Line 12: |
Line 12: |
| | document type = Deficiency Correspondence (per 10CFR50.55e and Part 21), Deficiency Report (per 10CFR50.55e and Part 21) | | | document type = Deficiency Correspondence (per 10CFR50.55e and Part 21), Deficiency Report (per 10CFR50.55e and Part 21) |
| | page count = 5 | | | page count = 5 |
| | }} |
| | |
| | =Text= |
| | {{#Wiki_filter:U.S. Nuclear Regulatory Commission Operations Center Event Report//201Page 152407Part 21 (PAR)Event #VALCOR ENGINEERING CORPORATIONFRAN LUCANOSTEVEN VITTO12/05/201612/05/201614:0912/05/2016ART BURRITTVINCENT GADDY PART 21/50.55 REACTORSR1DOR4DO EMAILDEFECTS AND NONCOMPLIANCENRC Notified by:HQ Ops Officer:Notification Date / Time:Event Date / Time:Last Modification:Rep Org:10 CFR Section:Notifications:NON EMERGENCYEmergency Class:VALCOR ENGINEERING CORPORATIONRegion:1City:SPRINGFIELDCounty:State:NJDocket #:License #:Agreement State:Yes(EST)(EST)Supplier:21.21(d)(3)(i)PART 21 - NON-CONFORMING COVER MACHINING ON SOLENOID VALVE The following is a synopsis of the Part 21 report that was received via fax:"Cover Machining is installed on upper section of Solenoid Valve and it allows for the electrical connection to the valve solenoid and protects inside wiring of the solenoid from environmental condition. Cover machining part number V52636-567 has 0.190 radius (Drawing V52620-50 Zone D3) which was machined too deep removing material from surface needed for proper O-ring seal. The lack of material exposes part of the sealing O-ring which could diminish the O-ring sealing capability. With O-ring sealing capability diminished, Valcor cannot ensure that valves with Cover Machining Installed on Solenoid Assembly will perform its safety function during all postulated events."This item has historically been manufactured by machining a casting. For the lot involved, castings were not available. Authorization was given to manufacture the Cover directly from suitable bar stock. To accomplish this, Valcor's vendor used the casting drawing and casting machining drawing to manufacture the finished machined part. The combination of these two drawings had insufficient control on the corner radius, resulting in this nonconformance."All defective covers in stock have been quarantined and a nonconformance report has been generated. Lack of location controlling dimension on the Cover Machining drawing for 0.190 radius was discovered to be the root cause of the defect. Valcor has created and released a new engineering drawing that properly controls the location of 0.190 radius. This action has been completed as of 11/22/2016. Engineering Manager-Nuclear was responsible to this action."Valcor is in a process of notifying all affected customers. |
| | U.S. Nuclear Regulatory Commission Operations Center Event Report//201Page 2"Customers: Ameren, Valve Part Number V526-6000-16 (Stock# 7731643), S/N 9, QTY 1, Location Ameren Missouri - CallawayBruce Power (BPC), Valve Part Number V526-6000-20 (Cat ID 142129), S/N 28-36, QTY 9, Bruce NGS"Note: All 9 valves supplied to BPC have been returned to Valcor for nameplate correction and are accounted for."If you have any questions or addition information is needed regarding this matter, please contact Fran Lucano at 973-467-8400."*********************************************************************************************************************************** |
| | |
| }} | | }} |
Revision as of 15:04, 30 April 2018
|
---|
Category:Deficiency Correspondence (per 10CFR50.55e and Part 21)
MONTHYEARML19346H8732019-12-12012 December 2019 Westinghouse Electric Company - Notification of the Potential Existence of Defect Pursuant to 10 CFR Part 21 ULNRC-06393, 10 CFR Part 21 Written Notification Regarding Cameron Barton Model 752B Differential Pressure Transmitters2017-10-31031 October 2017 10 CFR Part 21 Written Notification Regarding Cameron Barton Model 752B Differential Pressure Transmitters ML17026A4122016-12-0505 December 2016 Valcor Engineering Corp. - Part 21 - Non-Conforming Cover Machining on Solenoid Valve ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML0923900432009-08-25025 August 2009 Notification of Potential Part 21 Report Due to Radiation Monitor Defect ML0701704602007-01-0808 January 2007 10CFR21 for FMEA and Pre-installation Setup of Woodward Digital Reference Unit (Dru); Fairbanks Morse Engine Reporting Id# 06-05 2019-12-12
