|
|
Line 91: |
Line 91: |
| No findings were identified. | | No findings were identified. |
| {{a|1R04}} | | {{a|1R04}} |
| ==1R04 Equipment Alignment== | | ==1R04 Equipment Alignment |
|
| |
|
| ===.1 Partial System Walkdowns=== | | ===.1 Partial System Walkdowns=== |
| {{IP sample|IP=IP 71111.04Q|count=3}} | | {{IP sample|IP=IP 71111.04Q|count=3}}== |
|
| |
|
| ====a. Inspection Scope==== | | ====a. Inspection Scope==== |
Line 114: |
Line 114: |
| No findings were identified. | | No findings were identified. |
| {{a|1R05}} | | {{a|1R05}} |
| ==1R05 Fire Protection== | | ==1R05 Fire Protection |
|
| |
|
| ===.1 Resident Inspector Quarterly Walkdowns=== | | ===.1 Resident Inspector Quarterly Walkdowns=== |
| {{IP sample|IP=IP 71111.05Q|count=5}} | | {{IP sample|IP=IP 71111.05Q|count== |
| | =5}} |
|
| |
|
| ====a. Inspection Scope==== | | ====a. Inspection Scope==== |
Line 130: |
Line 131: |
| No findings were identified. | | No findings were identified. |
| {{a|1R07}} | | {{a|1R07}} |
| ==1R07 Heat Sink Performance (711111.07A - 1 sample)== | | ==1R07 Heat Sink Performance (711111.07A - 1 sample) |
|
| |
|
| ====a. Inspection Scope==== | | ====a. Inspection Scope==== |
| | == |
| The inspectors reviewed the D secondary closed cooler to determine its readiness and availability to perform its risk significant functions. The inspectors reviewed the design basis for the component and verified Exelons commitments to NRC Generic Letter 89-13, Service Water System Requirements Affecting Safety-Related Equipment, were being maintained. The inspectors observed actual inspections of the heat exchanger reviewed. The inspectors discussed the results of the most recent inspection with engineering staff and reviewed the as-found and as-left conditions. The inspectors verified that Exelon initiated appropriate corrective actions for identified deficiencies. | | The inspectors reviewed the D secondary closed cooler to determine its readiness and availability to perform its risk significant functions. The inspectors reviewed the design basis for the component and verified Exelons commitments to NRC Generic Letter 89-13, Service Water System Requirements Affecting Safety-Related Equipment, were being maintained. The inspectors observed actual inspections of the heat exchanger reviewed. The inspectors discussed the results of the most recent inspection with engineering staff and reviewed the as-found and as-left conditions. The inspectors verified that Exelon initiated appropriate corrective actions for identified deficiencies. |
|
| |
|
|
---|
Category:Inspection Report
MONTHYEARIR 05000320/20240012024-08-28028 August 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2024001 and 05000320/2024002 IR 07200077/20240012024-06-18018 June 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 07200077/2024001 IR 05000320/20230042024-02-0707 February 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023004 IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 IR 05000320/20220042023-02-16016 February 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2022004 and 05000320/2022401 IR 05000289/20220022023-02-13013 February 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 – NRC Inspection Report Nos. 05000289/2022002 and 005000289/2022402 IR 05000289/20220012022-08-26026 August 2022 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report Nos. 05000289/2022001 and 07200077/2022001 ML22228A0142022-08-17017 August 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report IR 05000289/20224012022-04-12012 April 2022 NRC Security Decommissioning Inspection Report No. 05000289/2022401 IR 05000289/20210022022-01-31031 January 2022 NRC Inspection Report 05000289/2021002 and 07200077/2021001 IR 05000320/20210042022-01-27027 January 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021004 IR 05000289/20210012021-06-28028 June 2021 NRC Inspection Report No. 05000289/2021001, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20214012021-06-28028 June 2021 Security Decommissioning Inspection Report 05000289/2021401 IR 05000320/20210032021-06-22022 June 2021 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021003 IR 05000289/20200052021-02-0101 February 2021 NRC Inspection Report No. 05000289/2020005, Exelon Generation Co., LLC, Three Mile Island Nuclear Station Unit 1 IR 05000320/20200022020-10-19019 October 2020 Gpu Nuclear, Inc., Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report 05000320/2020002 IR 05000289/20204012020-09-0101 September 2020 Unit 1 - Security Baseline Inspection Report 05000289/2020401 IR 05000289/20200032020-07-20020 July 2020 NRC Inspection Report No. 05000289/2020003, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20200012020-04-30030 April 2020 NRC Inspection Report 05000289/2020001 IR 05000289/20190102020-02-0404 February 2020 NRC Inspection Report No. 05000289/2019010, Exelon Generation Co., LLC, Three Mile Island Unit 1, Middletown, PA IR 