Line 12: | Line 12: | ||
| identified by = NRC | | identified by = NRC | ||
| Inspection procedure = IP 71153 | | Inspection procedure = IP 71153 | ||
| Inspector = A Alen, B Parks, C Smith, G Guerra, J Laughlin, R Kumana, T Hipschman, W Walkerb, | | Inspector = A Alen, B Parks, C Smith, G Guerra, J Laughlin, R Kumana, T Hipschman, W Walkerb, Parksc Smith, G Guerra, J Laughlin, R Kumana, T Hipschman, W Walker | ||
| CCA = H.5 | | CCA = H.5 | ||
| INPO aspect = WP.1 | | INPO aspect = WP.1 |
Latest revision as of 19:49, 20 February 2018
Site: | Diablo Canyon |
---|---|
Report | IR 05000275/2013005 Section 4OA3 |
Date counted | Dec 31, 2013 (2013Q4) |
Type: | Finding: Green |
cornerstone | Initiating Events |
Identified by: | NRC identified |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | A Alen B Parks C Smith G Guerra J Laughlin R Kumana T Hipschman W Walkerb Parksc Smith G Guerra J Laughlin R Kumana T Hipschman W Walker |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |