ML17201Q549: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:July 27, 2017  
{{#Wiki_filter:July 27, 2017
 
Mr. Al Queirolo, Director
  of Reactor Operations
Mr. Al Queirolo, Director
Massachusetts Institute of Technology
Nuclear Reactor Laboratory
Research Reactor
138 Albany Street, MS NW12-116A
Cambridge, MA 02139
SUBJECT:      MASSACHUSETTS INSTITUTE OF TECHNOLOGY - U.S. NUCLEAR
              REGULATORY COMMISSION ROUTINE INSPECTION REPORT
              NO. 50-020/2017-201
Dear Dr. Queirolo:
From April 25-27, 2017, the U.S. Nuclear Regulatory Commission (NRC or Commission)
conducted an inspection at the Massachusetts Institute of Technology Research Reactor facility.
The enclosed report documents the inspection results, which were discussed on April 27, 2017,
with you and members of your staff.
The inspection examined activities conducted under your license as they relate to safety and
compliance with Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed
personnel. Based on the results of this inspection, no findings of significance were identified.
No response to this letter is required.
In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public
inspections, exemptions, requests for withholding, a copy of this letter, its enclosure, and your
response (if any) will be available electronically for public inspection in the NRC Public
Document Room or from the NRCs document system (Agencywide Documents Access and
Management System (ADAMS)). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


  of Reactor Operations
A. Queirolo                                -2-
Massachusetts Institute of Technology Nuclear Reactor Laboratory
Should you have any questions concerning this inspection, please contact Mr. Johnny H. Eads at
Research Reactor
(301) 415-0136 or by electronic mail at Johnny.Eads@nrc.gov.
138 Albany Street, MS NW12-116A
                                            Sincerely,
Cambridge, MA  02139
                                            /RA/
                                            Anthony J. Mendiola, Chief
                                            Research and Test Reactors Oversight Branch
                                            Division of Policy and Rulemaking
                                            Office of Nuclear Reactor Regulation
Docket No. 50-020
License No. R-37
Enclosure:
As stated
cc: See next page


SUBJECT: MASSACHUSETTS INSTITUTE OF TECHNOLOGY - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE INSPECTION REPORT
NO. 50-020/2017-201
Dear Dr. Queirolo:
From April 25-27, 2017, the U.S. Nuclear Regulatory Commission (NRC or Commission)
conducted an inspection at the Massachusetts Institute of Technology Research Reactor facility. 
The enclosed report documents the inspection results, which were discussed on April 27, 2017,
with you and members of your staff.


  The inspection examined activities conducted under your license as they relate to safety and compliance with Commission's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed
  ML17201Q549; *concurred via e-mail                NRC-002
personnel. Based on the results of this inspection, no findings of significance were identified.  
  OFFICE        NRR/DPR/PROB*          NRR/DPR/PROB/LA*          NRR/DPR/PROB/BC
No response to this letter is required.  
  NAME          JEads                  NParker                    AMendiola
In accordance with Title 10 of the Code of Federal Regulations Section 2.390, "Public inspections, exemptions, requests for withholding," a copy of this letter, its enclosure, and your
  DATE          7/24/17                7/21/17                    7/27/17
response (if any) will be available electronica
                             
lly for public inspection in the NRC Public
Massachusetts Institute of Technology    Docket No. 50-020
Document Room or from the NRC's document system (Agencywide Documents Access and Management System (ADAMS)). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). 
cc:
A. Queirolo - 2 -
City Manager
Should you have any questions concerning this inspection, please contact Mr. Johnny H. Eads at
City Hall
(301) 415-0136 or by electronic mail at
Cambridge, MA 02139
Johnny.Eads@nrc.gov.  Sincerely, /RA/ 
Department of Environmental Protection
Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch
One Winter Street
Division of Policy and Rulemaking
Boston, MA 02108
Office of Nuclear Reactor Regulation
Mr. Jack Priest, Director
Radiation Control Program
Docket No. 50-020 License No. R-37
Department of Public Health
529 Main Street
Enclosure: 
Schrafft Center, Suite 1M2A
Charlestown, MA 02129
Mr. John Giarrusso, Chief
Planning and Preparedness Division
Massachusetts Emergency Management Agency
400 Worcester Road
Framingham, MA 01702-5399
Test, Research and Training
  Reactor Newsletter
P.O. Box 118300
University of Florida
Gainesville, FL 32611-8300
Ms. Sarah M. Don, Reactor Superintendent
Massachusetts Institute of Technology
Nuclear Reactor Laboratory
Research Reactor
138 Albany Street, MS NW12-116B
Cambridge, MA 02139


As stated
              U. S. NUCLEAR REGULATORY COMMISSION
              OFFICE OF NUCLEAR REACTOR REGULATION
Docket No.  50-020
License No.  R-37
Report No.  50-020/2017-201
Licensee:    Massachusetts Institute of Technology
Facility:    Nuclear Reactor Laboratory
Location:    Cambridge, Massachusetts
Dates:      April 25-27, 2017
Inspector:  Johnny Eads
Approved by: Anthony J. Mendiola, Chief
            Research and Test Reactors Oversight Branch
            Division of Policy and Rulemaking
            Office of Nuclear Reactor Regulation
                                                        Enclosure


cc: See next page 
                                      EXECUTIVE SUMMARY
                              Massachusetts Institute of Technology
                                    Nuclear Reactor Laboratory
                          NRC Inspection Report No. 50-020/2017-201
The primary focus of this routine, announced inspection was the onsite review of selected
aspects of the Massachusetts Institute of Technology (the licensees) Class I six megawatt
research reactor safety program including: (1) organization and staffing, (2) reactor operations,
(3) operator requalification, (4) maintenance and surveillance, (5) fuel handling, (6) experiments,
(7) procedures, and (8) emergency preparedness since the last U.S. Nuclear Regulatory
Commission (NRC) inspection of these areas. The licensees program was acceptably directed
toward the protection of public health and safety and in compliance with NRC requirements.
Organization and staffing
*  Organizational structure and staffing were consistent with technical specification (TS)
    requirements.
Reactor Operations
*  Reactor operations were conducted in accordance with procedure and the appropriate logs
    were being maintained.
Operator Requalification
*  Operator requalification was conducted as required by the Requalification Program and the
    program was being maintained up-to-date.
*  Operators were receiving biennial medical examinations as required.
Maintenance and Surveillance
*  The system for tracking and completing maintenance items and surveillance checks and
    calibrations was adequate and was being maintained as required.
*  Maintenance and surveillance records, performance, and reviews satisfied TS and
    procedure requirements.
Fuel Handling
*  Fuel was being controlled as required and fuel movements were conducted in accordance
    with TS and procedural requirements.
Experiments
*  The program for reviewing and conducting experiments satisfied procedural and TS
    requirements.


  ML17201Q549; *concurred via e-mail  NRC-002
                                              -2-
OFFICE NRR/DPR/PROB* NRR/DPR/PROB/LA* NRR/DPR/PROB/BC NAME JEads NParker AMendiola DATE 7/24/17 7/21/17 7/27/17  
Procedures
  Massachusetts Institute of Technology Docket No. 50-020
* The procedure review, revision, control, and implementation program satisfied TS
  cc: 
  requirements.
City Manager
Emergency Preparedness
The emergency preparedness program was conducted in accordance with the Emergency
  Plan (E-Plan).
*  Emergency response equipment was being maintained and inventoried as required.
*  Emergency drills were being conducted annually as required by the E-Plan.
* Emergency preparedness training for licensed operators and personnel from various
  support organizations was being completed as required.


City Hall
                                          REPORT DETAILS
Cambridge, MA  02139
Summary of Facility Status
The Massachusetts Institute of Technology (MIT or the licensee) Nuclear Reactor Laboratory
(NRL) six megawatt research and test reactor continued to be operated 24 hours a day, 7 days
a week in support of educational experiments, research and service irradiations, and reactor
operator training. During the inspection, the reactor was shutdown for maintenance.
1.    Organization and Staffing
      a.      Inspection Scope (Inspection Procedure (IP) 69006)
                The inspector reviewed the Massachusetts Institute of Technology Reactor
                (designated as MITR-II) organization and staffing to ensure that the requirements
                of technical specification (TS) 7.1, implemented through Renewed Facility
                Operating License R-37, Amendment 40 issued August 13, 2015, were being
                met regarding the following:
                *  Management responsibilities
                *  Qualifications of facility operations personnel
                *  MIT NRL Organization Chart, dated April 12, 2017
                *  Reactor Digital Logbook covering the period from March 2016 to present
                *  Staffing requirements for reactor operation stated in TS 7.1.3
                *  MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute
                    of Technology Annual Report to the U.S. Nuclear Regulatory Commission for
                    the Period January 1, 2016, to December 31, 2016.
      b.      Observations and Findings
                The inspector noted that the Director of Reactor Operations continued to report
                to the Director of the MIT NRL, who in turn reported to the President of the
                university through the Vice President for Research. This organization was
                consistent with that specified in the TS. The organizational structure and the
                responsibilities of the reactor staff had not changed since the last inspection.
                Staffing levels remained consistent with those noted during the last inspection of
                the facility. The current reactor operations organization consisted of the Director
                of Reactor Operations, the Deputy Director of Reactor Operations, the Assistant
                Director of Operations, the Superintendent of Operations, the Training
                Coordinator, a Quality Assurance Supervisor, and various reactor supervisors,
                and reactor operators (ROs). The Deputy Director of Reactor Operations, the
                Assistant Director of Reactor Operations, the Superintendent of Operations, the
                Quality Assurance Supervisor, the Training Coordinator, and the majority of the
                reactor supervisors were licensed senior reactor operators (SROs). In addition to
                the operations staff, there were various support groups, including a research
                staff, a research development group, a reactor engineering staff, maintenance
                personnel, and a reactor radiation protection group. Through a review of reactor


Department of Environmental Protection
                                            -2-
One Winter Street
        operations logs for the period from March 2016 through the present, and through
Boston, MA  02108
        interviews with operations personnel, the inspector determined that the licensee
        normally operated 24 hours a day with three crews and no shift rotation. Each
        operating crew was staffed with various personnel (with at least two licensed
        operators on duty at the MITR-II per shift). Operations shifts were scheduled for
        a period of 8 hours. The review of the reactor (console) logbooks and associated
        records confirmed that shift staffing during reactor operations met the minimum
        requirements for duty and on-call personnel specified in TS 7.1.3.
  c.    Conclusion
        The licensees organization and staffing were in compliance with the
        requirements specified in TS 7.1.
2. Reactor Operations
  a.    Inspection Scope (IP 69006)
        To verify that the licensee was conducting reactor operations in accordance with
        TS Sections 2 and 3 and procedural requirements, the inspector reviewed
        selected portions of the following:
        *  Reactor Digital Logbook covering the period from March 2016 to present
        *  MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute
            of Technology Annual Report to the U.S. Nuclear Regulatory Commission for
            the Period January 1, 2016, to December 31, 2016.
  b.    Observations and Findings
        (1)    Reactor Operation
                The inspector observed facility activities on various occasions during the
                week including routine reactor operations and updating the console logs
                while the reactor was shutdown for maintenance. Written procedures and
                checklists were used for each activity as required. It was noted that the
                reactor operators followed the appropriate procedures, were
                knowledgeable of the required actions, and professional in the conduct of
                their duties.
        (2)    Staff Communication
                During the inspection, the inspector observed reactor operator turnover
                activities during the shift. The status of the reactor and the facility was
                discussed on each occasion as required. The oncoming personnel were
                briefed on the upcoming activities and scheduled events before assuming
                the operations duty. Through direct observation and records review, the
                inspector verified that the content of turnover briefings was appropriate


                                            -3-
Mr. Jack Priest, Director Radiation Control Program Department of Public Health 
                  and that shift activities and plant conditions were discussed in sufficient
                  detail.
  c.    Conclusion
        MITR-II reactor operations, as well as turnovers and operator cognizance of
        facility conditions during routine operations, were acceptable.
3. Operator Requalification
  a.    Inspection Scope (IP 69003)
        To verify that the licensee was complying with the requirements of Title 10 of the
        Code of Federal Regulations (10 CFR) Part 55 and TS 7.2.3.3 (b) and
        conforming to Chapter 12, Sections 12.1 and 12.10 of the facility safety analysis
        report, the inspector reviewed selected aspects of the following:
        *  Current status of operator licenses
        *  Reactor Digital Logbook covering the period from March 2016 to present
        *  Results of the annual written examinations completed in 2016
        *  Medical examination records for selected operators for the past 2 years
        *  Procedure Manual (PM) 1.16, Requalification and Qualification, latest
            revision dated February 20, 2013.
  b.    Observations and Findings
        There were 21 individuals licensed to operate the reactor at MIT. Of those
        personnel, 15 were qualified SROs and 6 were ROs. A review of various
        Requalification Program records indicated that the program was maintained
        up-to-date and that SRO and RO licenses were current. MITR-II operator files
        and reactor logs also showed that all operators maintained active duty status with
        the exception of one SRO who was designated as inactive by the facility. A
        review of the MITR Safety Committee (MITRSC) meeting minutes and
        independent audit results indicated that the program was being audited annually
        as required by TS 7.2.3.3.(b).
        A review of the pertinent logs and records also showed that training was being
        conducted in accordance with the licensees requalification and training program.
        A series of lectures were given to operators during the 2 year training and
        requalification cycle. Information regarding facility changes, procedure changes,
        and other relevant information was routinely routed to all licensed operators for
        their review. The inspector verified that the required reactor operations, reactivity
        manipulations, other operations activities, and reactor supervisor activities were
        being completed and the appropriate records were being maintained. The
        inspector also noted that all operators were receiving biennial medical
        examinations within the time frame allowed as required by the program.


529 Main Street
                                            -4-
  c.    Conclusion
        Operator requalification was up-to-date and being completed as required by the
        MITR-II Operator Requalification Program. Operators were receiving biennial
        medical examinations as required.
4. Maintenance and Surveillance
  a.    Inspection Scope (IPs 69006 and 69010)
        To verify that the licensee was meeting the surveillance requirements specified in
        TS Section 4 and that maintenance was being conducted, the inspector reviewed
        selected aspects of the following:
        *  MITR-II Job Workbook
        *  MITR-II Daily Operations Schedule
        *  Reactor Digital Logbook covering the period from March 2016 to present
        *  MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute
            of Technology Annual Report to the U.S. Nuclear Regulatory Commission for
            the Period January 1, 2016, to December 31, 2016.
  b.    Observations and Findings
        (1)    Maintenance
                The inspector reviewed the system that the licensee had developed to
                track and complete maintenance activities. The system was designed to
                ensure that all maintenance activities were planned and completed as
                scheduled, that post maintenance testing was conducted, and that the
                entire process was documented appropriately. The licensee used a
                locally developed system called the Test and Calibration Tracker which
                listed nearly all the tests, checks, and calibrations that were due on a
                monthly basis, as well as MITR-II Systems, Tests, and Calibrations
                notebooks to document completion of the various periodic maintenance
                and surveillance activities. The inspector noted that all such tasks were
                tracked through this system. The program appeared to be effective.
        (2)    Surveillance
                Various periodic surveillance verifications and calibration records of
                equipment, including the testing of various reactor systems,
                instrumentation, and auxiliary systems were reviewed by the inspector.
                TS surveillance items were completed on schedule as required by TS and
                in accordance with licensee procedures. The results of selected tests,
                checks, and calibrations reviewed by the inspector were noted to be
                within the TS and procedurally prescribed parameters.


