Letter Sequence Other |
---|
|
|
MONTHYEARML1025101712010-08-27027 August 2010 Response to Request for Additional Information Relief Request No. 47 Project stage: Response to RAI ML1026700802010-10-14014 October 2010 Relief Request No. 47, from Certain ASME Code Requirements for Reactor Vessel Nozzle to Vessel Welds for Second 10-Year Inservice Inspection Interval Project stage: Other 2010-10-14
[Table View] |
|
---|
Category:Code Relief or Alternative
MONTHYEARML24297A6212024-10-22022 October 2024 Request for Additional Information Relief Request (RR) No. 72: Re-Submittal of RR-39/ASME Code X1 IWC-3420, IWA-3300 ML22124A2412022-05-12012 May 2022 Relief Request 67 for an Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML22049A0572022-02-23023 February 2022 Relief Request 69 to Extend Inservice Inspection of Containment Tendon by Four Months Due to the Covid 19 Pandemic (EPID L 2022 Llr 0011 (Covid 19)) ML21278B0912021-10-0606 October 2021 Presubmittal Meeting with Arizona Public Service Company Regarding Relief Request No. 68 for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (EPID L-2021-LRM-0104) (Slides) ML21228A1042021-08-12012 August 2021 RR-67, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (EPID L-2021-LLR-0050) (Email) ML21089A0102021-04-0202 April 2021 Relief Request 66 to Defer Inservice Inspection of Containment Tendon by One Year Due to Covid-19 Pandemic ML20088A5332020-03-27027 March 2020 Relief Request 65 - Unit 2, COVID-19, Request for Relief from Bottom Mounted Instrumentation Nozzles and a Pressurizer Nozzle to Surge Line Weld Overlay Examination ML19263F8752019-09-20020 September 2019 Relief Request VRR-01: Request for Alternative Frequency to Supplemental Indication Requirements of 10 CFR 50.55a(b)C3)(xi) ML19107A3722019-04-19019 April 2019 Relief Request 62 Regarding Proposed Alternative Pressurizer Heater Sleeve Repairs ML19044A6412019-02-19019 February 2019 Relief Request No. 58 for the Third 10-Year Inservice Inspection Interval, Request for Relief from the American Society of Mechanical Engineers for Certain Class 1 and Class 2 Welds ML18285A0292018-10-19019 October 2018 Relief Request 59 for the Deferral of Reactor Vessel Beltline Region Interior Attachment Examinations ML18079A7252018-03-17017 March 2018 Relief Request 58 - Unit 2 Impractical Examinations for the Third 10-Year Inservice Inspection Interval ML18016A1722018-01-12012 January 2018 Relief Request 50 - Request for Alternative to American Society of Mechanical Engineers Section XI Requirements for Pressure Retaining Boundary During System Leakage Tests ML17074A2092017-03-16016 March 2017 Relief Request GRR-01 to ASME Code Case OMN-20 for Third 10-Year Interval Pump and Valve Inservice Testing Program ML16172A0382016-06-23023 June 2016 Relief Request 54 to Approve an Alternative to Flaw Removal for Reactor Coolant Pump 2A Suction Pressure Instrument Nozzle, for the Third 10-Year Inservice Inspection Interval ML15238B6612015-09-15015 September 2015 Relief Request 53, Alternative to ASME Code Section XI Requirements Related to Flaw Removal ML15079A0062015-03-30030 March 2015 Relief Request 52 - Request for Approval of Alternate to Flaw Removal, Flaw Characterization and Successive Examinations, for the Remainder of Its Useful Life ML14093A4072014-04-10010 April 2014 Relief Request 51, Alternative to ASME Code for Flaw Removal, Reactor Vessel Bottom-mounted Instrumentation Nozzle, Third 10-Year ISI Interval ML13091A1772013-04-12012 April 2013 Relief Request 48 - Alternative to ASME Section III, Phased Array Ultrasonic Exam Techniques in Lieu of Radiography for Remainder of Third 10-Year Inservice Inspection Interval ML13085A2542013-04-0404 April 2013 Relief Request 49, Alternative to ASME Code, Section XI, for Reactor Vessel Head Flange Seal Leak Detection Piping, Third 10-Year Inservice Inspection Interval ML12257A1412012-09-18018 September 2012 Request for Relief to Use Subsequent Edition and Addenda of ASME Code, Section XI, for Examination Categories B-L-1, B-M-1, and C-G, for the Third 10-Year Inservice Inspection Interval ML1026700802010-10-14014 October 2010 Relief Request No. 47, from Certain ASME Code Requirements for Reactor Vessel Nozzle to Vessel Welds for Second 10-Year Inservice Inspection Interval ML1025001432010-09-21021 September 2010 Relief Request No. 45 from Certain ASME Code Class 1 Weld and Component Volumetric Exams of Reactor Vessel Outlet Nozzles for Second 10-Year Inservice Inspection Interval ML1021604872010-08-27027 August 2010 Relief Request No. RR-44, Reactor Vessel Weld Visual Examination Interval Extension for Third 10-Year Inservice Inspection Interval ML0921603982009-07-17017 July 2009 Submittal of Relief Request from the American Society of Mechanical Engineers (ASME) Code, Section XI - Relief Request No. 46 ML0917001972009-07-0202 July 2009 Relief Request No. 39, Alternative to Repair Weld Methods, ASME Code, Section XI for Remainder of Operating License ML0916304492009-06-0202 June 2009 Inservice Testing Relief Request for High Pressure Safety Injection Pump Testing - Pump Relief Request PRR-08, Revision 1 ML0905801992009-02-17017 February 2009 Relief Request 41, to Use Appendix I of ASME Code Case N-729-1 ML0830105722008-11-10010 November 2008 Relief Request Nos. 18 and 36, Proposed Alternatives for the Third Interval 10-Year Inservice Inspection Program Interval ML0825905562008-10-0202 October 2008 Relief Request No. 34 for Second 10-Year Inservice Inspection Interval ML0822506752008-07-11011 July 2008 American Society of Mechanical Engineers (ASME) Code, Section XI, Request for Approval of an Alternative Repair Method - Relief Request No. 39 ML0817002812008-06-0606 June 2008 Request for Extension to Complete the Final Confirmatory Analysis and Validation of Containment Sump Strainers Associated with NRC GL-04-002 ML0715600082007-06-21021 June 2007 Relief Request Nos. 36 and 37 Alternatives to Weld Overlay Requirements for Inservice Inspection ML0711400332007-05-16016 May 2007 Supplement to Relief Request No. 34 Request to Extend the Second 10-Year Inservice Inspection Program Interval for Reactor Vessel Weld Examinations ML0629302082006-11-0303 November 2006 Relief Request No. 32, Risk-Informed Inservice Inspection Program ML0626401992006-10-0404 October 2006 Relief Request No. 35 Request to Extend the Second 10-Year Inservice Inspection Program Interval for Reactor Vessel Visual Examinations ML0624905132006-09-20020 September 2006 Relief, Request to Extend the Second 10-Year Inservice Inspection Program Interval ML0623003332006-09-12012 September 2006 Relief Request No. 31, Revision 1, Proposed Alternative Repair for Reactor Coolant System Hot Leg Alloy 600 Small-Bore Nozzles ML0615702092006-05-26026 May 2006 Additional Information to Support the Request to Extend the Second 10-Year, American Society of Mechanical Engineers Section IX, Inservice Inspection Program Interval for Reactor Vessel Weld Examinations - Relief Request No. 34 ML0610803942006-04-0707 April 2006 Relief, Request to Use a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI for Repair/Replacement Activities at PVNGS in Accordance with 10 CFR 50.55a(g)(4)(iv) ML0518901452005-06-28028 June 2005 Revision 1 to 10 CFR 50.55a(a)(3)(i) Request for Alternatives to 10 CFR 50.55a(c) Requirement to Comply with ASME Section III, Subsection NB-1120, Temperature Limits, for a Portion of the Plant Pressurizer That Was Subjected To. ML0512901232005-05-0505 May 2005 Relief, Relief Request No. 31 Proposed Alternative Repair for Reactor Coolant System Hot Leg Alloy 600 Small-Bore Nozzles ML0434201672004-11-24024 November 2004 Relief Request No. 25 for Palo Verde, Unit 2 - Relaxation from First Revised NRC Order EA-03-009 - Additional Analysis Information for Control Element Drive Mechanism (CEDM) Nozzles ML0432706262004-11-19019 November 2004 Palo Verde - Correction to Approval Letter for Relief Request No. 30 ML0328705392003-10-0909 October 2003 Relief, Inservice Inspection Program Surface Examination Requirements, (TACs MC0830, MC0831, and MC0832) ML0321105422003-07-30030 July 2003 Relief Request 23 Alternative to Temper Bead Welding Requirements for Inservice Inspection Program (Tac. MB8973, MB8974 and MB8975) ML0314000512003-05-15015 May 2003 CFR 50.55a Alternative Repair Request for the Second 10-Year Interval of the Inservice Inspection Program: Relief Request 23, Pressurizer Heater Sleeves ML0302902122003-01-27027 January 2003 Relief, Requirements of American Society of Mechanical Engineers (ASME) Boiler & Pressure Vessel Code (Code) Concerning Use of Electrical Discharge Machining (Edm), MB6439, MB6440 & MB6441 ML0302801692003-01-24024 January 2003 Mechanical Nozzle Seal Assembly Type 2 Code Replacement Request for Relief from 10 CFR 50.55a ML0235200682002-12-11011 December 2002 Resubmittal of 10 CFR 50.55a Alternative Repair Request for the Second 10-Year Interval of the Inservice Inspection Program (Relief Request 18) 2024-10-22
[Table view] Category:Letter
MONTHYEARML24295A0362024-10-23023 October 2024 Regulatory Audit Plan in Support of Relief Request No. 71; Resubmittal of Relief Request-30 ML24296B2152024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 03: Alternative Request Allowing Removal of the Lower Acceptance Criteria Threshold from Solenoid-Operated Valves ML24296B2142024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 02: Alternative Request Allowing Normally Closed Valves with a Safety Function to Close to Be Exercise Tested Once Per Refueling Cycle IR 05000528/20244022024-10-22022 October 2024 Security Baseline Inspection Report 05000528/2024402 and 05000529/2024402 and 05000530/2024402 ML24296B2172024-10-18018 October 2024 Submittal of Unit 1 Core Operating Limits Report, Revision 34, Unit 2 Core Operating Limits Report, Revision 26, and Unit 3 Core Operating Limits Report, Revision 3 ML24292A2192024-10-18018 October 2024 Core Operating Limits Report Revision 34, 26 and 33 ML24292A0322024-10-17017 October 2024 Th Refueling Outage Steam Generator Tube Inspection Report ML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator2024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a IR 05000528/20243012024-06-17017 June 2024 NRC Examination Report 05000528/2024301; 05000529/2024301; 05000530/2024301 ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium 05000529/LER-2024-001, Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater2024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24129A1482024-05-0707 May 2024 And Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 2024-09-27
[Table view] Category:Safety Evaluation
MONTHYEARML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable ML22334A0702022-12-15015 December 2022 Issuance of Amendment Nos. 220, 220, and 220, to Revise Technical Specifications to Adopt TSTF-487, Relocate DNB Parameters to the COLR ML22178A0042022-08-11011 August 2022 Issuance of Amendment Nos. 219, 219, and 219, to Revise Technical Specifications to Adopt TSTF-567, Add Containment Sump Ts to Address GSI-191 Issues ML22049A0572022-02-23023 February 2022 Relief Request 69 to Extend Inservice Inspection of Containment Tendon by Four Months Due to the Covid 19 Pandemic (EPID L 2022 Llr 0011 (Covid 19)) ML21347A0032021-12-22022 December 2021 Issuance of Amendment Nos. 217, 217, and 217 Regarding Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML21307A1312021-11-17017 November 2021 the Independent Spent Fuel Storage Installation - Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases (EPID L-2021-LLM-0003) (Letter) ML21225A0932021-08-17017 August 2021 Ng Station, Units 1, 2,& 3 - Issuance of Amendment Nos. 216, 216, and 216 Regarding Revision to Technical Specifications to Adopt TSTF-501, Rev.1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21118B0282021-05-25025 May 2021 Letter/Se Approving Indirect Transfer of Licenses for Units 1, 2, and 3, and the Independent Spent Fuel Storage Installation ML21105A3402021-04-21021 April 2021 Issuance of Amendment Nos. 215, 215, and 215 Revision to Technical Specifications to Adopt TSTF-563, Revision 0 ML21089A0102021-04-0202 April 2021 Relief Request 66 to Defer Inservice Inspection of Containment Tendon by One Year Due to Covid-19 Pandemic ML20350B8032021-02-0808 February 2021 Issuance of Amendment Nos. 214, 214, and 214 to Make Administrative Changes to the Technical Specifications ML20216A5392020-08-0606 August 2020 Relief Request 65 for Inspection of Reactor Pressure Vessel Bottom Mounted Instrument Nozzles and Pressurizer Surge Line Weld Overlay ML20163A0372020-07-31031 July 2020 the Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 213, 213, and 213 to Revise Emergency Plan Staff Augmentation Times ML20114E3252020-04-30030 April 2020 Relief Request 64 for Impractical Examinations for the Third 10-Year Inservice Inspection Interval ML20031C9472020-03-0404 March 2020 Nonproprietary, Issuance of Amendment Nos. 212, 212, and 212 to Revise Technical Specifications to Support the Implementation of Framatome High Thermal Performance Fuel ML20016A4582020-02-10010 February 2020 Issuance of Amendment Nos. 211, 211, 211, to Extend Implementation Date for Amendment Nos. 209, 209, and 209 Associated W/Initiative 4b That Permit the Use of Risk-Informed Completion Times on the TS ML19309F3042019-12-18018 December 2019 Issuance of Amendment Nos. 210, 210, and 210, to Revise Technical Specifications to Adopt Traveler TSTF-529, Revision 4,Clarify Use and Application ML19304C5622019-11-0505 November 2019 Safety Evaluation - Arizona Public Service Company - Palo Verde Nuclear Generating Station - License Amendment Request to Adopt TSTF-529 ML19085A5252019-05-29029 May 2019 Issuance of Amendments Nos. 209, 209, and 209 - Regarding Adoption of Risk Informed Completion Times in Technical Specifications (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001) ML19107A3722019-04-19019 April 2019 Relief Request 62 Regarding Proposed Alternative Pressurizer Heater Sleeve Repairs ML19070A2182019-04-0303 April 2019 Issuance of Amendment Nos. 208, 208, and 208 - Regarding Response Time Testing of Pressure Transmitters ML19044A6412019-02-19019 February 2019 Relief Request No. 58 for the Third 10-Year Inservice Inspection Interval, Request for Relief from the American Society of Mechanical Engineers for Certain Class 1 and Class 2 Welds ML19037A0552019-02-19019 February 2019 Relief Requests 60 & 61 for the Fourth 10-Year Inservice Inspection Interval, Request for Relief from the American Society of Mechanical Engineers Half-Nozzle Repairs (EPID L-2018-LLR-0111 & EPID L-2018-LLR-0112) ML18285A0292018-10-19019 October 2018 Relief Request 59 for the Deferral of Reactor Vessel Beltline Region Interior Attachment Examinations ML18243A2802018-10-10010 October 2018 Issuance of Amendment Nos. 207, 207, and 207 to Adopt 10 CFR 50.69 (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) ML17254A4992017-09-27027 September 2017 Issuance of Amendment Nos. 204, 204, and 204 to Modify the Completion Date for Implementation of Milestone 8 of the Cyber Security Plan ML17188A4122017-07-28028 July 2017 Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - Issuance of Amendment Nos. 203, 203, and 203 to Revise Technical Specifications to Incorporate Updated Criticality Safety Analysis (CAC Nos. MF7138, MF7139, and MF7140) ML17123A4352017-05-16016 May 2017 Issuance of Amendment Nos. 202, 202, and 202 to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation ML17090A1642017-04-27027 April 2017 Issuance of Amendment No. 201, 201, and 201 to Revise Technical Specifications Related to Degraded and Loss of Voltage Relay Modifications ML17074A2092017-03-16016 March 2017 Relief Request GRR-01 to ASME Code Case OMN-20 for Third 10-Year Interval Pump and Valve Inservice Testing Program ML17004A0202017-01-0404 January 2017 Issuance of Amendment No. 200, Revise Technical Specification 3.8.1, AC Sources - Operating, for One-Time Extension of the Diesel Generator Completion Time, Risk-Informed (Emergency Circumstances) ML17004A2092017-01-0303 January 2017 Safety Evaluation Input for Palo Verde Nuclear Generating Station, Unit 3, Llcense Amendment Request for a One-Time Extension of the 3B Emergency Diesel Generator Completion Time ML17003A0832017-01-0303 January 2017 Safety Evaluation Input Regarding Changes to Technical Specifications for One-Time Extension of Completion Time for Emergency Diesel Generator ML17003A3892017-01-0303 January 2017 Safety Evaluation Input Regarding the Palo Verde Nuclear Generating Station Unit 3 Emergency Request to Extend Diesel Generator 3B Completion Time ML16358A4152016-12-23023 December 2016 Technical Specifications for One-Time Extension of Completion Time for Emergency Diesel Generator ML16358A6762016-12-23023 December 2016 Issuance of