ML12216A381: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov] | ||
Sent: Monday, July 30, 2012 8:19 AM To: Poole, Justin; Arent, Gordon; Bryan, Robert H Jr Cc: Boyd, Desiree L; Templeton, Pamela J | Sent: Monday, July 30, 2012 8:19 AM To: Poole, Justin; Arent, Gordon; Bryan, Robert H Jr Cc: Boyd, Desiree L; Templeton, Pamela J | ||
==Subject:== | ==Subject:== | ||
2012-07 | 2012-07 WBN Project Plan - Unit 2.pdf Attachments: 2012-07 WBN Project Plan - Unit 2.pdf Please see attached for todays 9:15 phone call. | ||
2012-07 | Thank you, | ||
~*~*~*~*~*~*~*~*~*~*~ | |||
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1 | |||
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 719 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF3023D61A) | |||
==Subject:== | |||
2012-07 WBN Project Plan - Unit 2.pdf Sent Date: 7/30/2012 8:19:01 AM Received Date: 7/30/2012 8:19:06 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients: | |||
"Boyd, Desiree L" <dlboyd@tva.gov> | |||
Tracking Status: None "Templeton, Pamela J" <pjtempleton@tva.gov> | |||
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov> | |||
Tracking Status: None "Arent, Gordon" <garent@tva.gov> | |||
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov> | |||
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 245 7/30/2012 8:19:06 AM 2012-07 WBN Project Plan - Unit 2.pdf 205038 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date: | |||
Recipients Received: | |||
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 2 of 38 I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications | |||
: 1. Common Service Station Transformer (CSST) A & B Credit Shea October 12, 2012 | |||
: 3. U2 Hydrology FSAR & TS Update Stockton August 26, 2012 SSER Open Item 32: | |||
: 4. Hilmes January 13, 2013 Revise Diesel Generator Frequency Allowable Value. [Commitment 113676066] | |||
SSER Appendix HH Open Items (requiring submittal) | |||
SSER Open Item 1: | |||
Following completion of cable pulls, submit letter to NRC either: | |||
: 1. | |||
* Affirming no power assisted cable pulls were made, or Hilmes TBD | |||
* Documenting any power assisted cable pulls. | |||
[Commitment 113676047] | |||
SSER Open Items 5 & 8: | |||
: 2. Westinghouse / Koontz July 30, 2012 Provide updated core map. [Commitment 113676148] | |||
SSER Open Item 13: | |||
: 3. Submit an ASME Section XI Inservice Test Program for the first ten year interval McDonald / Crouch March 2014 six months before receiving an Operating License. [Commitment NCO080008033: | |||
Item 017 of Enclosure 2 of letter T90 080128 001] | |||
SOURCE: POD UPDATES, COMMITMENTS | |||
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 3 of 38 Item No. Description Resp. Person Due Date SSER Open Item 25: | |||
: 4. Submit documentation of liability insurance coverage pursuant to 10 CFR 140.11(a)(4). Arent June 2014 | |||
[Commitment 113676162] | |||
SSER Open Item 37: | |||
: 5. Submit changes to the Emergency Plan (REP) prior to fuel load. Detchemendy June 2014 | |||
[Commitment 111032952] | |||
SSER Open Item 41: | |||
: 6. Update Plant design displays & dose assessment models to provide two unit capability. Hilmes / Koontz December 2013 | |||
[Commitment 111033086] | |||
SSER Open Item 43: | |||
: 7. Submit Emergency Plan implementing procedures no less than 180 days before schedule Detchemendy TBD issuance of Operating License. [Commitment ____________] | |||
SSER Open Item 61: | |||
: 8. Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a Koontz October 26, 2012 License Condition - tracking PWROG activity to update code. [Commitment 113676152] | |||
SSER Open Item 70: | |||
: 9. McDonald / Crouch September 28, 2012 Submit Pre-Service Inspection program update. [Commitment 113676155] | |||
SSER Open Item 77: | |||
: 10. Provide Electronic Filter Test Results for General Atomic High Range Rad Monitor. Hilmes August 31, 2012 | |||
[Commitment 113676079] | |||
SSER Open Item 79: | |||
Perform an EMI survey of the containment high range radiation monitors after they are | |||
: 11. Hilmes March 4, 2014 installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753] | |||
SOURCE: POD UPDATES, COMMITMENTS | |||
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 4 of 38 Item No. Description Resp. Person Due Date SSER Open Item 83: | |||
