{{#Wiki_filter:May 13, 2009 | {{#Wiki_filter:May 13, 2009 MEETING | ||
MEETING | |||
==SUMMARY== | ==SUMMARY== | ||
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. | LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC. | ||
FACILITY: VERMONT YANKEE NUCLEAR POWER STATION | |||
FACILITY: VERMONT YANKEE NUCLEAR POWER STATION | |||
==SUBJECT:== | ==SUBJECT:== | ||
==SUMMARY== | ==SUMMARY== | ||
OF THE APRIL 16, 2009, ANNUAL ASSESSMENT MEETING AND TOWN HALL MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC. | OF THE APRIL 16, 2009, ANNUAL ASSESSMENT MEETING AND TOWN HALL MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC. | ||
On April 16, 2009 at 3:30 p.m., an Annual Assessment Meeting was conducted at the Ramada Hotel and Conference Center, Brattleboro, Vermont, between the Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The NRC presented and discussed its assessment of the safety performance of the Vermont Yankee Nuclear Power Plant for the period of January 1 through December 31, 2008. In addition, at 7:00 p.m., a Town Hall Meeting was held to answer questions on the role of the NRC in ensuring safe plant operations. A list of meeting attendees is attached. | |||
On April 16, 2009 at 3:30 p.m., an Annual Assessment Meeting was conducted at the Ramada Hotel and Conference Center, Brattleboro, Vermont, between the Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The NRC presented and discussed its assessment of the safety performance of the Vermont Yankee Nuclear Power Plant for the period of January 1 through December 31, 2008. In addition, at 7:00 p.m., a Town Hall Meeting was held to answer questions on the role of the NRC in ensuring safe plant operations. A list of meeting attendees is attached. | The NRC presentation for the Annual Assessment Meeting included information on the NRC Organization, Reactor Oversight Program (ROP), and the results of NRC's performance assessment for Vermont Yankee. As part of this meeting, Entergy presented its perspective regarding the plant's performance and operational goals for 2009. At the end of the meeting between the NRC and Entergy, public attendees were offered the opportunity to ask questions of NRC officials. | ||
The NRC presentation for the Annual Assessment Meeting included information on the NRC Organization, Reactor Oversight Program (ROP), and the results of NRC's performance assessment for Vermont Yankee. As part of this meeting, Entergy presented its perspective regarding the plant's performance and operational goals for 2009. At the end of the meeting between the NRC and Entergy, public attendees were offered the opportunity to ask questions of NRC officials. | |||
Questions raised by members of the public and local media were also addressed by the NRC. | Questions raised by members of the public and local media were also addressed by the NRC. | ||
The | The NRCs assessment letter can be found on the NRCs public web page in ADAMS (ADAMS Accession No. ML090630467). A notice of the meeting was issued on March 19, 2009, and was posted on the NRCs public web page (ADAMS Accession No. ML090780293). The meeting slides can also be located in the ADAMS package (ADAMS Accession No. ML090630466). | ||
ADAMS is accessible from the NRC Web site at www.nrc.gov/reading-rm/adams.html. Sincerely, | ADAMS is accessible from the NRC Web site at www.nrc.gov/reading-rm/adams.html. | ||
Sincerely, | |||
/RA BY PAUL G. KROHN ACTING FOR/ | |||
Donald Jackson, Chief Projects Branch 5 Division of Reactor Projects | Donald Jackson, Chief Projects Branch 5 Division of Reactor Projects | ||
==Attachment:== | ==Attachment:== | ||
List of Attendees | List of Attendees | ||
A-1 LIST OF ATTENDEES VERMONT YANKEE NUCLEAR POWER PLANT APRIL 2009 ANNUAL ASSESSMENT MEETING THURSDAY, APRIL 16, 2009 3:30 p.m. | A-1 LIST OF ATTENDEES VERMONT YANKEE NUCLEAR POWER PLANT APRIL 2009 ANNUAL ASSESSMENT MEETING THURSDAY, APRIL 16, 2009 3:30 p.m. | ||
