Email - Purdue University License Renewal-Submission Schedule for Request for Additional Time to Respond to the 60- and 90-day Requests for Additional Information (RAIs)--Until January 31, 2012
ML121360631
Person / Time
Site: Purdue University
Issue date: 05/11/2012
From: Joel Jenkins
Purdue University
To: Montgomery C K
Research and Test Reactors Licensing Branch
montgomery c 415-3398
References
Download: ML121360631 (1)


Text

From:Jere Jenkins [jere@purdue.edu]Sent:Friday, May 11, 2012 3:15 PM To:Montgomery, Cindy

Subject:

RAI follow-up

Dear Ms. Montgomery,

As a follow-up to my e-mail (26 March 2012) requesting an extension for the remaining

RAIs for PUR-1, I would like to propose the following schedule for

submitting the

answers: Week ending06/01/125 06/15/125 06/29/125 07/13/125 07/27/125 08/10/125 08/24/125 09/07/122 09/21/122 10/05/122 10/19/122 11/02/122 11/16/122 11/30/122 12/14/122 12/28/122 01/11/132 01/25/132 01/31/131 This is a reasonable guidline, and takes advantage of additional time available over

the summer months, and will allow for all of the questions to be

answered by the 31

January 2013 target date asked for in the 26 March 2012 e-mail.

Please let me know if you have any questions or require further information.

Regards,

--jere--==================================================================

Jere Jenkins

Director of Radiation Labs; Purdue Univ. Nuclear Engineering