: 12. Provide Letter verifying completion of data storm test on DCS. Hilmes January 2015 | |||
[Commitment 113676093] | |||
SSER Open Item 115: | |||
: 13. Incorporate U1 dose reduction plant changes that 2010 letter said were being done on Unit Arent TBD 2 into FSAR Chapter 12. Engineering to identify change packages showing what is done/planned. | |||
SSER Open Item 117: | |||
: 14. Provide calculational basis for access to vital areas - mission dose and update FSAR. Koontz / Arent August 26, 2012 (Amendment 109) [Commitment 112046729] | |||
SSER Open Item 132: | |||
x Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed. [Commitment 113111704] | |||
: 15. Arent / Wallace May 24, 2013 x Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made. [Commitment 113111704] | |||
SSER Open Item 134: | |||
: 16. Provide resolution of dam stability analysis for Cherokee and Douglas Dams finite element Ray August 31, 2012 analysis. | |||
SSER Open Item 138: | |||
(Amendment 109) | |||
: 17. Bryan August 26, 2012 NRC to verify that the ODCM average annual X/Q & D/Q values have been updated to match the FSAR. [Commitment 113676172] | |||
SSER Open Item 139: | |||
: 18. Include cost benefit analysis in next update to FSAR. (Amend 109) Bryan August 26, 2012 | |||
[Commitment 113676181] | |||
SOURCE: POD UPDATES, COMMITMENTS | |||
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 5 of 38 Item No. Description Resp. Person Due Date Submit a Technical Specification and Bases change package to TVA Licensing to change Table 3.3.3-1, Line item 6 (Reactor Vessel Water Level) to remove the reference to note (g) and bases to show RVLIS as a Type A variable. | |||
: 19. Bryan August 26, 2012 Need calculation WBNO4SG4047 revised PER 488815 [Commitment 113307292] | |||
Submit a FSAR Change Package to TVA Licensing to Amendment 108, Table 7.5-2, Regulatory Guide 1.97 Post Accident Monitoring Variables Lists, will be updated to show RVLIS as a Type A variable. | |||
: 20. Stockton August 26, 2012 Need calculation WBNO4SG4047 revised. | |||
PER 488815 [Commitment 113307350] | |||
SOURCE: POD UPDATES, COMMITMENTS | |||
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 6 of 38 Item No. Description Resp. Person Due Date Other Submittals | |||
WBN UNIT 2 PROJECT PLAN: | : 1. As-Constructed Fire Protection Report [Commitment 113461862] Hilmes July 2014 | ||
: 1. | : 2. U2 FSAR With As-Constructed Figures [Commitment 112068531] Arent July 2014 Prior to fuel load, a final report will be submitted following certain validation activities as | ||
: | : 3. Koontz / Enis July 2014 described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893] | ||
TVA will provide the NRC staff an updated [security] classification scheme that reflects | |||
: | : 4. these changes for WBN Unit 2. [Commitment 111033038: RAI Response 3.r of Reynolds May 2014 Enclosure 2. of Letter T02 100427 001] | ||
: 5. Submit a merged U2 FSAR / U1 UFSAR [Commitment 111360889] Licensing April 2016 | |||
: 6. 10 CFR Part 70 License Extension Bryan August 26, 2012 | |||
: 7. Two Unit ODCM Woods / Shea September 14, 2012 | |||
: 8. As-Constructed PRA Guey / Koontz October 2014 | |||
: | : 9. TMI Commitment Review Letter Licensing January 2014 | ||
: 5. | : 10. Letter to terminate Part 30/40 License after receipt of Part 50 License Licensing January 2015 | ||
: 6. | : 11. ASME Section III N-3 Report Crouch September 2014 | ||
: 7. | : 12. Letter to NRC for notification of Vital Area Boundary Restoration Licensing May 2014 | ||
: 13. Unit 2 Completion Letter Licensing December 2014 SOURCE: POD UPDATES, COMMITMENTS | |||
: 8. | |||
: 9. | |||
: 10. | |||
: | |||
: | |||
: | |||
WBN UNIT 2 PROJECT PLAN: | WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 7 of 38 Item No. Description Resp. Person Due Date Other Submittals | ||
: 14. Fire Protection Report Hilmes / Wiggal September 13, 2012 | |||
: 15. PAM variable Calculation for EOP reviews. Partch December 31, 2012 | |||
: 16. Regulatory Framework Update [for status as of 07/31] Elton August 15, 2012 Regional Submittals 1. | |||
SOURCE: POD UPDATES, COMMITMENTS}} | |||
: 14. Fire Protection Report Hilmes / Wiggal September 13, 2012 | |||
: 15. PAM variable Calculation for EOP reviews. Partch December 31, 2012 | |||