05000289/20190032019-11-0606 November 2019 Integrated Inspection Report 05000289/2019003 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20193012019-08-15015 August 2019 Initial Operator Licensing Examination Report 05000289/2019301 IR 05000289/20190022019-08-0909 August 2019 Integrated Inspection Report 05000289/2019002 IR 05000320/20190012019-06-10010 June 2019 Gpu Nuclear, Inc., Three Mile Island Station, Unit 2 - NRC Inspection Report 05000320/2019001 IR 05000289/20195012019-06-0303 June 2019 Emergency Preparedness Biennial Exercise Inspection Report 05000289/2019501 IR 05000289/20194102019-03-18018 March 2019 Baseline Security Inspection Report 05000289/2019410 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180042019-01-31031 January 2019 Integrated Inspection Report 5000289/2018004 IR 05000289/20182012018-12-13013 December 2018 NRC Inspection Report 05000289/2018201 IR 05000289/20180032018-11-0808 November 2018 Integrated Inspection Report 5000289/2018003 IR 05000289/20184102018-09-18018 September 2018 Baseline Security Inspection Report 05000289/2018410 (Letter Only) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20180022018-08-0202 August 2018 Integrated Inspection Report 5000289/2018002 IR 05000320/20180112018-05-23023 May 2018 NRC Inspection Report 05000320/2018011 IR 05000289/20180102018-05-0202 May 2018 Design Bases Assurance Inspection (Teams) Report 05000289/2018010 IR 05000289/20180012018-05-0202 May 2018 Integrated Inspection Report 5000289/2018001 and Exercise of Enforcement Discretion IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170042018-01-25025 January 2018 Integrated Inspection Report 05000289-2017004 IR 05000289/20174052017-11-29029 November 2017 Problem Identification and Resolution Cyber Security Inspection Report 05000289/2017405 (Cover Letter) IR 05000289/20170032017-10-25025 October 2017 Integrated Inspection Report 5000289/2017003 IR 05000289/20174032017-09-25025 September 2017 Baseline Security Inspection Report 05000289/2017403 (Cover Letter) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20170102017-08-25025 August 2017 Susquehanna Steam Electric Station, Units 1 and 2 - Problem Identification and Resolution Cyber Security Inspection Report 05000387/2017405 and 05000388/2017405 (Cover Letter) IR 05000289/20173012017-08-23023 August 2017 Initial Operator Licensing Examination Report 05000289/2017301 IR 05000289/20170022017-08-0808 August 2017 Integrated Inspection Report 05000289/2017002 2024-08-28
[Table view] Category:Letter
MONTHYEARRS-24-124, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822024-11-19019 November 2024 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 RS-24-121, Regulatory Path to Reauthorize Power Operations2024-11-0404 November 2024 Regulatory Path to Reauthorize Power Operations RS-24-097, Notice of Intent to Pursue Subsequent License Renewal for Three Mile Island Nuclear Station, Unit 12024-10-23023 October 2024 Notice of Intent to Pursue Subsequent License Renewal for Three Mile Island Nuclear Station, Unit 1 ML24256A0422024-10-0404 October 2024 Updated Post-Shutdown Decommissioning Activities Report, Rev. 6 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24242A3032024-09-0909 September 2024 Letter - Three Mile Island Station, Unit 2, Issuance of Amendment No. 68, Historic and Cultural Resources IR 05000320/20240012024-08-28028 August 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2024001 and 05000320/2024002 ML24240A2222024-08-27027 August 2024 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 6 ML24220A2742024-08-15015 August 2024 Request for Additional Information Clarification Call Regarding Three Mile Island Station, Unit 2, Amended Post-Shutdown Decommissioning Activities Report, Rev. 6 ML24135A3292024-08-0909 August 2024 Amendment No 68, Historic and Cultural Resources Cover Letter IR 07200077/20240012024-06-18018 June 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 07200077/2024001 ML24135A1972024-06-13013 June 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0091 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24157A3672024-06-13013 June 2024 Updated Post-Shutdown Decommissioning Activities Report Request for Additional Information Transmittal Letter ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24120A3242024-05-24024 May 2024 TMI-2 Email to Fws RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24121A2472024-04-29029 April 2024 And Three Mile Island, Unit 2 - 2023 Occupational Radiation Exposure Annual Report ML24120A2552024-04-29029 April 2024 Annual Radiological Environmental Operating Report ML24113A0212024-04-18018 April 2024 (TMI-2), Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24088A0122024-03-28028 March 2024 Notification of Amended Post-Shutdown Decommissioning Activities Report (PSDAR) in Accordance with 10 CFR 50.82(a)(7), Revision 6 ML24065A0042024-03-28028 March 2024 Submittal of 2023 Aircraft Movement Data Annual