| issue date = 03/07/2011
| issue date = 03/07/2011
| title = Letter from Counsel for NRC Staff to Aslb Providing Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Nextera Energy Seabrook, LLC, Seabrook Station, Unit 1
| title = Letter from Counsel for NRC Staff to Aslb Providing Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Nextera Energy Seabrook, LLC, Seabrook Station, Unit 1
| author name = Spencer M B
| author name = Spencer M
| author affiliation = NRC/OGC
| author affiliation = NRC/OGC
| addressee name = Kennedy M F, Ryerson P S, Wardwell R E
| addressee name = Kennedy M, Ryerson P, Wardwell R
| addressee affiliation = NRC/ASLBP
| addressee affiliation = NRC/ASLBP
| docket = 05000443
| docket = 05000443

Revision as of 21:59, 10 July 2019

Letter from Counsel for NRC Staff to Aslb Providing Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Nextera Energy Seabrook, LLC, Seabrook Station, Unit 1
ML110660432
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/07/2011
From: Mary Spencer
NRC/OGC
To: Kennedy M, Paul Ryerson, Richard Wardwell
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 19756, 50-443-LR, ASLBP 10-906-02-LR-BD01
Download: ML110660432 (5)


Text

March 7, 2011

In the Matter of NEXTERA ENERGY SEABROOK, LLC (Seabrook Station, Unit 1)

Docket No. 50-443-LR RE: Projected Schedule for Completion of the Safety and Environmental Evaluations

Dear Administrative Judges:

Pursuant to the Board's Order of February 24, 2011 (Scheduling Initial Scheduling Conference), this letter informs the Board of the NRC Staff's best estimate of the projected schedule for completion of the safety and environmental evaluations. The projected schedule is in the form of a table and is attached to this submission. The projected dates are the Staff's current best estimate and are subject to change. Accordingly, the Staff will update the schedule and inform the parties as necessary.

Sincerely, Signed (electronically) by

_______________________________

Mary B. Spencer Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1324 E-mail: mary.spencer@nrc.gov Date of signature: March 7, 2011 Administrative Judge Paul S. Ryerson, Chair Atomic Safety and Licensing Board

Mail Stop: T-3F23 Washington, DC 20555-001 Administrative Judge Dr. Richard E. Wardwell Atomic Safety and Licensing Board

Mail Stop: T-3F23 Washington, DC 20555-0001 Administrative Judge

Dr. Michael F. Kennedy Atomic Safety and Licensing Board

Mail Stop: T-3F23 Washington, DC 20555-0001

Seabrook License Renewal Projected Milestone Schedule Projected Date Issue draft supplemental environmental impact statement (SEIS) 07/11 Issue safety evaluation report (SER) with open items 07/11 Issue final SER/Submit final SER to ACRS 01/12 Issue final SEIS 01/12 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD

In the Matter of )

) NEXTERA ENERGY SEABROOK, LLC ) Docket Nos. ) (Seabrook Station, Unit 1, ) ASLBP No. 10-905-02-LR-BD01

)

CERTIFICATE OF SERVICE

I hereby certify that copies of the foregoing Letter regarding Projected Schedule for Completion of the Safety and Environmental Evaluations, dated March 7, 2011, have been served upon the

following by the Electronic Information Exchange, this 7 th day of March, 2011:

Administrative Judge Paul S. Ryerson, Chair Atomic Safety and Licensing Board

Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: Paul.Ryerson@nrc.gov

Administrative Judge

Dr. Michael F. Kennedy Atomic Safety and Licensing Board Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

E-mail: Michael.Kennedy@nrc.gov Administrative Judge

Dr. Richard E. Wardwell Atomic Safety and Licensing Board

Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

E-mail: Richard.Wardwell@nrc.gov

Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Mail Stop - O-16G4 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov

Office of the Secretary Attn: Rulemakings and Adjudications Staff Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

E-mail: HEARINGDOCKET@nrc.gov

Hillary Cain, Law Clerk Atomic Safety and Licensing Board Mail Stop: T-3F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

E-mail: Hillary.cain@nrc.go

Steven Hamrick, Esq. NextEra Energy Seabrook, LLC

801 Pennsylvania Ave NW Suite 220 Washington, DC 20004 Steven.hamrick@fpl.com

Raymond Shadis Friends of the Coast New England Coalition Post Office Box 98

Edgecomb, Maine 04556 E-mail: shadis@prexar.com Kurt Ehrenberg New Hampshire Sierra Club

40 N. Main Street Concord, NH 03301 E-mail: kurt.ehrenberg@sierraclub.org Mitchell Ross, Esq. Antonio Fernandez, Esq.

NextEra Energy Seabrook, LLC

700 Universe Boulevard Juno Beach, FL 33408 E-mail: mitch.ross@fpl.com E-mail: antonio.fernandez@fpl.com

Doug Bogen Executive Director Seacoast Anti-Pollution League PO Box 1136

Portsmouth, NH 03802 E-mail: dbogen@metrocast.net\

Paul Gunter Beyond Nuclear 6930 Carroll Avenue, Suite 400

Takoma Park, MD 20912

E-mail: paul@beyondnuclear.com

Signed (electronically) by

_______________________________

Mary B. Spencer Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1324

E-mail: mary.spencer@nrc.gov Date of signature: March 7, 2011 3