: 16. Regulatory Framework Update [for status as of 07/31] Elton August 15, 2012 Regional Submittals 1.}} |
Revision as of 00:09, 12 November 2019
ML12216A381 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 07/30/2012 |
From: | - No Known Affiliation |
To: | Division of Operating Reactor Licensing |
References | |
Download: ML12216A381 (8) | |
Text
WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]
Sent: Monday, July 30, 2012 8:19 AM To: Poole, Justin; Arent, Gordon; Bryan, Robert H Jr Cc: Boyd, Desiree L; Templeton, Pamela J
Subject:
2012-07 WBN Project Plan - Unit 2.pdf Attachments: 2012-07 WBN Project Plan - Unit 2.pdf Please see attached for todays 9:15 phone call.
Thank you,
~*~*~*~*~*~*~*~*~*~*~
Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1
Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 719 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF3023D61A)
Subject:
2012-07 WBN Project Plan - Unit 2.pdf Sent Date: 7/30/2012 8:19:01 AM Received Date: 7/30/2012 8:19:06 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:
"Boyd, Desiree L" <dlboyd@tva.gov>
Tracking Status: None "Templeton, Pamela J" <pjtempleton@tva.gov>
Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>
Tracking Status: None "Arent, Gordon" <garent@tva.gov>
Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov>
Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 245 7/30/2012 8:19:06 AM 2012-07 WBN Project Plan - Unit 2.pdf 205038 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:
Recipients Received:
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 2 of 38 I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications
- 1. Common Service Station Transformer (CSST) A & B Credit Shea October 12, 2012
- 3. U2 Hydrology FSAR & TS Update Stockton August 26, 2012 SSER Open Item 32:
- 4. Hilmes January 13, 2013 Revise Diesel Generator Frequency Allowable Value. [Commitment 113676066]
SSER Appendix HH Open Items (requiring submittal)
SSER Open Item 1:
Following completion of cable pulls, submit letter to NRC either:
- 1.
- Affirming no power assisted cable pulls were made, or Hilmes TBD
- Documenting any power assisted cable pulls.
[Commitment 113676047]
SSER Open Items 5 & 8:
- 2. Westinghouse / Koontz July 30, 2012 Provide updated core map. [Commitment 113676148]
SSER Open Item 13:
- 3. Submit an ASME Section XI Inservice Test Program for the first ten year interval McDonald / Crouch March 2014 six months before receiving an Operating License. [Commitment NCO080008033:
Item 017 of Enclosure 2 of letter T90 080128 001]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 3 of 38 Item No. Description Resp. Person Due Date SSER Open Item 25:
- 4. Submit documentation of liability insurance coverage pursuant to 10 CFR 140.11(a)(4). Arent June 2014
[Commitment 113676162]
SSER Open Item 37:
- 5. Submit changes to the Emergency Plan (REP) prior to fuel load. Detchemendy June 2014
[Commitment 111032952]
SSER Open Item 41:
- 6. Update Plant design displays & dose assessment models to provide two unit capability. Hilmes / Koontz December 2013
[Commitment 111033086]
SSER Open Item 43:
- 7. Submit Emergency Plan implementing procedures no less than 180 days before schedule Detchemendy TBD issuance of Operating License. [Commitment ____________]
SSER Open Item 61:
- 8. Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a Koontz October 26, 2012 License Condition - tracking PWROG activity to update code. [Commitment 113676152]
SSER Open Item 70:
- 9. McDonald / Crouch September 28, 2012 Submit Pre-Service Inspection program update. [Commitment 113676155]
SSER Open Item 77:
- 10. Provide Electronic Filter Test Results for General Atomic High Range Rad Monitor. Hilmes August 31, 2012
[Commitment 113676079]
SSER Open Item 79:
Perform an EMI survey of the containment high range radiation monitors after they are
- 11. Hilmes March 4, 2014 installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 4 of 38 Item No. Description Resp. Person Due Date SSER Open Item 83:
- 12. Provide Letter verifying completion of data storm test on DCS. Hilmes January 2015
[Commitment 113676093]
SSER Open Item 115:
- 13. Incorporate U1 dose reduction plant changes that 2010 letter said were being done on Unit Arent TBD 2 into FSAR Chapter 12. Engineering to identify change packages showing what is done/planned.