Report ML24092A0012024-03-28028 March 2024 (TMI-2), Decommissioning Trust Fund Annual Report ML24085A2152024-03-25025 March 2024 (TMI-2) - Annual Notification of Property Insurance Coverage RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. ML24052A0602024-03-20020 March 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0061 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24074A3922024-03-14014 March 2024 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML24075A0062024-03-14014 March 2024 List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24073A2312024-03-13013 March 2024 And Three Mile Island Nuclear Station, Unit 2 - Management Change ML24044A0092024-02-12012 February 2024 License Amendment Request – Three Mile Island, Unit 2, Historic and Cultural Resources Review, Response to Request for Additional Information IR 05000320/20230042024-02-0707 February 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023004 ML24038A0222024-02-0505 February 2024 Achp Letter on Section 106 Programmatic Agreement Participation IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 ML23342A1242024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23325A1092024-01-0505 January 2024 Review of the Management Plan for Three Mile Island Station, Unit No. 2, Debris Material ML23354A2112023-12-20020 December 2023 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23354A2062023-12-20020 December 2023 (TMI-2), Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 ML23243A9082023-08-29029 August 2023 SHPO Letter to TMI-2 Regarding Section 106 Activities IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 ML23216A1772023-08-14014 August 2023 Consultation Letter to Rebecca Countess for TMI-2 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 ML23216A1782023-08-14014 August 2023 Consultation Letter to Steve Letavic for TMI-2 ML23216A1752023-08-14014 August 2023 Consultation Letter to Joanna Cain for TMI-2 ML23216A1742023-08-14014 August 2023 Consultation Letter to David Morrison for TMI-2 ML23216A1732023-08-14014 August 2023 Consultation Letter to Christine Turner for TMI-2 ML23221A1402023-08-0808 August 2023 (TMI-2), Response to Requests for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23213A2342023-08-0101 August 2023 Submittal of Defueled Safety Analysis Report and Decommissioning Quality Assurance Plan ML23200A1882023-07-31031 July 2023 TMI-2 Correction Letter Amendment 67 ML23209A7632023-07-28028 July 2023 Letter from PA SHPO to TMI-2 Solutions on Cultural and Historic Impacts of Decommissioning 2024-09-09
[Table view] |
Text
{{#Wiki_filter:ary 25, 2018
SUBJECT:
THREE MILE ISLAND STATION, UNIT 1 - INTEGRATED INSPECTION REPORT 05000289/2017004
Dear Mr. Hanson:
On December 31, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Three Mile Island, Unit 1 (TMI). On January 19, 2018, the NRC inspectors discussed the results of this inspection with Mr. Tom Haaf, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
NRC inspectors documented one finding of very low safety significance (Green) in this report.
This finding did not involve a violation of NRC requirements.
If you disagree with the cross-cutting aspect assignment or the finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U. S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Three Mile Island.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRCs Public Document Room in accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Silas R. Kennedy, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No. 50-289 License No. DPR-50
Enclosure:
Inspection Report 05000289/2017004 w/Attachment: Supplementary Information
REGION I==
Docket No: 50-289 License No: DPR-50 Report No: 05000289/2017004 Licensee: Exelon Generation Company Facility: Three Mile Island Station, Unit 1 Location: Middletown, PA 17057 Dates: October 1 through December 31, 2017 Inspectors: Z. Hollcraft, Senior Resident Inspector B. Lin, Resident Inspector J. Furia, Senior Health Physicist J. DeBoer, Emergency Preparedness Inspector Approved by: S. Kennedy, Chief Reactor Projects Branch 6 Division of Reactor Projects Enclosure
SUMMARY
Inspection Report 05000289/2017004, 10/01/2017-12/31/2017; Three Mile Island, Unit 1,
Integrated Inspection Report.
This report covered a three-month period of inspection by resident inspectors and announced inspections performed by regional inspectors. Inspectors identified one finding of very low safety significance (Green). The significance of most findings is indicated by their color (i.e.,
greater than Green, or Green, White, Yellow, Red) and determined using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP), dated November 15, 2016.
Cross-cutting aspects are determined using IMC 0310, Aspects Within Cross-Cutting Areas, dated December 4, 2014. All violations of Nuclear Regulatory Commission (NRC) requirements are dispositioned in accordance with the NRCs Enforcement Policy, dated November 1, 2016.