[Table view] Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARML21363A1512021-12-29029 December 2021 CFR Part 21 Written Notification Regarding Paragon Energy Solutions, LLC Power Supplies ML19346H8732019-12-12012 December 2019 Westinghouse Electric Company - Notification of the Potential Existence of Defect Pursuant to 10 CFR Part 21 ML19053A5002019-02-0101 February 2019 Sor, Inc. Part 21 Notification of Deviation Sor R-Series Housing with Terminal Block ULNRC-06393, 10 CFR Part 21 Written Notification Regarding Cameron Barton Model 752B Differential Pressure Transmitters2017-10-31031 October 2017 10 CFR Part 21 Written Notification Regarding Cameron Barton Model 752B Differential Pressure Transmitters ML17194A8252017-07-11011 July 2017 Part 21 Report Re Wedge Pin Failure in Anchor Darling Motor Operated Double Disc Gate Valves with Threaded Stem to Upper Wedge Connections ML17165A4052017-06-0909 June 2017 Part 21 Report - Potential Minimum Wall Thickness Issue on Certain Posi-Seal Valves ML17026A4122016-12-0505 December 2016 Valcor Engineering Corp. - Part 21 - Non-Conforming Cover Machining on Solenoid Valve ML16281A2702016-09-22022 September 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16278A4712016-09-22022 September 2016 Notification of 10 CFR Part 21 Condition, Masterpact Breaker Fail to Close ML16139A8322016-05-13013 May 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16139A8332016-05-13013 May 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML15280A3522015-10-0505 October 2015 Part 21 Report Electronic Position Controller Failed Internal ML14094A4452014-04-0101 April 2014 Notification of Part 21 Report on Defective Raw Material Used to Manufacture Valve Stems ML14069A4682014-03-0202 March 2014 Part 21 Report - Defective Raw Material Used to Manufacture Valve Stems ML13211A1682013-07-26026 July 2013 Westinghouse, Notification of Potential Existence of Defects Pursuant to 10 CFR Part 21 Inconsistency Between the Intended Design Functionality of the Shield Passive Thermal Shutdown Seal (SDS) and That Observed During Post-Service Testing ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13073A1072013-03-12012 March 2013 Notification of Potential Part 21 Report - Defective Raw Material Used to Manufacture Valve Stems ML13064A0122013-02-25025 February 2013 Notification of Potential Part 21 Report Re Wedge Pin Failure of an Anchor/Darling Double-Disc Gate Valve ML13045A8932013-02-0101 February 2013 Notification of Part 21 Report - Defective Raw Material Used to Manufacture Valve Stems ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML1219103372012-07-0202 July 2012 Update 10 CFR Part 21 Notification of Defective Moore 535 Controllers ML12110A1672012-04-17017 April 2012 Notification of Potential Part 21 Report - Swagelok U Series Bellows Valves Loosening of Stem Tips ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML1005129082010-02-12012 February 2010 Notification of Potential Part 21 Report Re Interim Report Concerning an Issue in Sump Blockage Generic Tests ML1004801382010-02-12012 February 2010 Interim Report of the Evaluation of a Deviation Pursuant to 10CFR21.21(a)(2) ML0934908692009-12-0808 December 2009 Engine Systems, Inc., Transmittal of 10 CFR 21Defects and Non-Compliance for Woodward Pgpl Actuator with Remote Servo P/N 529-044 P/N: 9903-539 ML0934401522009-12-0808 December 2009 Notification of Potential Part 21 on Woodward Governor Servo Failure Due to Silver Sulfide Corrosion of Surface Mount Resistors ML0926802462009-09-23023 September 2009 Notification of Potential Part 21 on Reportable Occurrence Under 10 CFR Part 21: Firmware Anomaly in the Model RM-80 Radiation Monitoring System ML0831900172008-11-12012 November 2008 Notification of Potential Part 21 on All Dimensionally Verified Commercial Grade Items Processed Per Fisher Manufacture Procedure Fmp 2K28 ML0828403842008-10-0303 October 2008 10 CFR Part 21 Reporting Thread Sealant Issue ML0823901062008-08-25025 August 2008 Notification of Potential Part 21 on Failure of F and G Switches ML0809906342008-04-0404 April 2008 Part 21 Notification Regarding Failure to Comply with the Requirements for Dedication of Commercial Grade Items ML0710002292007-04-0606 April 2007 Rosemount Nuclear Instruments, Inc., Submittal of Notification Under 10 CFR Part 21 for Certain Model 1152 Pressure Transmitters ULNRC-05312, CFR Part 21 Written Notification Regarding Prime Measurement Products, Models 763 and 763A Gauge Pressure Transmitters and Model 764 