Schrafft Center, Suite 1M2A
                                          -5-
Charlestown, MA  02129
  c.    Conclusion
Mr. John Giarrusso, Chief 
        The system for tracking and completing maintenance items and surveillance
Planning and Preparedness Division 
        checks and calibrations was adequate and was being maintained as required.
Massachusetts Emergency Management Agency 
        Maintenance and surveillance records, performance, and reviews satisfied TS
 
        and procedure requirements.
400 Worcester Road 
 
Framingham, MA  01702-5399
Test, Research and Training
 
  Reactor Newsletter
P.O. Box 118300
University of Florida
Gainesville, FL  32611-8300
Ms. Sarah M. Don, Reactor Superintendent
Massachusetts Institute of Technology 
Nuclear Reactor Laboratory
 
Research Reactor 138 Albany Street, MS NW12-116B Cambridge, MA  02139 
Enclosure U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION
  Docket No.  50-020
 
License No.  R-37
 
  Report No.  50-020/2017-201
 
Licensee:  Massachusetts Institute of Technology
 
Facility:  Nuclear Reactor Laboratory
 
Location:  Cambridge, Massachusetts
Dates:  April 25-27, 2017
 
Inspector:  Johnny Eads
Approved by:  Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch
Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
 
  EXECUTIVE SUMMARY
Massachusetts Institute of Technology Nuclear Reactor Laboratory
NRC Inspection Report No. 50-020/2017-201
The primary focus of this routine, announced inspection was the onsite review of selected
aspects of the Massachusetts Institute of Technology (the licensee's) Class I six megawatt
research reactor safety program including:  (1) organization and staffing, (2) reactor operations, (3) operator requalification, (4) maintenance and surveillance, (5) fuel handling, (6) experiments, (7) procedures, and (8) emergency preparedness since the last U.S. Nuclear Regulatory
 
Commission (NRC) inspection of these areas.  The licensee's program was acceptably directed toward the protection of public health and safety and in compliance with NRC requirements.
 
Organization and staffing
* Organizational structure and staffing were consistent with technical specification (TS)
requirements.
Reactor Operations 
* Reactor operations were conducted in accordance with procedure and the appropriate logs
were being maintained.
Operator Requalification
* Operator requalification was conducted as required by the Requalification Program and the program was being maintained up-to-date.
* Operators were receiving biennial medical examinations as required.
Maintenance and Surveillance
* The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.
* Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.
Fuel Handling
* Fuel was being controlled as required and fuel movements were conducted in accordance with TS and procedural requirements.
Experiments
* The program for reviewing and conducting experiments satisfied procedural and TS
requirements. 
- 2 -Procedures
* The procedure review, revision, control, and implementation program satisfied TS
requirements.
Emergency Preparedness
* The emergency preparedness program was conduc
ted in accordance with the Emergency
Plan (E-Plan).
* Emergency response equipment was being maintained and inventoried as required.
* Emergency drills were being conducted annually as required by the E-Plan.
* Emergency preparedness training for licensed operators and personnel from various support organizations was being completed as required.
 
  REPORT DETAILS
Summary of Facility Status
The Massachusetts Institute of Technology (MIT or the licensee) Nuclear Reactor Laboratory
(NRL) six megawatt research and test reactor continued to be operated 24 hours a day, 7 days
a week in support of educational experiments, research and service irradiations, and reactor
operator training.  During the inspection, the reactor was shutdown for maintenance.
1. Organization and Staffing
  a. Inspection Scope (Inspection Procedure (IP) 69006)
The inspector reviewed the Massachusetts Institute of Technology Reactor (designated as MITR-II) organization and staffing to ensure that the requirements
of technical specification (TS) 7.1, implemented through Renewed Facility
Operating License R-37, Amendment 40 issued August 13,  2015, were being
met regarding the following:
* Management responsibilities
* Qualifications of facility operations personnel
* MIT NRL Organization Chart, dated April 12, 2017
* Reactor Digital Logbook covering the period from March 2016 to present
* Staffing requirements for reactor operation stated in TS 7.1.3
* "MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for
the Period January 1, 2016, to December 31, 2016." 
b. Observations and Findings
The inspector noted that the Director of Reactor Operations continued to report to the Director of the MIT NRL, who in turn reported to the President of the
university through the Vice President for Research.  This organization was
consistent with that specified in the TS.  The organizational structure and the
responsibilities of the reactor staff had not changed since the last inspection.
Staffing levels remained consistent with those noted during the last inspection of
the facility.  The current reactor operations organization consisted of the Director
of Reactor Operations, the Deputy Director of Reactor Operations, the Assistant
Director of Operations, the Superintendent of Operations, the Training
Coordinator, a Quality Assurance Supervisor, and various reactor supervisors, and reactor operators (ROs).  The Deputy Director of Reactor Operations, the Assistant Director of Reactor Operations, the Superintendent of Operations, the
Quality Assurance Supervisor, the Training Coordinator, and the majority of the
reactor supervisors were licensed senior reactor operators (SROs).  In addition to
the operations staff, there were various support groups, including a research staff, a research development group, a reactor engineering staff, maintenance personnel, and a reactor radiation protection group.  Through a review of reactor 
- 2 -  operations logs for the period from March 2016 through the present, and through interviews with operations personnel, the inspector determined that the licensee normally operated 24 hours a day with three crews and no shift rotation.  Each
operating crew was staffed with various personnel (with at least two licensed
operators on duty at the MITR-II per shift).  Operations shifts were scheduled for
a period of 8 hours.  The review of the reactor (console) logbooks and associated
records confirmed that shift staffing during reactor operations met the minimum requirements for duty and on-call personnel specified in TS 7.1.3.
c. Conclusion
The licensee's organization and staffing were in compliance with the requirements specified in TS 7.1.
2. Reactor Operations
a. Inspection Scope (IP 69006)
To verify that the licensee was conducting reactor operations in accordance with
TS Sections 2 and 3 and procedural requirements, the inspector reviewed
selected portions of the following:
* Reactor Digital Logbook covering the period from March 2016 to present
* "MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for
the Period January 1, 2016, to December 31, 2016."
b. Observations and Findings
(1) Reactor Operation
The inspector observed facility activities on various occasions during the week including routine reactor operations and updating the console logs while the reactor was shutdown for maintenance.  Written procedures and
checklists were used for each activity as required.  It was noted that the
reactor operators followed the appropriate procedures, were
knowledgeable of the required actions, and professional in the conduct of
their duties.
(2) Staff Communication
During the inspection, the inspector observed reactor operator turnover
activities during the shift.  The status of the reactor and the facility was discussed on each occasion as required.  The oncoming personnel were briefed on the upcoming activities and scheduled events before assuming
the operations duty.  Through direct observation and records review, the
inspector verified that the content of turnover briefings was appropriate 
- 3 -  and that shift activities and plant conditions were discussed in sufficient
detail.  c. Conclusion
MITR-II reactor operations, as well as turnovers and operator cognizance of
facility conditions during routine operations, were acceptable.
3. Operator Requalification
  a. Inspection Scope (IP 69003)
To verify that the licensee was complying with the requirements of Title 10 of the
Code of Federal Regulations (10 CFR) Part 55 and TS 7.2.3.3 (b) and conforming to Chapter 12, Sections 12.1 and 12.10 of the facility safety analysis
report, the inspector reviewed selected aspects of the following:
* Current status of operator licenses
* Reactor Digital Logbook covering the period from March 2016 to present
* Results of the annual written examinations completed in 2016
* Medical examination records for selected operators for the past 2 years
* Procedure Manual (PM) 1.16, "Requalification and Qualification," latest revision dated February 20, 2013.
b. Observations and Findings
There were 21 individuals licensed to operate the reactor at MIT.  Of those personnel, 15 were qualified SROs and 6 were ROs.  A review of various Requalification Program records indicated that the program was maintained
up-to-date and that SRO and RO licenses were current.  MITR-II operator files
and reactor logs also showed that all operators maintained active duty status with
the exception of one SRO who was designated as inactive by the facility.  A review of the MITR Safety Committee (MITRSC) meeting minutes and independent audit results indicated that the program was being audited annually
as required by TS 7.2.3.3.(b).
 
