| number = ML063260215
| number = ML063260215
| issue date = 11/22/2006
| issue date = 11/22/2006
| title = Braidwood Unit 1, Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors
| title = Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors
| author name = Coutu T
| author name = Coutu T
| author affiliation = Exelon Nuclear
| author affiliation = Exelon Nuclear
Line 14: Line 14:
| page count = 41
| page count = 41
| project =  
| project =  
| stage = RAI
| stage = Request
}}
}}



Revision as of 16:38, 10 February 2019

Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors
ML063260215
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 11/22/2006
From: Coutu T
Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BW060101, EA-03-009
Download: ML063260215 (41)


Text

______________Exel_n~

~xe1on Generation Company, LLC www exeloncorp corn N 1 ci Braidwood Station 3 10 CFR 50.55a November 22, 2006 BW0601 01 United States Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, Maryland 20852 Braidwood Station, Unit 1 Facility Operating License No.NPF-72 NRC Docket No.50-456

Subject:

Relaxation Request for First Revised Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors

References:

(1)Letter from K.J.PoIson (Exelon Generation Company, LLC)to NRC,"Braidwood Station, Unit 1, 60-Day Response to First Revised NRC Order EA-03-009,'Issuance of First Revised NRC Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors,"

dated June 29, 2006 (2)Letter from J.A.Bauer (Exelon Generation Company, LLC)to NRC,"Relaxation Request for First Revised Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors,"

dated March 31, 2006 (3)Letter from T.J.McGinty (NRR)to C.M.Crane (Exelon),"Byron Station, Unit No.1, and Braidwood Station, Unit No.2-Relaxation of the First Revised Order EA-03-009 (TAC NOS.MD 1159 and MD 1160)"dated September 11, 2006 On February 11, 2003, the NRC issued Order EA-03-009 for interim inspection requirements for reactor pressure vessel (RPV)heads at pressurized water reactor (PWR)facilities.

On February 20, 2004, the NRC issued the First Revised Order EA-03-009 (the Order), which superseded Order EA-03-009.

Revision 1 of the Order modified the requirements regarding nondestructive examination of the penetration nozzles.

______________Exel_n~

~xe1on Generation Company, LLC www exeloncorp corn N 1 ci Braidwood Station 3 10 CFR 50.55a November 22, 2006 BW0601 01 United States Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, Maryland 20852 Braidwood Station, Unit 1 Facility Operating License No.NPF-72 NRC Docket No.50-456

Subject:

Relaxation Request for First Revised Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors

References:

(1)Letter from K.J.PoIson (Exelon Generation Company, LLC)to NRC,"Braidwood Station, Unit 1, 60-Day Response to First Revised NRC Order EA-03-009,'Issuance of First Revised NRC Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors,"

dated June 29, 2006 (2)Letter from J.A.Bauer (Exelon Generation Company, LLC)to NRC,"Relaxation Request for First Revised Order (EA-03-009)

Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors,"

dated March 31, 2006 (3)Letter from T.J.McGinty (NRR)to C.M.Crane (Exelon),"Byron Station, Unit No.1, and Braidwood Station, Unit No.2-Relaxation of the First Revised Order EA-03-009 (TAC NOS.MD 1159 and MD 1160)"dated September 11, 2006 On February 11, 2003, the NRC issued Order EA-03-009 for interim inspection requirements for reactor pressure vessel (RPV)heads at pressurized water reactor (PWR)facilities.

On February 20, 2004, the NRC issued the First Revised Order EA-03-009 (the Order), which superseded Order EA-03-009.

Revision 1 of the Order modified the requirements regarding nondestructive examination of the penetration nozzles.