Amendment No. 199, Request for One-Time Extension of the Diesel Generator Completion Time (Emergency Circumstances) ML16180A1092016-09-0808 September 2016 Issuance of Amendment Nos. 198, 198, and 198, Adopt Emergency Action Level Scheme Pursuant to Nuclear Energy Institute 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. ML16194A3232016-07-22022 July 2016 Review and Approval of Request for Quality Assurance Plan Change Per Nuclear Energy Institute (NEI) 11-04A, Nuclear Generation Quality Assurance Program Description ML16088A2612016-07-20020 July 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16172A0382016-06-23023 June 2016 Relief Request 54 to Approve an Alternative to Flaw Removal for Reactor Coolant Pump 2A Suction Pressure Instrument Nozzle, for the Third 10-Year Inservice Inspection Interval ML16004A0132016-02-19019 February 2016 Issuance of Amendment No. 197, 197, and 197, Adopt Technical Specification Task Force Traveler TSTF-439-A, Revision 2, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML15266A0052015-09-25025 September 2015 Issuance of Amendment No. 196, Revise Technical Specification Surveillance Requirement 3.1.5.3 for Control Element Assembly 88 for the Remainder of Cycle 19 (Exigent Circumstances) ML15238B6612015-09-15015 September 2015 Relief Request 53, Alternative to ASME Code Section XI Requirements Related to Flaw Removal ML15070A1242015-03-30030 March 2015 Issuance of Amendment Nos. 195, 195, and 195, Adopt TSTF-486, Revision 2, Revise Mtc Surveillance for Startup Test Activity Reduction (STAR) Program (WCAP-16011) and TSTF-406, Revision 2 ML15079A0062015-03-30030 March 2015 Relief Request 52 - Request for Approval of Alternate to Flaw Removal, Flaw Characterization and Successive Examinations, for the Remainder of Its Useful Life 2024-08-20
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 October 14, 2010 Mr. Randall K.
Executive Vice President Chief Nuclear Officer Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034 PALO VERDE NUCLEAR GENERATING STATION, UNIT 3 -RELIEF REQUEST NO. 47 RE: ASME CODE CLASS 1 WELD AND COMPONENT VOLUMETRIC EXAMINATIONS FOR THE SECOND 10-YEAR INSERVICE INSPECTION INTERVAL (TAC NO. ME3052)
Dear Mr. Edington:
By letter dated December 21,2009, as supplemented by letter dated August 27, 2010, Arizona Public Service Company (APS, the licensee) submitted Request for Relief No. 47 to the Nuclear Regulatory Commission (NRC) for relief from certain American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI requirements at Palo Verde Nuclear Generating Station, Unit 3 (PVNGS-3).
In its submittal, the licensee, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(g)(6)(i), requested relief from certain ASME Code Class 1 weld and component examinations for the second 1 O-year inservice inspection (lSI) program interval on the basis that the ASME Code requirement is impractical.
As set forth in the enclosed safety evaluation, the NRC staff has reviewed the licensee's submittal and concludes that ASME Code examination coverage requirements are impractical for Reactor Vessel Nozzle-to-Vessel Welds 1-15 and 1-18. Furthermore, imposition of these ASME Code requirements would create a burden on the licensee.
The staff further determined that it is reasonable to conclude that if significant service-induced degradation had occurred, evidence of it would have been detected by the examinations that were performed.
Furthermore, the staff concludes that the examinations performed to the extent practical on the subject reactor vessel nozzle-to-vessel welds provide reasonable assurance of structural integrity of the subject welds. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(g)(6)(i).
Therefore, the NRC staff grants relief for the subject examinations of the components contained in Relief Request No. 47 at PVNGS-3 for the second 1 O-year lSI program interval, which ended on January 10, 2008. The NRC staff has further determined that granting relief pursuant to 10 CFR 50.55a(g)(6)(i) is authorized by law and will not endanger life or property, or the common defense and security, and is otherwise in the public interest giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.