A review of the pertinent logs and records also showed that training was being
conducted in accordance with the licensee's requalification and training program.  A series of lectures were given to operators during the 2 year training and requalification cycle.  Information regarding facility changes, procedure changes, and other relevant information was routinely routed to all licensed operators for
their review.  The inspector verified that the required reactor operations, reactivity
manipulations, other operations activities, and reactor supervisor activities were being completed and the appropriate records were being maintained.  The inspector also noted that all operators were receiving biennial medical
examinations within the time frame allowed as required by the program.
    
- 4 -  c. Conclusion
Operator requalification was up-to-date and being completed as required by the
MITR-II Operator Requalification Program.  Operators were receiving biennial
medical examinations as required.
4. Maintenance and Surveillance
  a. Inspection Scope (IPs 69006 and 69010)
To verify that the licensee was meeting the surveillance requirements specified in
TS Section 4 and that maintenance was being conducted, the inspector reviewed selected aspects of the following:
* MITR-II Job Workbook
* MITR-II Daily Operations Schedule 
* Reactor Digital Logbook covering the period from March 2016 to present
* "MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for
the Period January 1, 2016, to December 31, 2016."
b. Observations and Findings
(1) Maintenance
The inspector reviewed the system that the licensee had developed to track and complete maintenance activities.  The system was designed to
ensure that all maintenance activities were planned and completed as
scheduled, that post maintenance testing was conducted, and that the
entire process was documented appropriately.  The licensee used a
locally developed system called the "Test and Calibration Tracker" which listed nearly all the tests, checks, and calibrations that were due on a monthly basis, as well as MITR-II "Systems, Tests, and Calibrations" notebooks to document completion of the various periodic maintenance
and surveillance activities.  The inspector noted that all such tasks were
tracked through this system.  The program appeared to be effective.
(2) Surveillance
Various periodic surveillance verifications and calibration records of
equipment, including the testing of various reactor systems, instrumentation, and auxiliary systems
were reviewed by the inspector.  TS surveillance items were completed on schedule as required by TS and
in accordance with licensee procedures.  The results of selected tests,
checks, and calibrations reviewed by the inspector were noted to be
within the TS and procedurally prescribed parameters.
 
- 5 - 
c. Conclusion  
The system for tracking and completing maintenance items and surveillance  
checks and calibrations was adequate and was being maintained as required.
Maintenance and surveillance records, performance, and reviews satisfied TS  
and procedure requirements.  
5. Fuel Handling
5. Fuel Handling
  a. Inspection Scope (IP 69009)  
  a.   Inspection Scope (IP 69009)
To ensure that the licensee was following the requirements of TSs 3.1.4, 3.1.6, 4.1.5, and 5.4, the inspector reviewed selected aspects of the following:  
        To ensure that the licensee was following the requirements of TSs 3.1.4, 3.1.6,
* Reactor Digital Logbook covering the period from March 2016 to present  
        4.1.5, and 5.4, the inspector reviewed selected aspects of the following:
* Approved packets for core configurations completed in 2016 and 2017, including:  
        *   Reactor Digital Logbook covering the period from March 2016 to present
"Fuel Loading Permission" Form (form revision dated February 20, 2013), completed for fuel element transfers in 2016 and 2017 to date  
        *   Approved packets for core configurations completed in 2016 and 2017,
b. Observations and Findings  
            including:
The inspector reviewed the fuel movement process and verified that fuel moves were conducted according to established procedure and documented on specific  
                      Fuel Loading Permission Form (form revision dated
fuel movement sheets developed by the Reactor Engineer. The inspector  
                        February 20, 2013), completed for fuel element transfers in 2016
reviewed selected fuel movement sheets for 2016 and to date in 2017. They had  
                        and 2017 to date
been developed and used for each specific core refueling as required.  
  b.   Observations and Findings
c. Conclusion  
        The inspector reviewed the fuel movement process and verified that fuel moves
Fuel was being controlled as required and fuel movements were performed in  
        were conducted according to established procedure and documented on specific
accordance with approved procedures and TS requirements.  
        fuel movement sheets developed by the Reactor Engineer. The inspector
        reviewed selected fuel movement sheets for 2016 and to date in 2017. They had
        been developed and used for each specific core refueling as required.
  c.   Conclusion
        Fuel was being controlled as required and fuel movements were performed in
        accordance with approved procedures and TS requirements.
6. Experiments
6. Experiments
  a. Inspection Scope (IP 69005)  
  a.   Inspection Scope (IP 69005)
To verify compliance with the licensee's procedures, TSs 6, 7.5, and 10 CFR 50.59 the inspector reviewed the following:  
        To verify compliance with the licensees procedures, TSs 6, 7.5, and
* Reactor Digital Logbook covering the period from March 2016 to present  
        10 CFR 50.59 the inspector reviewed the following:
* Experiment Review Process documented in PM 1.10, "Experiment Review and Approval," latest revision dated February 20, 2013.  
        *   Reactor Digital Logbook covering the period from March 2016 to present
b. Observations and Findings  
        *   Experiment Review Process documented in PM 1.10, Experiment Review
            and Approval, latest revision dated February 20, 2013.
The inspector reviewed the experimental review and approval process described  
  b.   Observations and Findings
in PM 1.10. The inspector reviewed selected safety review forms and irradiation
        The inspector reviewed the experimental review and approval process described
- 6 -  request forms for experiments that were currently active.  The experimental facilities and/or equipment had been evaluated in accordance with TS requirements and the associated data sheets indicated that the experiments
        in PM 1.10. The inspector reviewed selected safety review forms and irradiation
would be within the specified limits.  The analysis for each had been performed
and the reviews and approvals completed.  The appropriate reviews and
approvals had also been completed for the samples and/or materials to be
irradiated and the experiments were conducted under the cognizance of the reactor supervisor and in accordance with the specified requirements.
c. Conclusion
Conduct and control of experiments met the requirements of the TS and the applicable facility procedures.
7. Procedures
  a. Inspection Scope (IP 69008)
To verify that the licensee was meeting the requirements of TS 7.4, the


inspectors reviewed selected aspects of the following:  
                                            -6-
  PM 1.4, "Review and Approval of Plans, Procedures and Facility Equipment and Changes Thereto," which included:  
        request forms for experiments that were currently active. The experimental
- PM 1.4.1, "Plan, Procedure, and Equipment Change Classification," latest revision dated February 20, 2013 - PM 1.4.2, "Class C Review and Approval," latest revision dated  
        facilities and/or equipment had been evaluated in accordance with TS
February 20, 2013 - PM 1.4.3, "Class B Review and Approval," latest revision dated  
        requirements and the associated data sheets indicated that the experiments
February 20, 2013 - PM 1.4.4, "Class A Review and Approval," latest revision dated  
        would be within the specified limits. The analysis for each had been performed
February 20, 2013 - PM 1.4.5, "Safety Review Form," latest revision dated  
        and the reviews and approvals completed. The appropriate reviews and
February 20, 2013 - PM 1.4.6, "Procedure Manuals," latest revision dated  
        approvals had also been completed for the samples and/or materials to be
February 20, 2013  
        irradiated and the experiments were conducted under the cognizance of the
        reactor supervisor and in accordance with the specified requirements.
  c.    Conclusion
        Conduct and control of experiments met the requirements of the TS and the
        applicable facility procedures.
7. Procedures
  a.    Inspection Scope (IP 69008)
        To verify that the licensee was meeting the requirements of TS 7.4, the
        inspectors reviewed selected aspects of the following:
            PM 1.4, Review and Approval of Plans, Procedures and Facility Equipment
            and Changes Thereto, which included:
                      -   PM 1.4.1, Plan, Procedure, and Equipment Change
                          Classification, latest revision dated February 20, 2013
                      -   PM 1.4.2, Class C Review and Approval, latest revision dated
                          February 20, 2013
                      -   PM 1.4.3, Class B Review and Approval, latest revision dated
                          February 20, 2013
                      -   PM 1.4.4, Class A Review and Approval, latest revision dated
                          February 20, 2013
                      -   PM 1.4.5, Safety Review Form, latest revision dated
                          February 20, 2013
                      -   PM 1.4.6, Procedure Manuals, latest revision dated
                          February 20, 2013
            PM 1.5, Procedure Adherence and Temporary Change Method, latest
            revision dated February 20, 2013
  b.    Observations and Findings
        The inspector noted that procedures had been developed for reactor operations
        and safety as required by the TS 7.4. The licensees procedures were found to
        be acceptable for the current facility status and staffing level. The inspector
        noted that the administrative procedure specified the responsibilities of the
        various positions and for the MITRSC.


  PM 1.5, "Procedure Adherence and Temporary Change Method," latest revision dated February 20, 2013
                                        -7-
b.  Observations and Findings
        Operations procedures were typically reviewed by operators and support
The inspector noted that procedures had been developed for reactor operations
        personnel prior to being used/implemented and were revised as needed. The
and safety as required by the TS 7.4.  The licensee's procedures were found to
        inspector noted that abnormal and emergency procedures were reviewed
be acceptable for the current facility status and staffing level.  The inspector noted that the administrative procedure specified the responsibilities of the various positions and for the MITRSC.
        annually by all licensed operators as required and revised when needed. Major
 
        procedure revisions were reviewed and approved by the Director of Reactor
- 7 - Operations procedures were typically reviewed by operators and support personnel prior to being used/implemented and were revised as needed. The inspector noted that abnormal and emergency procedures were reviewed  
        Operations and submitted to the MITRSC for review. All procedure changes
annually by all licensed operators as required and revised when needed. Major  
        were routinely routed to all operators for review as well.
procedure revisions were reviewed and approved by the Director of Reactor  
        It was also noted that management and supervisory oversight was focused on
Operations and submitted to the MITRSC for review. All procedure changes  
        proper implementation and adherence to procedures. Through observation of
were routinely routed to all operators for review as well.  
        various activities in progress during the inspection, the inspector noted that
It was also noted that management and supervisory oversight was focused on  
        adherence to procedures was adequate.
proper implementation and adherence to procedures. Through observation of  
  c.   Conclusion
various activities in progress during the inspection, the inspector noted that  
        Procedures were properly prepared and implemented in compliance with license
adherence to procedures was adequate.  
        requirements.
c. Conclusion  
8. Emergency Preparedness
Procedures were properly prepared and implemented in compliance with license  
  a.  Inspection Scope (IP 69011)
        The inspector reviewed selected aspects to verify compliance with TS 7.2.3.d
        and the licensees Emergency Plan and associated procedures of the following:
        *    Training records for MITR Support Personnel
        *    Review and Critique of the 2016 Emergency Exercise conducted on
              August 16, 2016
        *    Review and Critique of the 2016 actual medical emergencies which occurred
              on February 13, 2016 and July 6, 2016
        *    PM 4.0, MITR-II Emergency Plan and Procedures, revision dated
              June 20, 2013
        *    PM 4.4.4, Emergency Operating Procedures
  b.  Observations and Findings
        The inspector reviewed the Emergency Plan (EP) and implementing procedures
        in use at the reactor and verified that the procedures were reviewed annually by
        all licensed operators in accordance with the Operator Requalification Program.
        Through records reviews and interviews with facility emergency personnel (i.e.,
        licensed operators or emergency responders), the inspector determined that they
        were knowledgeable of the proper actions to take in case of an emergency.
        Training for staff members had been conducted annually as required and
        documented acceptably.
        Emergency training for MIT Police Department personnel was required to be
        conducted annually by EP Section 4.10.1.1. The inspector reviewed the training
        records and noted that the most recent training had been completed as required.


requirements.
                                            -8-
8. Emergency Preparedness
          The inspector verified that letters of agreement with various emergency support
  a. Inspection Scope (IP 69011)
          organizations were on file and being maintained.
The inspector reviewed selected aspects to verify compliance with TS 7.2.3.d and the licensee's Emergency Plan and associated procedures of the following:
          Communications capabilities with support groups were acceptable and were
* Training records for MITR Support Personnel
          verified annually through a communications check with the various organizations.
* Review and Critique of the 2016 Emergency Exercise conducted on August 16, 2016
          Emergency call lists had been revised and updated as needed and were
* Review and Critique of the 2016 actual medical emergencies which occurred on February 13, 2016 and July 6, 2016
          available in various areas of the facility, including in controlled copies of the
* PM 4.0, "MITR-II Emergency Plan and Procedures," revision dated June 20, 2013
          Emergency Procedures Manuals. The inspector also verified that emergency
* PM 4.4.4, "Emergency Operating Procedures"
          equipment was being inventoried quarterly as required.
b. Observations and Findings
          The inspector verified compliance with the EP requirement for annual emergency
          plan drills. The licensee met this requirement by conducting radiological
The inspector reviewed the Emergency Plan (EP) and implementing procedures
          emergency and medical emergency drills each year or by taking credit for an
in use at the reactor and verified that the procedures were reviewed annually by all licensed operators in accordance with the Operator Requalification Program.
          actual emergency. Following each drill, a critique was conducted to identify
          areas of strength and weakness. Drills and critiques were documented in writing
Through records reviews and interviews with facility emergency personnel (i.e.,
          as referenced above. The drills appeared to be challenging and provided a good
licensed operators or emergency responders), the inspector determined that they
          indication of each organizations responsiveness and capabilities.
were knowledgeable of the proper actions to take in case of an emergency.  Training for staff members had been conducted annually as required and documented acceptably. 
  c.     Conclusion
Emergency training for MIT Police Department personnel was required to be
          The licensee was maintaining acceptable emergency preparedness in
conducted annually by EP Section 4.10.1.1.  The inspector reviewed the training
          accordance with TS and E-Plan requirements.
records and noted that the most recent training had been completed as required. 
- 8 -  The inspector verified that letters of agreement with various emergency support organizations were on file and being maintained.  
Communications capabilities with support groups were acceptable and were  
verified annually through a communications check with the various organizations.
Emergency call lists had been revised and updated as needed and were  
available in various areas of the facility, including in controlled copies of the Emergency Procedures Manuals. The inspector also verified that emergency equipment was being inventoried quarterly as required.  
The inspector verified compliance with the EP requirement for annual emergency  
plan drills. The licensee met this requirement by conducting radiological emergency and medical emergency drills each year or by taking credit for an actual emergency. Following each drill, a critique was conducted to identify  
areas of strength and weakness. Drills and critiques were documented in writing  
as referenced above. The drills appeared to be challenging and provided a good  
indication of each organization's responsiveness and capabilities.  
c. Conclusion  
The licensee was maintaining acceptable emergency preparedness in  
accordance with TS and E-Plan requirements.  
9. Exit Interview
9. Exit Interview
  The inspection scope and results were summarized on April 27, 2017, with members of  
  The inspection scope and results were summarized on April 27, 2017, with members of
licensee management. The inspector described the areas inspected and discussed the  
  licensee management. The inspector described the areas inspected and discussed the
preliminary inspection findings. The licensee acknowledged the results of the inspection and did not identify as proprietary any of the material provided to or reviewed during the inspection.
  preliminary inspection findings. The licensee acknowledged the results of the inspection
  PARTIAL LIST OF PERSONS CONTACTED
  and did not identify as proprietary any of the material provided to or reviewed during the
 
  inspection.
Licensee Personnel:  
 
