05000275/FIN-2013003-02: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 12: Line 12:
| identified by = Licensee
| identified by = Licensee
| Inspection procedure =  
| Inspection procedure =  
| Inspector = C Osterholtz, D Strickland, L Micewski, N O,'Keefe T, Farina T, Hipschma
| Inspector = C Osterholtz, D Strickland, L Micewski, N O'Keefe, T Farina, T Hipschman
| CCA = N/A for ROP
| CCA = N/A for ROP
| INPO aspect =  
| INPO aspect =  
| description = The inspectors reviewed a licensee-identified Green non-cited violation of Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, for failure to correctly translate the design basis requirement for welded anchorage configurations into specifications and drawings for electrical load centers. Specifically, in 1977, seismic design qualification testing established the 125-volt DC load center anchor design, but the licensee failed to update Drawing 050053, Sheet 11, Anchorage Requirements for Design Class I Electrical Equipment, Revision 12, to reflect the tested configuration. As a result, Load Center SD21 was reinstalled in the plant after the testing with an anchorage configuration that was less robust than the tested configuration, which degraded the load centers ability to withstand a seismic event. The performance deficiency was more than minor because it was associated with the design control attribute of the mitigating system cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the missing welds on the load center anchorage reduced the capability of the cabinet to withstand shaking from a seismic event compared to the seismic verification test configuration. This violation was of very low safety significance (Green) because, while the violation was a deficiency affecting design or qualification of a mitigating system, it did not result in the loss of operability or functionality of the system. The licensee entered the issue into the corrective action program as Notification 50540606 and has corrected the condition by adding additional welds to the base of the load center consistent with the configuration used for design qualification testing.  
| description = The inspectors reviewed a licensee-identified Green non-cited violation of Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, for failure to correctly translate the design basis requirement for welded anchorage configurations into specifications and drawings for electrical load centers. Specifically, in 1977, seismic design qualification testing established the 125-volt DC load center anchor design, but the licensee failed to update Drawing 050053, Sheet 11, Anchorage Requirements for Design Class I Electrical Equipment, Revision 12, to reflect the tested configuration. As a result, Load Center SD21 was reinstalled in the plant after the testing with an anchorage configuration that was less robust than the tested configuration, which degraded the load centers ability to withstand a seismic event. The performance deficiency was more than minor because it was associated with the design control attribute of the mitigating system cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the missing welds on the load center anchorage reduced the capability of the cabinet to withstand shaking from a seismic event compared to the seismic verification test configuration. This violation was of very low safety significance (Green) because, while the violation was a deficiency affecting design or qualification of a mitigating system, it did not result in the loss of operability or functionality of the system. The licensee entered the issue into the corrective action program as Notification 50540606 and has corrected the condition by adding additional welds to the base of the load center consistent with the configuration used for design qualification testing.  
}}
}}

Latest revision as of 10:47, 30 May 2018

02
Site: Diablo Canyon Pacific Gas & Electric icon.png
Report IR 05000275/2013003 Section 4OA7
Date counted Jun 30, 2013 (2013Q2)
Type: NCV: Green
cornerstone Mitigating Systems
Identified by: Licensee-identified
Inspection Procedure:
Inspectors (proximate) C Osterholtz
D Strickland
L Micewski
N O'Keefe
T Farina
T Hipschman
Violation of: 10 CFR 50 Appendix B Criterion III, Design Control
INPO aspect
'