The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 6.
Cornerstone: Initiating Events
- Green.
The inspectors documented a self-revealing finding involving the failure to follow LS-AA-125, Corrective Action Program, Revision 14. Specifically, the licensee failed to take appropriate corrective actions to correct degraded control rod drive mechanism cable connections identified during a 2010 stuck rod event. This resulted in a rod drop event on October 10, 2017, that caused a turbine runback to 55 percent and required a plant shutdown to repair. As an immediate corrective action, the licensee replaced the Bendix 7-pin electrical connector for the control rod drive mechanism (CRDM) and performed extent of condition visual and resistance checks on the other CRDM cables. The issue was entered into their corrective action program (CAP) as issue report (IR) 04061160.
The performance deficiency is more-than-minor because it was associated with the equipment performance attribute of the Initiating Events cornerstone and adversely affected the objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during power operations. Specifically, a transient resulting from a dropped rod challenged the critical safety function of reactivity control. The inspectors determined that this finding was of very low safety significance (Green) since it did not cause both a reactor trip and the loss of mitigation equipment relied upon to transition the plant to a stable shutdown condition.
This finding has a cross-cutting aspect in the area of Problem Identification and Resolution,
Evaluation, because despite indications of degradation during inspections in 2013 and 2015, the site failed to ensure that a resolution addressed the cause commensurate with its safety significance (P.2). (Section 1R12)
REPORT DETAILS
Summary of Plant Status
Unit 1 began the inspection period shutdown in refueling outage (1R22), which started on September 18, 2017. Operators took the reactor critical on October 8 and reached 72 percent power before having to shut the reactor down to perform repairs on the control rod drive system on October 11. Following repairs, operators returned the unit to 100 percent power on October 12. The unit remained at or near 100 percent power for the remainder of the inspection period.
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
Main article: IP 71111.01
.1 Readiness for Seasonal Extreme Weather Conditions
a. Inspection Scope
The inspectors performed a review of Exelons readiness for the onset of seasonal low temperatures on December 11, 2017. The review focused on borated water storage tank heat tracing and industrial coolers. The inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), technical specifications, control room logs, and the CAP to determine what temperatures or other seasonal weather could challenge these systems, and to ensure Exelon personnel had adequately prepared for these challenges.
The inspectors reviewed station procedures, including Exelons seasonal weather preparation procedure and applicable operating procedures. The inspectors performed walkdowns of the selected systems to ensure station personnel identified issues that could challenge the operability of the systems during cold weather conditions.
Documents reviewed for each section of this inspection report are listed in the
.
b. Findings
No findings were identified.
==1R04 Equipment Alignment
.1 Partial System Walkdowns
Main article: IP 71111.04Q ==
a. Inspection Scope
The inspectors performed partial walkdowns of the following systems:
- Protected system lineup on the intermediate closed cooling system on October 7, 2017
- Emergency Feedwater system following the scheduled 1R22 outage on October 20, 2017
- 2 hour backup air supply banks for the Emergency Feedwater System on December 8, 2017 The inspectors selected these systems based on their risk-significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors reviewed applicable operating procedures, system diagrams, the UFSAR, technical specifications, work orders, issue reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have impacted system performance of their intended safety functions. The inspectors also performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and were operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies. The inspectors also reviewed whether Exelon staff had properly identified equipment issues and entered them into the corrective action program for resolution with the appropriate significance characterization.
b. Findings
No findings were identified.
.2 Full System Walkdown
Main article: IP 71111.04S
a. Inspection Scope
On October 7, the inspectors performed a complete system walkdown of accessible portions of the core flood system to verify the existing equipment lineup was correct prior to the conclusion to the 1R22 outage. The inspectors reviewed operating procedures, surveillance tests, drawings, equipment line-up check-off lists, and the UFSAR to verify the system was aligned to perform its required safety functions. The inspectors also reviewed electrical power availability, component lubrication and equipment cooling, hangar and support functionality, and operability of support systems. The inspectors performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies. Additionally, the inspectors reviewed a sample of related issue reports and work orders to ensure Exelon appropriately evaluated and resolved any deficiencies. The inspectors confirmed that systems and components were aligned correctly, free from interference from temporary services or isolation boundaries, environmentally qualified, and protected from external threats. The inspectors also examined the material condition of the components for degradation and observed operating parameters of equipment to verify that there were no deficiencies. For identified degradation the inspectors confirmed the degradation was appropriately managed by the applicable aging management program.
b. Findings
No findings were identified.
==1R05 Fire Protection
.1 Resident Inspector Quarterly Walkdowns
Main article: IP 71111.05Q