J. Bernard Senior Advisor, Research Staff  
                          PARTIAL LIST OF PERSONS CONTACTED
S. Don   Superintendent Operations  
Licensee Personnel:
J. Foster Deputy Director of Reactor Operations  
J. Bernard         Senior Advisor, Research Staff
E. Lau   Assistant Director of Reactor Operations W. McCarthy Reactor Radiation Protection Officer and Deputy Director, MIT     Environment, Health, and Safety Office  
S. Don             Superintendent Operations
A. Queirolo Director of Reactor Operations  
J. Foster           Deputy Director of Reactor Operations
S. Tucker Quality Assurance Supervisor  
E. Lau             Assistant Director of Reactor Operations
W. McCarthy         Reactor Radiation Protection Officer and Deputy Director, MIT
                    Environment, Health, and Safety Office
A. Queirolo         Director of Reactor Operations
S. Tucker           Quality Assurance Supervisor
                          INSPECTION PROCEDURES USED
IP 69003    Class 1 Research and Test Reactor Operator Licenses, Requalification, and
                    Medical Examinations
IP 69005    Class 1 Research and Test Reactor Experiments
IP 69006    Class 1 Research and Test Reactors Organization and Operations and
                    Maintenance Activities
IP 69008    Class 1 Procedures
IP 69009    Class 1 Research and Test Reactor Fuel Movement
IP 69010    Class 1 Research and Test Reactor Surveillance
IP 69011    Class 1 Research and Test Reactor Emergency Preparedness
                      ITEMS OPENED, CLOSED, AND DISCUSSED
Opened:
None
Closed:
None


  INSPECTION PROCEDURES USED
                        LIST OF ACRONYMS USED
  IP 69003 Class 1 Research and Test Reactor Operator Licenses, Requalification, and Medical Examinations IP 69005 Class 1 Research and Test Reactor Experiments IP 69006 Class 1 Research and Test Reactors Organization and Operations and
CFR   Code of Federal Regulations
Maintenance Activities IP 69008 Class 1 Procedures
EP     Emergency Plan
IP 69009 Class 1 Research and Test Reactor Fuel Movement
IP     Inspection Procedure
IP 69010 Class 1 Research and Test Reactor Surveillance IP 69011 Class 1 Research and Test Reactor Emergency Preparedness
MIT   Massachusetts Institute of Technology
MITR  Massachusetts Institute of Technology Reactor
ITEMS OPENED, CLOSED, AND DISCUSSED
MITRSC Massachusetts Institute of Technology Reactor Safety Committee
 
NRC   U.S. Nuclear Regulatory Commission
Opened:  None
NRL   Nuclear Reactor Laboratory
PM     Procedure Manual
Closed:  None 
RO     Reactor Operator
  LIST OF ACRONYMS USED
SRO   Senior Reactor Operator
 
TS     Technical Specification
CFR Code of Federal Regulations
EP Emergency Plan  
IP Inspection Procedure  
MIT Massachusetts Institute of Technology  
MITR  Massachusetts Institute of Technology Reactor  
MITRSC Massachusetts Institute of Technology Reactor Safety Committee NRC U.S. Nuclear Regulatory Commission NRL Nuclear Reactor Laboratory  
PM Procedure Manual  
RO Reactor Operator  
SRO Senior Reactor Operator TS Technical Specification
}}
}}

Latest revision as of 00:53, 30 October 2019

Massachusetts Institute of Technology U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-020/2017-201
ML17201Q549
Person / Time
Site: MIT Nuclear Research Reactor
Issue date: 07/27/2017
From: Anthony Mendiola
Research and Test Reactors Oversight Branch
To: Queirolo A
Massachusetts Institute of Technology (MIT)
Eads J
References
50-020/2017-201, IR 2017201
Download: ML17201Q549 (17)


See also: IR 05000020/2017201

Text

July 27, 2017

Mr. Al Queirolo, Director

of Reactor Operations

Massachusetts Institute of Technology

Nuclear Reactor Laboratory

Research Reactor

138 Albany Street, MS NW12-116A

Cambridge, MA 02139

SUBJECT: MASSACHUSETTS INSTITUTE OF TECHNOLOGY - U.S. NUCLEAR

REGULATORY COMMISSION ROUTINE INSPECTION REPORT

NO. 50-020/2017-201

Dear Dr. Queirolo:

From April 25-27, 2017, the U.S. Nuclear Regulatory Commission (NRC or Commission)

conducted an inspection at the Massachusetts Institute of Technology Research Reactor facility.

The enclosed report documents the inspection results, which were discussed on April 27, 2017,

with you and members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed

personnel. Based on the results of this inspection, no findings of significance were identified.

No response to this letter is required.

In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public

inspections, exemptions, requests for withholding, a copy of this letter, its enclosure, and your

response (if any) will be available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (Agencywide Documents Access and

Management System (ADAMS)). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

A. Queirolo -2-

Should you have any questions concerning this inspection, please contact Mr. Johnny H. Eads at

(301) 415-0136 or by electronic mail at Johnny.Eads@nrc.gov.

Sincerely,

/RA/

Anthony J. Mendiola, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Docket No.50-020

License No. R-37

Enclosure:

As stated

cc: See next page

ML17201Q549; *concurred via e-mail NRC-002

OFFICE NRR/DPR/PROB* NRR/DPR/PROB/LA* NRR/DPR/PROB/BC

NAME JEads NParker AMendiola

DATE 7/24/17 7/21/17 7/27/17

Massachusetts Institute of Technology Docket No.50-020

cc:

City Manager

City Hall

Cambridge, MA 02139

Department of Environmental Protection

One Winter Street

Boston, MA 02108

Mr. Jack Priest, Director

Radiation Control Program

Department of Public Health

529 Main Street

Schrafft Center, Suite 1M2A

Charlestown, MA 02129

Mr. John Giarrusso, Chief

Planning and Preparedness Division

Massachusetts Emergency Management Agency

400 Worcester Road

Framingham, MA 01702-5399

Test, Research and Training

Reactor Newsletter

P.O. Box 118300

University of Florida

Gainesville, FL 32611-8300

Ms. Sarah M. Don, Reactor Superintendent

Massachusetts Institute of Technology

Nuclear Reactor Laboratory

Research Reactor

138 Albany Street, MS NW12-116B

Cambridge, MA 02139

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

Docket No.50-020

License No. R-37

Report No. 50-020/2017-201

Licensee: Massachusetts Institute of Technology

Facility: Nuclear Reactor Laboratory

Location: Cambridge, Massachusetts

Dates: April 25-27, 2017

Inspector: Johnny Eads

Approved by: Anthony J. Mendiola, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Enclosure

EXECUTIVE SUMMARY

Massachusetts Institute of Technology

Nuclear Reactor Laboratory

NRC Inspection Report No. 50-020/2017-201

The primary focus of this routine, announced inspection was the onsite review of selected

aspects of the Massachusetts Institute of Technology (the licensees) Class I six megawatt

research reactor safety program including: (1) organization and staffing, (2) reactor operations,

(3) operator requalification, (4) maintenance and surveillance, (5) fuel handling, (6) experiments,

(7) procedures, and (8) emergency preparedness since the last U.S. Nuclear Regulatory

Commission (NRC) inspection of these areas. The licensees program was acceptably directed

toward the protection of public health and safety and in compliance with NRC requirements.

Organization and staffing

  • Organizational structure and staffing were consistent with technical specification (TS)

requirements.

Reactor Operations

  • Reactor operations were conducted in accordance with procedure and the appropriate logs

were being maintained.

Operator Requalification

  • Operator requalification was conducted as required by the Requalification Program and the

program was being maintained up-to-date.

  • Operators were receiving biennial medical examinations as required.

Maintenance and Surveillance

  • The system for tracking and completing maintenance items and surveillance checks and

calibrations was adequate and was being maintained as required.

  • Maintenance and surveillance records, performance, and reviews satisfied TS and

procedure requirements.

Fuel Handling

  • Fuel was being controlled as required and fuel movements were conducted in accordance

with TS and procedural requirements.

