Line 3: |
Line 3: |
| | issue date = 07/13/2006 | | | issue date = 07/13/2006 |
| | title = July 8, 2006, Perry Reported Noncompliance in Accordance with Ohio Environmental Protection Agency, Permit No. 3IB00016*ED | | | title = July 8, 2006, Perry Reported Noncompliance in Accordance with Ohio Environmental Protection Agency, Permit No. 3IB00016*ED |
| | author name = Pearce L W | | | author name = Pearce L |
| | author affiliation = FirstEnergy Nuclear Operating Co | | | author affiliation = FirstEnergy Nuclear Operating Co |
| | addressee name = Underwood M | | | addressee name = Underwood M |
Revision as of 15:42, 13 July 2019
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 L-24-168, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 L-24-155, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-140, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification L-24-066, Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency2024-04-15015 April 2024 Response to Request for Additional Information Regarding 10 CFR 50.55a Request Number VR-9, Feedwater Check Valve Exercising Test Frequency L-24-057, Submittal of the Decommissioning Funding Status Report2024-03-28028 March 2024 Submittal of the Decommissioning Funding Status Report ML24088A1922024-03-28028 March 2024 Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 2024-09-09
[Table view] Category:NPDES Noncompliance Notification
MONTHYEARML0620203912006-07-13013 July 2006 July 8, 2006, Perry Reported Noncompliance in Accordance with Ohio Environmental Protection Agency, Permit No. 3IB00016*ED 2006-07-13
[Table view] |
Text
FENGOC Perry Nuclear Power Station"--%%10 Center Road FirstEnergy Nuctear Operating Company Perry, Ohio 44081 L. WiIaN= Pearce 440-280-5382 Vice President Fax: 440-280-8029 July 13, 2006 PY-CEI/OEPA-0455L Ohio Environmental Protection Agency Northeast District Office Attention:
Ms. Marie Underwood 2110 E. Aurora Rd.Twinsburg, OH 44087-1 969 Ladies and Gentlemen, On July 8, 2006, the Perry Nuclear Power Plant (PNPP) reported a Noncompliance in accordance with Ohio Environmental Protection Agency (QEPA) Permit No. 31B00016*ED.
The report was made due to exceeding the maximum daily limit of 100 ppm for total suspended solids (TSS) for Internal Monitoring Station 601, neutralized demnineralizer regenerant waste. The initial report was made to the Ohio Environmental Protection Agency by phone on July 8, 2006.A follow-up telephone notification was made on July 11, 2006 regarding the TSS monthly average.The TSS monthly average for Internal Monitoring S~tation 601 was exceeded due to June 29, 2006 discharge.
The monthly average for Internal Monitoring Station 601 was 44.2 ppm versus a permit limitation of 30 ppm. This letter serves as the five-day follow-up report for both the June 29, 2006 daily exceedance and the resulting monthly exceedance required by the National Pollution Discharge Elimination System (NPDES) Permit.Per Part Ill, Section 12.13, the following information was reported on July 8, 2006: 1 .The times at which the discharge occurred, and was discovered:
The discharge occurred at 16:30 on June 29, 2006. The TSS concentration was discovered on July 7, 2006 when FENOC Beta Lab reported the analysis of that discharge.
- 2. The approximate amount and the characteristics of the discharge:
Approximately 18,300 gallons of neutralized demnineralizer regenerant waste with a pH of 7.94 and TSS of 142 ppm was pumped to Lake Erie via discharge 004.3. The stream affected by the discharge:
Lake.Erie.
Internal Monitoring Station 601 is mixed with final effluent 004.4. The circumstances which created the discharge:
Unknown at the time of the initial phone call.-Smbs ftha Parson's wohave know'e dge Of hs~~~~~~~~~~~g It ft.II~It~JvJIa~~Z.U)
O /U-- ,cs:Li RanorPal cwls'i. -rr6c230 uu.
July 13, 2006 PY-CEI/OEPA-0455L Page 2 of 2 Per Part 111, Section 12.0, the following information is provided for both exceedances:
1 .The limitation which has been exceeded:
The daily discharge limitation for Internal Monitoring Station 601 for TSS is a maximum of 100 ppm. The monthly permit limitation is 30 ppm.2. The extent of the exceedance:
Approximately 18,300 gallons of neutralized demineralizer regenerant water with a pH of 7.94 and TSS of 142 ppm was pumped to Lake Erie via discharge 004. As a result, the monthly average for Internal Monitoring Station 601 for TSS was 44.2 ppm.3. The cause of the exceedance:
The most likely cause of the high TSS was a contaminated sample from dirty sample lines. A discharge from the same basin on July 5, 2006 contained 5 ppm TSS.4. The period of the exceedance(s) including exact dates and times: The discharge started at 16:30 on June 29, 2006 and lasted approximately 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.5. If uncorrected, the anticipated time the exceedance is expected to continue:
The most likely cause of this exceedance has been eliminated.
- 6. Steps taken to reduce, eliminate, and/or prevent recurrence of the exceedance:
The contaminated sample lines have been removed from service. In addition, site specific procedures have been changed to obtain the analysis of the treated water prior to discharge.
If you have any questions or require additional information, please contact Ms. Liz Ryan or Mr. Paul Kowalski at (440)-280-5536/5063.
Sincerel cc: NRC Region Ill NRC Resident Inspector NRC Project Manager NRC Document Control Desk (Docket No. 50-440)