|
---|
Category:Exemption from NRC Requirements
MONTHYEARML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23093A1012023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - Letter ML23093A1032023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (EPID L-2022-LLE-0020) - Exemption ML23094A1142023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Exemption ML23094A1192023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Letter ML23096A1902023-08-0101 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - Cover Letter ML23096A1952023-08-0101 August 2023 Exemption from the Requirements of 10 CFR 50, Appendix K, ECCS (Emergency Core Cooling Systems) Evaluation Models (EPID L-2022-LLE-0021) - Exemption ML22284A1322022-11-22022 November 2022 Exemption - Vogtle LAR-22-003 U4 Electrical ITAAC Consolidation Amendment NL-22-0583, Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment2022-08-12012 August 2022 Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment ML21279A1922021-11-23023 November 2021 Draft Federal Register Notice Regarding Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21320A0442021-11-23023 November 2021 FRN Exemption from the Requirements of 73.55(a)(4) and 73.56(a)(3) (EPID L-2021-LLE-0049)_Rev.1 ML21306A0022021-11-0404 November 2021 Request for Exemption: Applicability of 10 CFR 26.3, Scope, Until Initial Fuel Load - Draft ML21299A0272021-10-31031 October 2021 Southern Nuclear Operating Company (SNC) Vogtle Electric Generating Plant (VEGP) Units 3 and 4 Draft Request for Exemption: Protected Area Declaration ML21237A2382021-10-15015 October 2021 Exemption Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2392021-10-15015 October 2021 Exemption Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21179A1762021-08-0505 August 2021 FRN for Issuance of Exemption - Farley and Vogtle FSAR Update Exemption - Rev 1 ML21179A1852021-08-0404 August 2021 Exemption - Farley and Vogtle - FSAR Update Exemption - Rev 1 ML21179A2042021-08-0404 August 2021 LTR - Farley and Vogtle - Exemption Transmittal Letter - FSAR Update Exemption - Rev 1. Exemptions from the Requirements of 10 CFR Part 50, Section 50.71(e)(4), Final Safety Analysis Report Update Schedule ML21071A0532021-07-30030 July 2021 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors (Exemption) ML21189A1552021-07-0808 July 2021 Enclosure 1: Request for Exemption from Operator Written Examination and Operating Test for Unit 4 Licenses ML21189A1562021-07-0808 July 2021 Enclosure 2: Unit 4 Operator Candidates Requesting Credit for Unit 3 Written Examination and Operating Test NL-21-0543, Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2021-06-0909 June 2021 Units 1 and 2 and Vogtle Electric Generating Plant - Units 1 and 2, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule ML20329A3922020-12-0404 December 2020 Exemption from Annual Force-On-Force Exercise Requirement of 10 Cfr Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(I)(1) (EPID L 2020 Lle 0216 (Covid 19)) ML20315A3742020-12-0404 December 2020 Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel Subsection VI C.3(I)(1) (EPID L-2020-LLE-0183 (COVID-19)) NL-20-1254, Request for One-Time Exemptions from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic2020-11-0606 November 2020 Request for One-Time Exemptions from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to COVID-19 Pandemic ML20132A0772020-08-0303 August 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) NL-20-0620, SNC Requests a Temporary Exemption from the Quarterly Fire Brigade Drills and Annual Live Fire Fighting Training Requirements of the Regulation2020-05-22022 May 2020 SNC Requests a Temporary Exemption from the Quarterly Fire Brigade Drills and Annual Live Fire Fighting Training Requirements of the Regulation ML20126G2662020-05-14014 May 2020 Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI ML20059N7872020-05-12012 May 2020 Exemption - LAR-19-010: Auxiliary Building Room Heatup ML20059N7902020-05-12012 May 2020 Exemption - LAR-19-010: Auxiliary Building Room Heatup ML20066G9042020-03-0606 March 2020 Request for Exemption from 10 CFR Part 50, Appendix E Exercise Requirements ND-20-0204, Enclosure 1 - Vogtle Electric Generating Plant (VEGP) Unit 4, Exemption Request 10 CFR Part 50, Appendix E Exercise Requirements2020-03-0606 March 2020 Enclosure 1 - Vogtle Electric Generating Plant (VEGP) Unit 4, Exemption Request 10 CFR Part 50, Appendix E Exercise Requirements ML19350C6612020-01-28028 January 2020 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19350C6272020-01-28028 January 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) ML19361A1092020-01-13013 January 2020 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-003) ML19361A1192020-01-13013 January 2020 Exemption - Vogtle Electric Generating Plant Unit 3 (LAR 19-003) ML19337A7412019-12-27027 December 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-002) Exemption from Regulations Set Forth in Appendix D of 10CFR52 ML19337B1392019-12-27027 December 2019 Exemption - Vogtle Electric Generating Plant Unit 4 (LAR 19-002) Exemption from Regulations Set Forth in Appendix D of 10CFR52 ML19164A2652019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 19-005) ML19164A2662019-11-15015 November 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 (LAR 19-005) NL-19-0801, Quality Assurance Topical Report Submittal, Request for Schedular Exemption - 10 CFR 50.54(a)(3)2019-10-31031 October 2019 Quality Assurance Topical Report Submittal, Request for Schedular Exemption - 10 CFR 50.54(a)(3) ML19238A3512019-09-27027 September 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 LAR 19-004 ML19239A0892019-09-27027 September 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 LAR 19-004 ND-19-0782, Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015)2019-08-0909 August 2019 Request for License Amendment and Exemption: Onsite Standby Diesel Generator Loading Changes (LAR-19-015) ML19133A1702019-06-12012 June 2019 Exemption - Vogtle Electric Generating Plant Unit 4 LAR 18-030 ML19133A1692019-06-12012 June 2019 Exemption - Vogtle Electric Generating Plant Unit 3 LAR 18-030 ML19113A2592019-05-20020 May 2019 Exemption - Vogtle Electric Generating Plant, Unit 3 (LAR 18-028) ML19113A2602019-05-20020 May 2019 Exemption - Vogtle Electric Generating Plant, Unit 4 (LAR 18-028) ML19063A8892019-04-18018 April 2019 Exemption - Vogtle Electric Generating Plant (LAR-18-021) PORV Relief Valve Noise Mitigation Unit 4 2024-01-31
[Table view] Category:Letter
MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] |
Text
Michael J. Yox r.