Experiments

  • The program for reviewing and conducting experiments satisfied procedural and TS

requirements.

-2-

Procedures

  • The procedure review, revision, control, and implementation program satisfied TS

requirements.

Emergency Preparedness

Plan (E-Plan).

  • Emergency response equipment was being maintained and inventoried as required.
  • Emergency drills were being conducted annually as required by the E-Plan.

support organizations was being completed as required.

REPORT DETAILS

Summary of Facility Status

The Massachusetts Institute of Technology (MIT or the licensee) Nuclear Reactor Laboratory

(NRL) six megawatt research and test reactor continued to be operated 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day, 7 days

a week in support of educational experiments, research and service irradiations, and reactor

operator training. During the inspection, the reactor was shutdown for maintenance.

1. Organization and Staffing

a. Inspection Scope (Inspection Procedure (IP) 69006)

The inspector reviewed the Massachusetts Institute of Technology Reactor

(designated as MITR-II) organization and staffing to ensure that the requirements

of technical specification (TS) 7.1, implemented through Renewed Facility

Operating License R-37, Amendment 40 issued August 13, 2015, were being

met regarding the following:

  • Management responsibilities
  • Qualifications of facility operations personnel
  • MIT NRL Organization Chart, dated April 12, 2017
  • Reactor Digital Logbook covering the period from March 2016 to present
  • Staffing requirements for reactor operation stated in TS 7.1.3
  • MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute

of Technology Annual Report to the U.S. Nuclear Regulatory Commission for

the Period January 1, 2016, to December 31, 2016.

b. Observations and Findings

The inspector noted that the Director of Reactor Operations continued to report

to the Director of the MIT NRL, who in turn reported to the President of the

university through the Vice President for Research. This organization was

consistent with that specified in the TS. The organizational structure and the

responsibilities of the reactor staff had not changed since the last inspection.

Staffing levels remained consistent with those noted during the last inspection of

the facility. The current reactor operations organization consisted of the Director

of Reactor Operations, the Deputy Director of Reactor Operations, the Assistant

Director of Operations, the Superintendent of Operations, the Training

Coordinator, a Quality Assurance Supervisor, and various reactor supervisors,

and reactor operators (ROs). The Deputy Director of Reactor Operations, the

Assistant Director of Reactor Operations, the Superintendent of Operations, the

Quality Assurance Supervisor, the Training Coordinator, and the majority of the

reactor supervisors were licensed senior reactor operators (SROs). In addition to

the operations staff, there were various support groups, including a research

staff, a research development group, a reactor engineering staff, maintenance

personnel, and a reactor radiation protection group. Through a review of reactor

-2-

operations logs for the period from March 2016 through the present, and through

interviews with operations personnel, the inspector determined that the licensee

normally operated 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day with three crews and no shift rotation. Each

operating crew was staffed with various personnel (with at least two licensed

operators on duty at the MITR-II per shift). Operations shifts were scheduled for

a period of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The review of the reactor (console) logbooks and associated

records confirmed that shift staffing during reactor operations met the minimum

requirements for duty and on-call personnel specified in TS 7.1.3.

c. Conclusion

The licensees organization and staffing were in compliance with the

requirements specified in TS 7.1.

2. Reactor Operations

a. Inspection Scope (IP 69006)

To verify that the licensee was conducting reactor operations in accordance with

TS Sections 2 and 3 and procedural requirements, the inspector reviewed

selected portions of the following:

  • Reactor Digital Logbook covering the period from March 2016 to present
  • MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute

of Technology Annual Report to the U.S. Nuclear Regulatory Commission for

the Period January 1, 2016, to December 31, 2016.

b. Observations and Findings

(1) Reactor Operation

The inspector observed facility activities on various occasions during the

week including routine reactor operations and updating the console logs

while the reactor was shutdown for maintenance. Written procedures and

checklists were used for each activity as required. It was noted that the

reactor operators followed the appropriate procedures, were

knowledgeable of the required actions, and professional in the conduct of

their duties.

(2) Staff Communication

During the inspection, the inspector observed reactor operator turnover

activities during the shift. The status of the reactor and the facility was

discussed on each occasion as required. The oncoming personnel were

briefed on the upcoming activities and scheduled events before assuming

the operations duty. Through direct observation and records review, the

inspector verified that the content of turnover briefings was appropriate

-3-

and that shift activities and plant conditions were discussed in sufficient

detail.

c. Conclusion

MITR-II reactor operations, as well as turnovers and operator cognizance of

facility conditions during routine operations, were acceptable.

3. Operator Requalification

a. Inspection Scope (IP 69003)

To verify that the licensee was complying with the requirements of Title 10 of the

Code of Federal Regulations (10 CFR) Part 55 and TS 7.2.3.3 (b) and

conforming to Chapter 12, Sections 12.1 and 12.10 of the facility safety analysis

report, the inspector reviewed selected aspects of the following:

  • Current status of operator licenses
  • Reactor Digital Logbook covering the period from March 2016 to present
  • Results of the annual written examinations completed in 2016
  • Medical examination records for selected operators for the past 2 years
  • Procedure Manual (PM) 1.16, Requalification and Qualification, latest

revision dated February 20, 2013.

b. Observations and Findings

There were 21 individuals licensed to operate the reactor at MIT. Of those

personnel, 15 were qualified SROs and 6 were ROs. A review of various

Requalification Program records indicated that the program was maintained

up-to-date and that SRO and RO licenses were current. MITR-II operator files

and reactor logs also showed that all operators maintained active duty status with

the exception of one SRO who was designated as inactive by the facility. A

review of the MITR Safety Committee (MITRSC) meeting minutes and

independent audit results indicated that the program was being audited annually

as required by TS 7.2.3.3.(b).

A review of the pertinent logs and records also showed that training was being

conducted in accordance with the licensees requalification and training program.

A series of lectures were given to operators during the 2 year training and

requalification cycle. Information regarding facility changes, procedure changes,

and other relevant information was routinely routed to all licensed operators for

their review. The inspector verified that the required reactor operations, reactivity

manipulations, other operations activities, and reactor supervisor activities were

being completed and the appropriate records were being maintained. The

inspector also noted that all operators were receiving biennial medical

examinations within the time frame allowed as required by the program.

-4-

c. Conclusion

Operator requalification was up-to-date and being completed as required by the

MITR-II Operator Requalification Program. Operators were receiving biennial

medical examinations as required.

4. Maintenance and Surveillance

a. Inspection Scope (IPs 69006 and 69010)

To verify that the licensee was meeting the surveillance requirements specified in

TS Section 4 and that maintenance was being conducted, the inspector reviewed

selected aspects of the following:

  • MITR-II Job Workbook
  • MITR-II Daily Operations Schedule
  • Reactor Digital Logbook covering the period from March 2016 to present
  • MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute

of Technology Annual Report to the U.S. Nuclear Regulatory Commission for

the Period January 1, 2016, to December 31, 2016.

b. Observations and Findings

(1) Maintenance

The inspector reviewed the system that the licensee had developed to

track and complete maintenance activities. The system was designed to

ensure that all maintenance activities were planned and completed as

scheduled, that post maintenance testing was conducted, and that the

entire process was documented appropriately. The licensee used a

locally developed system called the Test and Calibration Tracker which

listed nearly all the tests, checks, and calibrations that were due on a

monthly basis, as well as MITR-II Systems, Tests, and Calibrations

notebooks to document completion of the various periodic maintenance

and surveillance activities. The inspector noted that all such tasks were

tracked through this system. The program appeared to be effective.

(2) Surveillance

Various periodic surveillance verifications and calibration records of

equipment, including the testing of various reactor systems,

instrumentation, and auxiliary systems were reviewed by the inspector.

TS surveillance items were completed on schedule as required by TS and

in accordance with licensee procedures. The results of selected tests,

checks, and calibrations reviewed by the inspector were noted to be

within the TS and procedurally prescribed parameters.