R. Edington -2 All other ASME Code,Section XI requirements for which relief was not specifically requested and approved in the subject requests for relief remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
If you have any questions, please contact James R. Hall at 301-415-4032.
Sincerely, l
- Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. STN Safety cc w/encl: Distribution via UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REQUEST FOR RELIEF NO. 47 REGUARDING CERTAIN REACTOR VESSEL NOZZLE-TO-VESSEL WELDS ARIZONA PUBLIC SERVICE COMPANY PALO VERDE NUCLEAR GENERATING STATION, UNIT 3 DOCKET NO. STN 50-530
1.0 INTRODUCTION
By letter dated December 21, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 100040068), as supplemented by letter dated August 27, 2010 (ADAMS Accession No. ML 102510171), Arizona Public Service Company (APS, the licensee) submitted Request for Relief No. 47 to the Nuclear Regulatory Commission (NRC) for relief from certain American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI requirements at Palo Verde Nuclear Generating Station, Unit 3 (PVNGS-3).
In its submittal, the licensee, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(g)(6)(i), requested relief from certain ASME Code Class 1 weld and component examinations for the second 1 O-year inservice inspection (lSI) program interval on the basis that the ASME Code requirement is impractical.
2.0 REGULATORY EVALUATION
Inservice inspection of the ASIVIE Code Class 1, 2, and 3 components is to be performed in accordance with Section XI of the ASME Code, and applicable addenda, as required by 10 CFR 50.55a(g), except where specific relief has been granted by the Commission pursuant to 10 CFR 50.55a(g)(6)(i).
The regUlations in 10 CFR 50.55a(a)(3) state that alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if the licensee demonstrates that (i) the proposed alternatives would provide an acceptable level of quality and safety, or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety. Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the preservice examination requirements, set forth in the ASME Code,Section XI, to the extent practical within the limitations of design, geometry, and materials of construction of the components.
The regulations require that inservice examination of components and system pressure tests conducted during the first 1 O-year interval and subsequent intervals comply with Enclosure
-2 the requirements in the latest edition and addenda of Section XI of the ASME Code, which was incorporated by reference in 10 CFR 50.55a(b) 12 months prior to the start of the 120-month interval, sUbject to the limitations and modifications listed therein. The ASME Code of record for PVNGS-3's second 10-year lSI program interval, which ended on January 10, 2008, is the 1992 Edition, through 1992 Addenda, of Section XI of the ASME Boiler and Pressure Vessel Code. 3.0 TECHNICAL EVALUATION
3.1 Relief
Request No. 47 Relief Request No. 47 supports closure of the second 10-year lSI program interval for PVNGS-3. Based on a one-cycle deferral of the PVNGS-3 reactor vessel nozzle-to-vessel weld examinations, submitted in Relief Request 34 and approved by the NRC on May 16, 2007 (ADAMS Accession No. ML071140033), the subject PVNGS-3 examinations were performed during the unit's 14th refueling outage completed on May 28, 2009. As such, the licensee's submittal of this request for relief on December 21, 2009, was less than 12 months after the completion of the sUbject examinations and consistent with the requirements of 10 CFR 50.55a(g)(5)(iv) as they apply in this circumstance.
ASME Code,Section XI, Examination Category B-D, Reactor Vessel Nozzle-to-Vessel Welds, Item Number B3.90 in Table IWB-2500-7 requires essentially 100 percent volumetric examination of the reactor vessel nozzle-to-vessel welds. "Essentially 100%," as clarified by ASME Code Case N-460, "Alternative Examination Coverage for Class 1 and Class 2 Welds," is greater than 90 percent coverage of the examination volume, or surface area, as applicable.
ASME Code Case N-460 has been approved for use by the NRC in Regulatory Guide 1.147, Revision 15, "Inservice Inspection Code Case Acceptability" (RG 1.147).
The licensee is requesting relief from the requirement to examine essentially 100 percent of the reactor vessel nozzle-to-vessel welds for the following components:
- Weld 1-15 on hot leg nozzle A
- Weld 1-18 on hot leg nozzle B In its letter dated December 21,2009, the licensee provided the following information:
3.1.1 Impracticality
of Compliance (as stated by the licensee)
ASME Code requires a minimum of 90 percent coverage of the weld volume; but, because of the configuration of the reactor vessel outlet nozzles and the geometric shape, the examination is limited and APS is seeking relief from the [ASME] Code requirement.
3.1.2 Burden
Caused by Compliance (as stated by the licensee)
Due to component geometry several scans are performed on these nozzles to maximize coverage.
To comply with the [ASME] Code, the reactor vessel outlet nozzles and geometric shape would need to be redesigned and modified to increase the coverage to 90 percent or better.
-3 3.1.3 Proposed Alternative and Basis for Relief (as stated by the licensee)
Figure 1 [shown on page 3 of the Enclosure to the licensee's letter dated December 21, 2009] illustrates the lSI drawing for Zone 1 and the welds 1-15 and 1-18. The design of the reactor vessel outlet nozzle protrusion provides a geometric limitation to the scanning area. The examination robot and transducer sled are physically limited by this protrusion
.... All reactor vessel surfaces were examined, with the exception of scanning from the radius and protrusion.
Examination scanning was performed on these nozzles to obtain the highest examination volume practical.
The examination volume coverage was 98% for perpendicular to the weld centerline scans from the nozzle bore. The tangential scans that are parallel to the weld centerline are limited to 67%. The overall combined examination volume was 82.5%. Based on the above evaluation, the proposed alternative is to examine these welds to the extent practical.
3.2 NRC Staff Evaluation The ASME Code requires essentially 100 percent volumetric examination of the reactor vessel nozzle-to-vessel welds; however, due to the design of the reactor vessel outlet nozzle, a protrusion provides a geometric limitation to the scanning area. To comply with the ASME Code, the reactor vessel outlet nozzles would need to be redesigned and modified to increase the coverage to 90 percent or better. Imposition of this requirement would create a burden on the licensee; therefore, the ASME Code-required examination is impractical.
Ultrasonic examination scanning was performed on these nozzles to obtain the highest examination volume practical.
The examination volume coverage was 98 percent for perpendicular to the weld centerline scans from the nozzle bore. The tangential scans that are parallel to the weld centerline are limited to 67 percent. The overall combined examination volume was 82.5 percent. This was confirmed by the NRC staff's review of figures and drawings provided by the licensee to substantiate the coverage obtained.
There were no indications recorded during the ultrasonic inspections of Welds 1-15 and 1-18. Based on the volumetric examination coverage obtained on the nozzle welds, it is reasonable to conclude that, if significant service-induced degradation had occurred, evidence of it would have been detected by the examinations performed.
Furthermore, the staff concluded that the examinations performed to the extent practical provide reasonable assurance of structural integrity of the subject welds.
4.0 CONCLUSION
The NRC staff has reviewed the licensee's submittal and concludes that ASME Code examination coverage requirements are impractical for Reactor Vessel Nozzle-to-Vessel Welds 1-15 and 1-18. Furthermore, imposition of these ASME Code requirements would create a burden on the licensee.
The staff further determined that it is reasonable to conclude that if significant service-induced degradation had occurred, evidence of it would have been detected by the examinations that were performed.
Furthermore, the staff concludes that the
-examinations performed to the extent practical on the subject reactor vessel nozzle-to-vessel welds provide reasonable assurance of structural integrity of the subject welds. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(g)(6)(i).
Therefore, the NRC staff grants relief for the subject examinations of the components contained in Relief Request No. 47 at PVNGS-3 for the second 10-year lSI program interval, which ended on January 10, 2008. The staff has further determined that granting relief pursuant to 10 CFR 50.55a(g)(6)(i) is authorized by law and will not endanger life or property, or the common defense and security, and is otherwise in the public interest giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.
All other ASME Code,Section XI requirements for which relief was not specifically requested and approved in the subject requests for relief remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
Principal Contributor:
Edward Andruszkiewicz Date: October 14, 2010 R. Edington -2 All other ASME Code,Section XI requirements for which relief was not specifically requested and approved in the subject requests for relief remain applicable, including third-party review by the Authorized Nuclear Inservice Inspector.
If you have any questions, please contact James R. Hall at 301-415-4032.
Sincerely, IRA! Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. STN Safety cc w/encl: Distribution via LPLIV RidsAcrsAcnw_MailCTR RidsNrrDciCvib RidsNrrDorlDpr RidsNrrDorlLpl4 RidsNrrPMPaloVerde RidsNrrLAJBurkhardt RidsOgcRp RidsRgn4MailCenter L Trocine, EDO EAndruszkiewicz, ADAMS A ccesslon N o. ML 102670080