| Q | CCA | Title |
---|
05000275/FIN-2011005-02 | 2011Q4 | H.14 | Failure to Perform an Operability Determination for New Seismic Information |
05000275/FIN-2011005-01 | 2011Q4 | P.2 | Less than Adequate Evaluations of a Degreaded/Non-conforming Control Room Habitability Train |
05000275/FIN-2012403-01 | 2012Q1 | P.6 | Security |
05000275/FIN-2012002-01 | 2012Q1 | P.2 | Inadequate Operability Determination |
05000275/FIN-2012002-02 | 2012Q1 | | Incomplete and Inaccurate Information Provided to the NRC in Response to Generic Letter 2003-01, Control Room Habitability |
05000275/FIN-2012003-05 | 2012Q2 | | Control Room Habitability Operability Issues |
05000275/FIN-2012003-07 | 2012Q2 | H.1 | Entering a High Radiation Area with Dose Rates Greater than 1.0 Rem/Hour Without Knowing the Dose Rates in the Area |
05000275/FIN-2012003-06 | 2012Q2 | H.12 | Failure to Follow Procedure Resulted in the Loss of Low Temperature Overpressure Protection System Safety Function |
05000275/FIN-2012003-04 | 2012Q2 | H.12 | Feedwater System Weld Flaw |
05000275/FIN-2012003-03 | 2012Q2 | H.2 | Failure to Follow Procedure for the Control of Tools for Use on Stainless Steel |
05000275/FIN-2012003-01 | 2012Q2 | H.14 | Inadequate Preferred Offsite Power System Design Control |
05000275/FIN-2012003-02 | 2012Q2 | H.14 | Failure to Perform a 50.59 Evaluation |
05000275/FIN-2012404-02 | 2012Q3 | | Security |
05000275/FIN-2012404-01 | 2012Q3 | H.2 | Security |
05000275/FIN-2012004-01 | 2012Q3 | H.14 | Inadequate Corrective Actions to Update the Final Safety Analysis Report Update with Required Information |