Differential Pressure Transmitters2006-07-17017 July 2006 CFR Part 21 Written Notification Regarding Prime Measurement Products, Models 763 and 763A Gauge Pressure Transmitters and Model 764 Differential Pressure Transmitters ML0617703542006-06-22022 June 2006 Operations Center Event Report, Prime Measurement Products, Models 763 and 763A Gage Pressure Transmitters and Model 764 Differential Pressure Transmitters. ML0536203682005-12-16016 December 2005 Part 21 Notification -Prime Measurement Products Models 763 & 763A Pressure Transmitters and Model 764 Differential Pressure Transmitters ML0532503742005-11-17017 November 2005 Initial Part 21 Notification - Prime Measurement Products, Models 763 & 763A Pressure Transmitters and Model 764 Differential Pressure Transmitters ML0332505392003-11-20020 November 2003 Event 40344: Low Voltage Circuit Breaker Defect and Noncompliance Report ML0305502482003-02-17017 February 2003 10CFR Part 21 Notification - Carboline Company ML0215102952002-05-15015 May 2002 10 CFR 21 Notification - Potential Defect Fan Assemblies for UPS Systems ML0215502492002-05-10010 May 2002 Letter from W. G. Hampton Subject: 10CFR Part 21 Notification-Potenial Defect Involving Fan Assemblies Used in Forced Air Cooled Uninterruptible Power Supply Systems ML0204400182002-01-15015 January 2002 Resubmittal of Final Report No. 41, Report of a Potential Safety Hazard from Dresser-Rand 2021-12-29
[Table view] |
Text
U.S. Nuclear Regulatory Commission Operations Center Event Report//201Page 152407Part 21 (PAR)Event #VALCOR ENGINEERING CORPORATIONFRAN LUCANOSTEVEN VITTO12/05/201612/05/201614:0912/05/2016ART BURRITTVINCENT GADDY PART 21/50.55 REACTORSR1DOR4DO EMAILDEFECTS AND NONCOMPLIANCENRC Notified by:HQ Ops Officer:Notification Date / Time:Event Date / Time:Last Modification:Rep Org:10 CFR Section:Notifications:NON EMERGENCYEmergency Class:VALCOR ENGINEERING CORPORATIONRegion:1City:SPRINGFIELDCounty:State:NJDocket #:License #:Agreement State:Yes(EST)(EST)Supplier:21.21(d)(3)(i)PART 21 - NON-CONFORMING COVER MACHINING ON SOLENOID VALVE The following is a synopsis of the Part 21 report that was received via fax:"Cover Machining is installed on upper section of Solenoid Valve and it allows for the electrical connection to the valve solenoid and protects inside wiring of the solenoid from environmental condition. Cover machining part number V52636-567 has 0.190 radius (Drawing V52620-50 Zone D3) which was machined too deep removing material from surface needed for proper O-ring seal. The lack of material exposes part of the sealing O-ring which could diminish the O-ring sealing capability. With O-ring sealing capability diminished, Valcor cannot ensure that valves with Cover Machining Installed on Solenoid Assembly will perform its safety function during all postulated events."This item has historically been manufactured by machining a casting. For the lot involved, castings were not available. Authorization was given to manufacture the Cover directly from suitable bar stock. To accomplish this, Valcor's vendor used the casting drawing and casting machining drawing to manufacture the finished machined part. The combination of these two drawings had insufficient control on the corner radius, resulting in this nonconformance."All defective covers in stock have been quarantined and a nonconformance report has been generated. Lack of location controlling dimension on the Cover Machining drawing for 0.190 radius was discovered to be the root cause of the defect. Valcor has created and released a new engineering drawing that properly controls the location of 0.190 radius. This action has been completed as of 11/22/2016. Engineering Manager-Nuclear was responsible to this action."Valcor is in a process of notifying all affected customers.
U.S. Nuclear Regulatory Commission Operations Center Event Report//201Page 2"Customers: Ameren, Valve Part Number V526-6000-16 (Stock# 7731643), S/N 9, QTY 1, Location Ameren Missouri - CallawayBruce Power (BPC), Valve Part Number V526-6000-20 (Cat ID 142129), S/N 28-36, QTY 9, Bruce NGS"Note: All 9 valves supplied to BPC have been returned to Valcor for nameplate correction and are accounted for."If you have any questions or addition information is needed regarding this matter, please contact Fran Lucano at 973-467-8400."***********************************************************************************************************************************