Line 40: |
Line 40: |
|
| |
|
| As such, the NRC staff has concluded that the information sought to be withheld from public disclosure does not meet the requirements of 10 CFR 2.390. Please respond within 30 days of the receipt of this letter to inform the staff of your plans for revising your LAR and withholding proprietary information request, to resolve the identified deficiencies as described above. | | As such, the NRC staff has concluded that the information sought to be withheld from public disclosure does not meet the requirements of 10 CFR 2.390. Please respond within 30 days of the receipt of this letter to inform the staff of your plans for revising your LAR and withholding proprietary information request, to resolve the identified deficiencies as described above. |
| If you have any questions regarding this review, please contact me at (301) 415-0893 or electronic mail at Geoffrey.Wertz@nrc.gov | | If you have any questions regarding this review, please contact me at (301) 415-0893 or electronic mail at Geoffrey.Wertz@nrc.gov. Sincerely, |
| . Sincerely, | |
| | |
| /RA Alexander Adams Jr., Acting For Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation | | /RA Alexander Adams Jr., Acting For Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation |
|
| |
|
Letter Sequence Withholding Request Acceptance |
---|
|
|
MONTHYEARML17089A2282017-03-27027 March 2017 University of Missouri - Columbia Research Reactor - Transmittal of Attachments 1, 4, 5, 6, 7, and 8 in Support of a Request to Amend Technical Specifications Project stage: Request ML17089A2292017-03-27027 March 2017 University of Missouri - Columbia Research Reactor - Written Communication as Specified by 10 CFR 50.4(b)(l) Requesting U.S. Nuclear Regulatory Commission Approval to Amend the Technical Specifications Project stage: Request ML17108A8092017-04-19019 April 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML17137A0012017-05-18018 May 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor Project stage: Withholding Request Acceptance ML17142A4192017-06-0606 June 2017 University of Missouri Research Reactor Acceptance of Requested Licensing Action License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor Project stage: Acceptance Review ML17177A1192017-06-28028 June 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML17234A7332017-09-0707 September 2017 University of Missouri at Columbia - Request for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor Project stage: RAI ML17285A0302017-10-10010 October 2017 Request for a 60-day Extension to Respond to the University of Missouri at Columbia - Request for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Misso Project stage: Request 2017-05-18
[Table View] |
|
---|
Category:Letter
MONTHYEARML24142A1422024-08-27027 August 2024 Examination Report Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24142A1432024-08-27027 August 2024 Examination Result Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24184A1132024-07-0202 July 2024 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.10.d IR 05000186/20242012024-05-29029 May 2024 the Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2024201 05000186/LER-2024-001, Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d2024-05-23023 May 2024 Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d ML24081A1332024-04-0202 April 2024 University of Missouri-Columbia (MURR) – Change of Facility Project Manager ML24044A1162024-03-0101 March 2024 Examination Confirmation Letter No. 50-186/OL-24-02, University of Missouri-Columbia ML24064A1922024-03-0101 March 2024 Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel ML24059A4412024-02-28028 February 2024 Univ. of Missouri - Columbia - Submittal of Annual Operating Report Technical Specification 6.6.e IR 05000186/20232022023-12-12012 December 2023 the Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023202 ML23198A0232023-08-29029 August 2023 Examination Result Letter No. 50-186/OL-23-02, University of Missouri-Columbia ML23198A0222023-08-29029 August 2023 Examination Report Letter No. 50-186/OL-23-02, University of Missouri - Columbia ML23221A1172023-08-0303 August 2023 Written Communication as Specified by 10 CFR 50.4(b)(4) Regarding the Submittal of the Physical Security Plan for the University of Missouri Research Reactor as a Part of the Process to Renew Amended Facility Operating License R-103 ML23213A0592023-08-0101 August 2023 Written Communication as Specified by University of Missouri Research Reactor Technical Specification 6.6.2(d) Regarding a Permanent Change in the Facility Organization Involving the Executive Director ML23186A2132023-07-31031 July 2023 Examination Confirmation Letter No. 50-186/OL-23-03, University of Missouri - Columbia IR 05000186/20232012023-07-31031 July 2023 the Curators of the University of Missouri U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023201 ML23124A0422023-05-0808 May 2023 Examination Confirmation Letter 50-186/OL-23-02, University of Missouri - Columbia ML23103A0742023-04-10010 April 2023 University of Missouri, Columbia Research Reactor, Shipment of Radioactive Material Shipment Identifier MURR 23-01 Highway Route Controlled Quantity ML23024A2772023-04-0707 April 2023 Cover Letter for the Security Inspection Report for the University of Missouri (Public) - October 2022 ML23087A1132023-03-29029 March 2023 Examination Report No. 50-186/OL-23-01, University of Missouri-Columbia ML23087A1142023-03-29029 March 2023 Examination Results Letter No. 50-186/OL-23-01, University of Missouri - Columbia ML23089A3162023-03-29029 March 2023 Letter Notifying Univ. of Missouri That Us Dept. of Energy Funding Will Not Be Available in Fiscal Year 2023 to Complete the Conversion of MURR to LEU Fuel ML23055B1372023-02-24024 February 2023 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e IR 05000186/20222022023-02-23023 February 2023 the Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2022202 - Cover Letter and Enclosure ML23031A0132023-02-14014 February 2023 Examination Confirmation Letter No. 50-186/OL-23-01, University of Missouri-Columbia ML23017A2072023-01-13013 January 2023 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 6.1.f ML22349A0422022-12-0808 December 2022 Written Communication as Specified in 10 CFR 50.54(b)(5) Regarding Changes to the University of Missouri-Columbia Research Reactor Facility Emergency Plan Without Prior Commission Approval Pursuant to 10 CFR 50.54(q)(3) ML22314A2102022-11-0909 November 2022 Written Communication as Required by Technical Specification 6.6.d(2), Other Reports, Regarding a Change in University of Missouri-Columbia Research Reactor Organization Involving the Reactor Facility Director ML22304A0042022-10-27027 October 2022 University of Missouri - Columbia, Shipment of Radioactive Material, Highway Route Controlled Quantity ML22291A0322022-10-14014 October 2022 University of Missouri Written Communication as Required by 10 CFR 73, Appendix G Regarding a Deviation from the MURR Physical Security Plan ML22290A0042022-10-12012 October 2022 University of Missouri-Columbia Research Reactor, Reportable Event Report Pursuant to 20.2201(a)(ii) Regarding Loss of Licensed Material During Shipment IR 05000186/20222012022-06-14014 June 2022 the Curators of the University of Missouri - U.S. NRC Routine Inspection Report No. 05000186/2022201 ML22158A0792022-06-0606 June 2022 Submittal of Revised Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22097A0592022-04-0707 April 2022 Approval for Spent Nuclear Fuel Highway Route Application - NRC Route No. 182D - Docket Number 050-0186 ML22088A0782022-03-25025 March 2022 Univ. of Missouri, Federal Funding for the Conversion of the Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel IR 05000186/20212032022-03-0202 March 2022 the Curators of the University of Missouri U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2021203 ML22056A5162022-02-25025 February 2022 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22038A6012022-02-0808 February 2022 Acceptance for Spent Nuclear Fuel Highway Route Application NRC No. 182D-Docket No. 050-0186 ML22013B1412022-01-21021 January 2022 Examination Confirmation Letter No. 50-186-OL-22-02, University of Missouri-Columbia ML21327A3042021-11-23023 November 2021 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.f.6 ML21298A1972021-10-25025 October 2021 University of Missouri-Columbia Research Reactor - Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.g.6 ML21253A2482021-09-23023 September 2021 Examination Confirmation Letter No. 50-186/OL-22-01, University of Missouri Columbia ML21221A3252021-08-0909 August 2021 University of Missouri-Columbia Research Reactor, Written Communication as Required by Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a ML21217A2982021-08-0505 August 2021 University of Missouri-Columbia Research Reactor - Reportable Event Report Pursuant to 20.2203(a)(2)(iv) ML21215A4982021-07-0707 July 2021 Univ of Missouri, Submittal of Revised Road Transportation Security Plan for the Shipment of Irradiated Reactor Fuel ML21098A1992021-06-10010 June 2021 the Curators of the University of Missouri Issuance of Amendment No. 40 to Renewed Facility Operating License No. R 103 to Amend Technical Specifications 6.2 and 6.4 for the University of Missouri Columbia Research Reactor IR 05000186/20212022021-05-28028 May 2021 the Curators of the University of Missouri - U.S. Nuclear Commission Routine Inspection Report No. 05000186/2021202 IR 05000186/20212012021-05-27027 May 2021 University of Missouri-Columbia U. S. Nuclear Regulatory Commission Security Inspection Report No. 05000186/2021201 - Non-OUO-Sri Cover Letter ML21118A9682021-04-28028 April 2021 Examination Confirmation Letter No. 50-186/OL-21-01, University of Missouri-Columbia ML21092A1712021-04-0202 April 2021 University of Missouri-Columbia Research Reactor - Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel 2024-08-27
[Table view] Category:Proprietary Information Review
MONTHYEARML18045A3462018-02-16016 February 2018 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure Revision to License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Rese ML17297B2422017-11-0202 November 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure Supplemental Information for License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the Univ. of M ML17177A1192017-06-28028 June 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure ML17137A0012017-05-18018 May 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor ML17108A8092017-04-19019 April 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure ML17041A4302017-02-16016 February 2017 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure ML16216A6962016-08-11011 August 2016 Proprietary Determination Regarding MURR Molybdenum-99 Project ML15051A0042015-02-20020 February 2015 University of Missouri at Columbia, Request for Withholding Information from Public Disclosure ML12206A3862012-08-10010 August 2012 University of Missouri, Columbia - Request for Withholding Information from Public Disclosure 2018-02-16