Regulatory Att Director I . Affairs . 7825 River
,,, ^ Road ik.Southern Nuclear ,,
Vogt e 3 & 4
^ Waynesboro, GA 30830 706-848-6459 tel March 6, 2020 Docket No.: 52-026 ND-20-0204 10 CFR 50.12 10 CFR 50, Appendix E U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 Request for Exemption from 10 CFR Part 50, Appendix E Exercise Requirements Ladies and Gentlemen:
In accordance with the provisions of 10 CFR 50.12, Specific Exemptions, Southern Nuclear Operating Company (SNC), requests an exemption from the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.a.iii as applicable to Vogtle Electric Generating Plant (VEGP) Unit 4 (License Number NPF-92). Specifically, SNC requests an exemption from the 10 CFR Part 50, Appendix E, Section IV.F.2.a.iii requirement for an applicant who currently has an operating reactor at the site to perform an exercise, either full or partial participation, for each subsequent reactor constructed on the site.
VEGP Unit 4 is of the same reactor design type as VEGP Unit 3 and shares the same operating site as VEGP Units 1, 2 and 3. VEGP Unit 3 will have already successfully completed an emergency preparedness exercise per the requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.a.iii, commenced initial fuel load, and established an 8-calendar-year exercise cycle which incorporates both VEGP Unit 3 and Unit 4 drill and exercise requirements, prior to VEGP Unit 4 commencing initial fuel load. The requested exemption would allow VEGP Unit 4 to credit the VEGP Unit 3 exercise to meet the exercise requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.a.iii for an applicant currently having an operating reactor on site. provides the background and supporting basis for the requested exemption.
This letter contains no regulatory commitments. This letter has been reviewed and determined not to contain security-related information.
SNC requests NRC staff approval of the requested exemption by December 31, 2020. Approval by this date will eliminate the planning, coordination, scheduling and exercise development activities associated with conducting a VEGP Unit 4 exercise prior to VEGP Unit 4 initial fuel load.
Should you have any questions, please contact Mr. Steve Leighty at (706) 848-6790.
U.S. Nuclear Regulatory Commission ND-20-0204 Page 2 of 4 I declare under penalty of perjury that the foregoing is true and correct. Executed on the 6'^ day of March 2020.
Respectfully submitted, Michael J. Yox Regulatory Affairs Director Vogtle 3&4 MJY/RLB/sfr Enclosures 1) VEGP Unit 4 - Request for Exemption from 10 CFR Part 50, Appendix E Exercise Requirements
U.S. Nuclear Regulatory Commission ND-20-0204 Page 3 of 4 go:
Southern Nuclear Operating Company / Georgia Power Company Mr. S. E. Kuczynski (w/o enclosures)
Mr. P. P. Sena III (w/o enclosures)
Mr. M. D. Meier (w/o enclosures)
Mr. D. H. Jones(w/o enclosures)
Mr. G. Chick Mr. M. Page Mr. P. Martino Mr. D. L. McKinney (w/o enclosures)
Mr. T. W. Yelverton (w/o enclosures)
Mr. B. H. Whitley Ms. C. A. Gayheart Ms. M. Ronnlund Mr. D. L. Fulton Mr. M. J. Vox Mr. C. T. Defnall Mr. J. Tupik Ms. S. Agee Mr. M. Humphrey Ms. A. C. Chamberlain Mr. S. Leighty Mr. N. Kellenberger Mr. E. Riffle Ms. K. Roberts Mr. J. Haswell Mr. D. T. BIythe Mr. K. Warren Document Services RTYPE: VND.LI.LOO File AR.01.02.06 Nuclear Reaulatorv Commission Mr. W. Jones(w/o enclosures)
Mr. M. King (w/o enclosures)
Ms. M. Bailey (w/o enclosures)
Mr. C. Patel Mr. C. Santos Mr. B. Kemker Mr. J. Eargle Mr. G. Khouri Ms. S. Temple Mr. C. J. Even Mr. A. Lerch Mr. S. Walker Mr. N.D. Karlovich Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. V. Hall Ms. K. P. Carrington Mr. M. Webb Mr. P.J. Heher
U.S. Nuclear Regulatory Commission ND-20-0204 Page 4 of 4 State of Georgia Mr. R. Dunn Oglethorpe Power Corporation Mr. M. W. Price Ms. A. Whaley Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company. LLC Mr. L. Oriani (w/o enclosures)
Mr. T. Rubenstein (w/o enclosures)
Mr. M. Corletti Mr. D. Hawkins Mr. J. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. A. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Ms. S. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham