit 3 COL
- 4. Exemption for VEGP Unit 4 COL
- 5. Safety Evaluation cc: See next page
ML18017A721 - Package *via e-mail NRO-008 OFFICE DNRL/LB4: LA DNRL/LB4: PM DNRL/LB4: PM NRR/DEI/SEB: BC NAME RButler WGleaves (c) Chandu Patel SSammadar*
DATE 1/18/2018 1/18/2018 1/30/18 1/18/2018 OFFICE NRO/DEI/ICE:BC NRO/DSRA/SPSB:BC NRO/DCIP/HOIB:BC NAME IJung* ADias* ARivera-Varona*
DATE 1/16/2018 1/18/2018 1/19/2018 OFFICE NRO/DCIP/RPAC: BC NRO/DEI/MEB: BC NRR/DE/EENB: BC NAME MDudek* TLupold* TMartinez-Navedo*
DATE 1/18/18 1/19/2018 1/16/2018 OFFICE DNRL/LB4: BC OGC/NLO NRO/DNRL: D NAME JDixon-Herrity *AWilson FAkstulewicz (MMcCoppin for)
DATE 2/1/18 1/30/2018 2/1/18
Vogtle Units 3 & 4 Mailing List (Revised 01/29/2018) cc:
Southern Nuclear Operating Company Mr. Barty Simonton Document Control Coordinator Team Leader 42 Inverness Center Parkway, Bin 237 Environmental Radiation Program Birmingham, AL 35242 Air Protection Branch Environmental Protection Division Office of the Attorney General 4244 International Parkway, Suite 120 40 Capitol Square, SW Atlanta, GA 30354-3906 Atlanta, GA 30334 George B. Taylor, Jr.
Resident Manager 2100 East Exchange Pl Oglethorpe Power Corporation Atlanta, GA 30084-5336 Alvin W. Vogtle Nuclear Plant 7821 River Road Brian H. Whitley Waynesboro, GA 30830 Regulatory Affairs Director Southern Nuclear Operating Company Anne F. Appleby 42 Inverness Center Parkway, BIN B237 Olgethorpe Power Corporation Birmingham, AL 35242 2100 East Exchange Place Tucker, GA 30084 Mr. Michael Yox Site Regulatory Affairs Director County Commissioner Vogtle Units 3 & 4 Office of the County Commissioner 7825 River Road, Bin 63031 Burke County Commission Waynesboro, GA 30830 Waynesboro, GA 30830 Mr. Wayne Guilfoyle Commissioner District 8 Augusta-Richmond County Commission 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Resident Inspector Vogtle Plant Units 3 & 4 8805 River Road Waynesboro, GA 30830 Page 1 of 3
Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)
ALPUGH@southernco.com (Amanda Pugh) annacom@westinghouse.com (Michael J. Annacone) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)
Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crenshjw@westinghouse.com (John Crenshaw) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis)
G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner)
JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)
John.Bozga@nrc.gov (John Bozga)
Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) jtgasser@southernco.com (Jeff Gasser) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kdfili@southernco.com (Karen Fili)
Page 2 of 3
Vogtle Units 3 & 4 Mailing List kmstacy@southernco.com (Kara Stacy)
KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson)
Melissa.Smith@Hq.Doe.Gov (Melissa Smith)
Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price) mlgraves@southernco.com (Michelle Graves)
MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)
Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)
Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi) rjarrett@southernco.com (Robyn Jarrett)
RJB@NEI.org (Russell Bell)
Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)
Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)
TomClements329@cs.com (Tom Clements)
Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert)
Page 3 of 3