NRC LAR Extension Supplemental Letter 2020-05-27
ML20149K414
Person / Time
Site: MIT Nuclear Research Reactor
Issue date: 05/27/2020
From: Lau E
Massachusetts Institute of Technology (MIT)
To: Patrick Boyle
Document Control Desk, Office of Nuclear Reactor Regulation
Boyle P
References
EPID L-2016-LLA-0003
Download: ML20149K414 (1)


Text

MIT NUCLEAR REACTOR LABORATORY AN MIT INTERDEPARTMENTAL CENTER Edward Lau Mail Stop: NW12-122 Phone: 617 253-4211 Assistant Director 138 Albany Street Fax: 617 324-0042 Reactor Operations Cambridge, MA 02139 Email: eslau@mit.edu 27 May 2020 U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attn.: Document Control Desk

Subject:

Amendment No. 42 to Renewed Facility Operating License No. R-37 for the Massachusetts Institute of Technology (MIT) Research Reactor regarding the Nuclear Safety System Digital Upgrade (EPDI No. L-2016-LLA-0003)

This letter supplements a similar letter dated 21 April 2020 which described the need for a time extension for implementation of the Nuclear Safety System digital upgrade, as a result of facility lockdowns for the ongoing Coronavirus Disease 2019 (COVOD-19) public health emergency (PHE). On 4 December 2019, the U.S. Nuclear Regulatory Commission (NRC) issued Amendment No. 42 to Renewed Facility Operating License No. R-37 for the Massachusetts Institute of Technology Research Reactor (MITR), with an implementation deadline of 180 days for this upgrade. With the letter dated 21 April 2020, MIT requests approval from NRC to be authorized to implement License Amendment No. 42 within 180 days after the MITR can resume normal staffing levels due to relaxation of the COVID-19 PHE restrictions.

Again, MIT is committed to this upgrade, and will be making the license amendment transition a top priority once normal staffing can be resumed.

Sincerely, Edward S. Lau, NE Assistant Director of Reactor Operations MIT Research Reactor I declare under penalty of perjury that the foregoing is true and correct.

Executed on 5/27/2020 __________________________________

Date Signature cc: USNRC - Senior Project Manager Research and Test Reactors Licensing Branch Division of Licensing Projects Office of Nuclear Reactor Regulation USNRC - Senior Reactor Inspector Research and Test Reactors Oversight Branch Division of Licensing Projects Office of Nuclear Reactor Regulation