NAME | NAME ORGANIZATION Norm Rademacher Entergy Ruth Clark Guilford VT Citizen David Mannai Entergy Charles Baker Heather Jones NRC Justin Heinley NRC John Dreyfuss Uldis Vanags Vermont DPS Randy Sullivan NRC Jim Kim NRC Jonathan Rowley NRC Howard Shaffer Nuclear Public Outreach Larry Smith Entergy M.J. Colomb Entergy Tim Johnson WTSA - Media Bob Wanczyk Entergy Tom Buchanan NRC Phil Couture Entergy Susan Smallheer Rutland Herald Roland Lilee DPHS (NH) | ||
Chris Wamser | Chris Wamser Entergy George Patterson Contractor M Nawoj NH John Giarrusio, Jr. MEMA Dennis ODowd NH Radiation Control Program Gorty Baldwin WKVT Radio Sarah Kotkan Michael Dusaniwskyj NRC Anneliese Simmons NRC Michael Granoor Public Clay Turbull New England Coalition Harry Sprugt President Sachs Mike McKenney VY Patti Buck Public M. Philippon VY G. Gibbs VY P Van der Does Public Ellen Cote VY Mary Alice Hechert VCAN and NEC Ken Wit VCAN and NEC | ||
A-2 NAME ORGANIZATION Sally Shaw NEC John Ward CAN Brad Ferland Vermont Energy Partnership Mark Gilvesoe Entergy Matthew Campbell CBS 3 | |||
NAME | A-3 LIST OF ATTENDEES VERMONT YANKEE NUCLEAR POWER PLANT APRIL 2009 TOWN HALL MEETING THURSDAY, APRIL 16, 2009 7:00 p.m. | ||
NAME ORGANIZATION Ruth van Houten Chesterfield EMD Mike Granger Newfane, VT Jim Kim NRC Randy Sullivan NRC Daniel Sicken CAN Hattie Nestel CAN Ken West CAN Mike Nawoj NH Janet Schwarz CAN Anthony L. Stevens Entergy Bernard Buteau VY Clay Turnbull NEC Bill Murray Anneliese Simmons NRC Ami Rao NRC Justin Heinley NRC Heather Jones NRC John Ward Howard Shaffer ANS - PI Committee Jim Rogers Entergy Riaz Ghare Entergy Vermont Yankee Phillip DeVan Entergy Jonathan Rowley NRC Russ Pearson Alison MaCrae Jim Matteau Windham Regional Commission Charles Baker Walter Schwarz S&G Amit Kumar Entergy Claire Chang Peter van der Does Public Ned Childs | |||
ML090630467). A notice of the meeting was issued on March 19, 2009, and was posted on the | ML090630467). A notice of the meeting was issued on March 19, 2009, and was posted on the NRCs public web page (ADAMS Accession No. ML090780293). The meeting slides can also be located in the ADAMS package (ADAMS Accession No. ML090630466). ADAMS is accessible from the NRC Web site at www.nrc.gov/reading-rm/adams.html. | ||
Sincerely, | |||
/RA BY PAUL G. KROHN ACTING FOR/ | |||
Donald Jackson, Chief Projects Branch 5 Division of Reactor Projects | |||
==Attachment:== | ==Attachment:== | ||
List of Attendees Distribution | List of Attendees Distribution: J. Clifford, DRP M. Marshfield, SRI S. Collins, RA D. Jackson, DRP H. Jones, RI M. Dapas, ORA T. Setzer, DRP A. Rancourt, OA D. Lew, DRP A. Rao, DRP J. Kim, NRR SUNSI REVIEW COMPLETE _PGK______ (Reviewers Initials) ML091330823 After declaring this document An Official Agency Record it will be released to the Public Document Name: G:\DRP\BRANCH5\Annual Assessment Meetings\2008 EOC\Meeting Summaries\VY 2009 AA Meeting Summary.doc To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP N RI/DRP N NAME TSetzer/ TS DJackson/PGK for DATE 05/ 13 /09 05/ 13 /09}} | ||
: | |||
" C" = Copy without attachment/enclosure |
Latest revision as of 06:53, 14 November 2019
ML091330823 | |
Person / Time | |
---|---|
Site: | Vermont Yankee File:NorthStar Vermont Yankee icon.png |
Issue date: | 05/13/2009 |
From: | Diane Jackson NRC/RGN-I/DRP/PB5 |
To: | |
Jackson, D E RI/DRP/PB5/610-337-5306 | |
References | |
Download: ML091330823 (4) | |
Text
May 13, 2009 MEETING
SUMMARY
LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.
FACILITY: VERMONT YANKEE NUCLEAR POWER STATION
SUBJECT:
SUMMARY
OF THE APRIL 16, 2009, ANNUAL ASSESSMENT MEETING AND TOWN HALL MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC.
On April 16, 2009 at 3:30 p.m., an Annual Assessment Meeting was conducted at the Ramada Hotel and Conference Center, Brattleboro, Vermont, between the Nuclear Regulatory Commission (NRC) and Entergy Nuclear Operations, Inc. (Entergy). The NRC presented and discussed its assessment of the safety performance of the Vermont Yankee Nuclear Power Plant for the period of January 1 through December 31, 2008. In addition, at 7:00 p.m., a Town Hall Meeting was held to answer questions on the role of the NRC in ensuring safe plant operations. A list of meeting attendees is attached.