-5-

c. Conclusion

The system for tracking and completing maintenance items and surveillance

checks and calibrations was adequate and was being maintained as required.

Maintenance and surveillance records, performance, and reviews satisfied TS

and procedure requirements.

5. Fuel Handling

a. Inspection Scope (IP 69009)

To ensure that the licensee was following the requirements of TSs 3.1.4, 3.1.6,

4.1.5, and 5.4, the inspector reviewed selected aspects of the following:

  • Reactor Digital Logbook covering the period from March 2016 to present
  • Approved packets for core configurations completed in 2016 and 2017,

including:

Fuel Loading Permission Form (form revision dated

February 20, 2013), completed for fuel element transfers in 2016

and 2017 to date

b. Observations and Findings

The inspector reviewed the fuel movement process and verified that fuel moves

were conducted according to established procedure and documented on specific

fuel movement sheets developed by the Reactor Engineer. The inspector

reviewed selected fuel movement sheets for 2016 and to date in 2017. They had

been developed and used for each specific core refueling as required.

c. Conclusion

Fuel was being controlled as required and fuel movements were performed in

accordance with approved procedures and TS requirements.

6. Experiments

a. Inspection Scope (IP 69005)

To verify compliance with the licensees procedures, TSs 6, 7.5, and

10 CFR 50.59 the inspector reviewed the following:

  • Reactor Digital Logbook covering the period from March 2016 to present
  • Experiment Review Process documented in PM 1.10, Experiment Review

and Approval, latest revision dated February 20, 2013.

b. Observations and Findings

The inspector reviewed the experimental review and approval process described

in PM 1.10. The inspector reviewed selected safety review forms and irradiation

-6-

request forms for experiments that were currently active. The experimental

facilities and/or equipment had been evaluated in accordance with TS

requirements and the associated data sheets indicated that the experiments

would be within the specified limits. The analysis for each had been performed

and the reviews and approvals completed. The appropriate reviews and

approvals had also been completed for the samples and/or materials to be

irradiated and the experiments were conducted under the cognizance of the

reactor supervisor and in accordance with the specified requirements.

c. Conclusion

Conduct and control of experiments met the requirements of the TS and the

applicable facility procedures.

7. Procedures

a. Inspection Scope (IP 69008)

To verify that the licensee was meeting the requirements of TS 7.4, the

inspectors reviewed selected aspects of the following:

PM 1.4, Review and Approval of Plans, Procedures and Facility Equipment

and Changes Thereto, which included:

- PM 1.4.1, Plan, Procedure, and Equipment Change

Classification, latest revision dated February 20, 2013

- PM 1.4.2, Class C Review and Approval, latest revision dated

February 20, 2013

- PM 1.4.3, Class B Review and Approval, latest revision dated

February 20, 2013

- PM 1.4.4, Class A Review and Approval, latest revision dated

February 20, 2013

- PM 1.4.5, Safety Review Form, latest revision dated

February 20, 2013

- PM 1.4.6, Procedure Manuals, latest revision dated

February 20, 2013

PM 1.5, Procedure Adherence and Temporary Change Method, latest

revision dated February 20, 2013

b. Observations and Findings

The inspector noted that procedures had been developed for reactor operations

and safety as required by the TS 7.4. The licensees procedures were found to

be acceptable for the current facility status and staffing level. The inspector

noted that the administrative procedure specified the responsibilities of the

various positions and for the MITRSC.

-7-

Operations procedures were typically reviewed by operators and support

personnel prior to being used/implemented and were revised as needed. The

inspector noted that abnormal and emergency procedures were reviewed

annually by all licensed operators as required and revised when needed. Major

procedure revisions were reviewed and approved by the Director of Reactor

Operations and submitted to the MITRSC for review. All procedure changes

were routinely routed to all operators for review as well.

It was also noted that management and supervisory oversight was focused on

proper implementation and adherence to procedures. Through observation of

various activities in progress during the inspection, the inspector noted that

adherence to procedures was adequate.

c. Conclusion

Procedures were properly prepared and implemented in compliance with license

requirements.

8. Emergency Preparedness

a. Inspection Scope (IP 69011)

The inspector reviewed selected aspects to verify compliance with TS 7.2.3.d

and the licensees Emergency Plan and associated procedures of the following:

  • Training records for MITR Support Personnel
  • Review and Critique of the 2016 Emergency Exercise conducted on

August 16, 2016

  • Review and Critique of the 2016 actual medical emergencies which occurred

on February 13, 2016 and July 6, 2016

June 20, 2013

  • PM 4.4.4, Emergency Operating Procedures

b. Observations and Findings

The inspector reviewed the Emergency Plan (EP) and implementing procedures

in use at the reactor and verified that the procedures were reviewed annually by

all licensed operators in accordance with the Operator Requalification Program.

Through records reviews and interviews with facility emergency personnel (i.e.,

licensed operators or emergency responders), the inspector determined that they

were knowledgeable of the proper actions to take in case of an emergency.

Training for staff members had been conducted annually as required and

documented acceptably.

Emergency training for MIT Police Department personnel was required to be

conducted annually by EP Section 4.10.1.1. The inspector reviewed the training

records and noted that the most recent training had been completed as required.

-8-

The inspector verified that letters of agreement with various emergency support

organizations were on file and being maintained.

Communications capabilities with support groups were acceptable and were

verified annually through a communications check with the various organizations.

Emergency call lists had been revised and updated as needed and were

available in various areas of the facility, including in controlled copies of the

Emergency Procedures Manuals. The inspector also verified that emergency

equipment was being inventoried quarterly as required.

The inspector verified compliance with the EP requirement for annual emergency

plan drills. The licensee met this requirement by conducting radiological

emergency and medical emergency drills each year or by taking credit for an

actual emergency. Following each drill, a critique was conducted to identify

areas of strength and weakness. Drills and critiques were documented in writing

as referenced above. The drills appeared to be challenging and provided a good

indication of each organizations responsiveness and capabilities.

c. Conclusion

The licensee was maintaining acceptable emergency preparedness in

accordance with TS and E-Plan requirements.

9. Exit Interview

The inspection scope and results were summarized on April 27, 2017, with members of

licensee management. The inspector described the areas inspected and discussed the

preliminary inspection findings. The licensee acknowledged the results of the inspection

and did not identify as proprietary any of the material provided to or reviewed during the

inspection.

PARTIAL LIST OF PERSONS CONTACTED

Licensee Personnel:

J. Bernard Senior Advisor, Research Staff

S. Don Superintendent Operations

J. Foster Deputy Director of Reactor Operations

E. Lau Assistant Director of Reactor Operations

W. McCarthy Reactor Radiation Protection Officer and Deputy Director, MIT

Environment, Health, and Safety Office

A. Queirolo Director of Reactor Operations

S. Tucker Quality Assurance Supervisor

INSPECTION PROCEDURES USED

IP 69003 Class 1 Research and Test Reactor Operator Licenses, Requalification, and

Medical Examinations

IP 69005 Class 1 Research and Test Reactor Experiments

IP 69006 Class 1 Research and Test Reactors Organization and Operations and

Maintenance Activities

IP 69008 Class 1 Procedures

IP 69009 Class 1 Research and Test Reactor Fuel Movement

IP 69010 Class 1 Research and Test Reactor Surveillance

IP 69011 Class 1 Research and Test Reactor Emergency Preparedness

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened:

None

Closed:

None

LIST OF ACRONYMS USED

CFR Code of Federal Regulations

EP Emergency Plan

IP Inspection Procedure

MIT Massachusetts Institute of Technology

MITR Massachusetts Institute of Technology Reactor

MITRSC Massachusetts Institute of Technology Reactor Safety Committee

NRC U.S. Nuclear Regulatory Commission

NRL Nuclear Reactor Laboratory

PM Procedure Manual

RO Reactor Operator

SRO Senior Reactor Operator

TS Technical Specification