SSER Open Item 117:
- 14. Provide calculational basis for access to vital areas - mission dose and update FSAR. Koontz / Arent August 26, 2012 (Amendment 109) [Commitment 112046729]
SSER Open Item 132:
x Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed. [Commitment 113111704]
- 15. Arent / Wallace May 24, 2013 x Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made. [Commitment 113111704]
SSER Open Item 134:
- 16. Provide resolution of dam stability analysis for Cherokee and Douglas Dams finite element Ray August 31, 2012 analysis.
SSER Open Item 138:
(Amendment 109)
- 17. Bryan August 26, 2012 NRC to verify that the ODCM average annual X/Q & D/Q values have been updated to match the FSAR. [Commitment 113676172]
SSER Open Item 139:
- 18. Include cost benefit analysis in next update to FSAR. (Amend 109) Bryan August 26, 2012
[Commitment 113676181]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 5 of 38 Item No. Description Resp. Person Due Date Submit a Technical Specification and Bases change package to TVA Licensing to change Table 3.3.3-1, Line item 6 (Reactor Vessel Water Level) to remove the reference to note (g) and bases to show RVLIS as a Type A variable.
- 19. Bryan August 26, 2012 Need calculation WBNO4SG4047 revised PER 488815 [Commitment 113307292]
Submit a FSAR Change Package to TVA Licensing to Amendment 108, Table 7.5-2, Regulatory Guide 1.97 Post Accident Monitoring Variables Lists, will be updated to show RVLIS as a Type A variable.
- 20. Stockton August 26, 2012 Need calculation WBNO4SG4047 revised.
PER 488815 [Commitment 113307350]
SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 6 of 38 Item No. Description Resp. Person Due Date Other Submittals
- 1. As-Constructed Fire Protection Report [Commitment 113461862] Hilmes July 2014
- 2. U2 FSAR With As-Constructed Figures [Commitment 112068531] Arent July 2014 Prior to fuel load, a final report will be submitted following certain validation activities as
- 3. Koontz / Enis July 2014 described in the IPEEE Design Report (Enclosure 1). [Commitment 111027893]
TVA will provide the NRC staff an updated [security] classification scheme that reflects
- 4. these changes for WBN Unit 2. [Commitment 111033038: RAI Response 3.r of Reynolds May 2014 Enclosure 2. of Letter T02 100427 001]
- 6. 10 CFR Part 70 License Extension Bryan August 26, 2012
- 7. Two Unit ODCM Woods / Shea September 14, 2012
- 8. As-Constructed PRA Guey / Koontz October 2014
- 9. TMI Commitment Review Letter Licensing January 2014
- 10. Letter to terminate Part 30/40 License after receipt of Part 50 License Licensing January 2015
- 11. ASME Section III N-3 Report Crouch September 2014
- 12. Letter to NRC for notification of Vital Area Boundary Restoration Licensing May 2014
- 13. Unit 2 Completion Letter Licensing December 2014 SOURCE: POD UPDATES, COMMITMENTS
WBN UNIT 2 PROJECT PLAN: 07/30/2012 Page 7 of 38 Item No. Description Resp. Person Due Date Other Submittals
- 14. Fire Protection Report Hilmes / Wiggal September 13, 2012
- 16. Regulatory Framework Update [for status as of 07/31] Elton August 15, 2012 Regional Submittals 1.
SOURCE: POD UPDATES, COMMITMENTS