The NRC presentation for the Annual Assessment Meeting included information on the NRC Organization, Reactor Oversight Program (ROP), and the results of NRC's performance assessment for Vermont Yankee. As part of this meeting, Entergy presented its perspective regarding the plant's performance and operational goals for 2009. At the end of the meeting between the NRC and Entergy, public attendees were offered the opportunity to ask questions of NRC officials.
Questions raised by members of the public and local media were also addressed by the NRC.
The NRCs assessment letter can be found on the NRCs public web page in ADAMS (ADAMS Accession No. ML090630467). A notice of the meeting was issued on March 19, 2009, and was posted on the NRCs public web page (ADAMS Accession No. ML090780293). The meeting slides can also be located in the ADAMS package (ADAMS Accession No. ML090630466).
ADAMS is accessible from the NRC Web site at www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA BY PAUL G. KROHN ACTING FOR/
Donald Jackson, Chief Projects Branch 5 Division of Reactor Projects
Attachment:
List of Attendees
A-1 LIST OF ATTENDEES VERMONT YANKEE NUCLEAR POWER PLANT APRIL 2009 ANNUAL ASSESSMENT MEETING THURSDAY, APRIL 16, 2009 3:30 p.m.
NAME ORGANIZATION Norm Rademacher Entergy Ruth Clark Guilford VT Citizen David Mannai Entergy Charles Baker Heather Jones NRC Justin Heinley NRC John Dreyfuss Uldis Vanags Vermont DPS Randy Sullivan NRC Jim Kim NRC Jonathan Rowley NRC Howard Shaffer Nuclear Public Outreach Larry Smith Entergy M.J. Colomb Entergy Tim Johnson WTSA - Media Bob Wanczyk Entergy Tom Buchanan NRC Phil Couture Entergy Susan Smallheer Rutland Herald Roland Lilee DPHS (NH)
Chris Wamser Entergy George Patterson Contractor M Nawoj NH John Giarrusio, Jr. MEMA Dennis ODowd NH Radiation Control Program Gorty Baldwin WKVT Radio Sarah Kotkan Michael Dusaniwskyj NRC Anneliese Simmons NRC Michael Granoor Public Clay Turbull New England Coalition Harry Sprugt President Sachs Mike McKenney VY Patti Buck Public M. Philippon VY G. Gibbs VY P Van der Does Public Ellen Cote VY Mary Alice Hechert VCAN and NEC Ken Wit VCAN and NEC
A-2 NAME ORGANIZATION Sally Shaw NEC John Ward CAN Brad Ferland Vermont Energy Partnership Mark Gilvesoe Entergy Matthew Campbell CBS 3
A-3 LIST OF ATTENDEES VERMONT YANKEE NUCLEAR POWER PLANT APRIL 2009 TOWN HALL MEETING THURSDAY, APRIL 16, 2009 7:00 p.m.
NAME ORGANIZATION Ruth van Houten Chesterfield EMD Mike Granger Newfane, VT Jim Kim NRC Randy Sullivan NRC Daniel Sicken CAN Hattie Nestel CAN Ken West CAN Mike Nawoj NH Janet Schwarz CAN Anthony L. Stevens Entergy Bernard Buteau VY Clay Turnbull NEC Bill Murray Anneliese Simmons NRC Ami Rao NRC Justin Heinley NRC Heather Jones NRC John Ward Howard Shaffer ANS - PI Committee Jim Rogers Entergy Riaz Ghare Entergy Vermont Yankee Phillip DeVan Entergy Jonathan Rowley NRC Russ Pearson Alison MaCrae Jim Matteau Windham Regional Commission Charles Baker Walter Schwarz S&G Amit Kumar Entergy Claire Chang Peter van der Does Public Ned Childs
ML090630467). A notice of the meeting was issued on March 19, 2009, and was posted on the NRCs public web page (ADAMS Accession No. ML090780293). The meeting slides can also be located in the ADAMS package (ADAMS Accession No. ML090630466). ADAMS is accessible from the NRC Web site at www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA BY PAUL G. KROHN ACTING FOR/
Donald Jackson, Chief Projects Branch 5 Division of Reactor Projects
Attachment:
List of Attendees Distribution: J. Clifford, DRP M. Marshfield, SRI S. Collins, RA D. Jackson, DRP H. Jones, RI M. Dapas, ORA T. Setzer, DRP A. Rancourt, OA D. Lew, DRP A. Rao, DRP J. Kim, NRR SUNSI REVIEW COMPLETE _PGK______ (Reviewers Initials) ML091330823 After declaring this document An Official Agency Record it will be released to the Public Document Name: G:\DRP\BRANCH5\Annual Assessment Meetings\2008 EOC\Meeting Summaries\VY 2009 AA Meeting Summary.doc To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP N RI/DRP N NAME TSetzer/ TS DJackson/PGK for DATE 05/ 13 /09 05/ 13 /09