[Table view] |
Text
April 19, 2017
Mr. Ralph A. Butler, Executive Director
University of Missouri-Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI RESEARCH REACTOR - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (CAC NO. MF9524)
Dear Mr. Butler:
By letter dated March 27, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML17089A228, and ML17089A229), the University of Missouri Research Reactor (MURR), submitted a license amendment request (LAR) to produce molybdenum-99 using the General Atomics, Sele ctive Gas Extraction process, which included an affidavit executed by Keith E. Asmussen, which requested that information contained in the following documents be withheld from public disclosure pursuant to the Title 10 of the Code of Federal Regulations (10 CFR), Section 2.390:
- 1. Attachment 1, License Amendment Request to Implement SGE Target Experiment Facility (TEF) at the University of Missouri Research Reactor 2. Attachment 4, GA Report 30441R00021: "Target Assembly Thermal Analysis" 3. Attachment 5, GA Report 30441R00022: "Source Term Analysis Design Calculation Report" 4. Attachment 6, GA Report 30441R00031: "Mo-99 Target Assembly Nuclear Design for Once-Through Operation" 5. Attachment 7, GA Report 30441R00032: "RELAP Accident Analysis and FRAPTRAN Target Rod Transient Analysis Design Calculation Report" 6. Attachment 8, GA Report 30441R00017: "ANSYS Target Cartridge, Housing Structural Analysis Design Calculation Report"
Section 2.390(b)(1)(iii) of 10 CFR Part 2 of the Commission's regulations requires that each supporting affidavit contain a full statement of the reasons for claiming the information should be withheld from public disclosure. The section further requires the statement to address with specificity the considerations listed in 10 CFR 2.390(b)(4).
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed your application and affidavit in accordance with the requirements of 10 CFR 2.390. The NRC staff has concluded that insufficient justification was provided to determine that all of the information sought to be withheld from public disclosure was proprietary information.
The NRC staff found numerous examples where information in the public version was designated proprietary (redacted) which had already been made publicly available in the meeting presentation provided by MURR at the February 13, 2017, NRC public meeting (ADAMS Accession No. ML17041A074). The NRC staff found that the proprietary information was not marked in accordance with the requirements in 10 CFR 2.390(b)(1)(i)(B) to indicate the basis for the proprietary nature of the information. The NRC staff also noted that the public (redacted) version of the LAR was not the same revision as the proprietary version since the redaction process had been performed prior to the final review and approval of the LAR by the licensee. The NRC staff also noted that the affi davit statement that, "essentially each and every page of these documents (items 1 through 6, referenced above) contains proprietary material developed by General Atomics, and for General Atomics by its partners MURR and Nordion that is "confidential," "proprietary," "business sensitive" and/or "trade secret," was not supported by the redacted versions provided, since not every page contained proprietary (redacted) information. Additionally, item no. (5) in the affidavit stated that, "Some examples categories of information which fit into the definition of proprietary information," implied that other categories existed, but were not listed.
These issues were discussed with your staff during our telephone conversation conducted on April 17, 2017, and you indicated that you understood the issues and would respond accordingly.
As such, the NRC staff has concluded that the information sought to be withheld from public disclosure does not meet the requirements of 10 CFR 2.390. Please respond within 30 days of the receipt of this letter to inform the staff of your plans for revising your LAR and withholding proprietary information request, to resolve the identified deficiencies as described above.
If you have any questions regarding this review, please contact me at (301) 415-0893 or electronic mail at Geoffrey.Wertz@nrc.gov. Sincerely,
/RA Alexander Adams Jr., Acting For Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
Docket No. 50-186
cc: See next page University of Missouri-Columbia Docket No. 50-186
cc: Les Foyto, Associate Director Reactor and Facilities Operations University of Missouri - Columbia
Research Reactor Center 1513 Research Park Drive Columbia, MO 65211
Homeland Security Coordinator
Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102
Planner, Dept of Health and Senior Services Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570
Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101
A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101
Test, Research and Training
Reactor Newsletter P.O. Box 118300 University of Florida Gainesville, FL 32611
ML17108A809; *concurred via email NRR-088 OFFICE NRR/DPR/PRLB/PM* NRR/DPR/PROB/LA*NRR/DPR/PRLB/BC NRR/DPR/PRLB/PMNAME GWertz NParker AAdams GWertz (AAdams for) DATE 4/19/17 4/19/17 4/19/17 4/19/17