| number = ML14330A311
| number = ML14330A311
| issue date = 12/15/2014
| issue date = 12/15/2014
| title = Diablo Canyon Power Plant, Units 1 and 2, Results of NRC Assessment of New Seismic Hazards Information Developed in Response to State of California Assembly Bill 1632 (TAC Nos. MF4750 and MF4751)
| title = Results of NRC Assessment of New Seismic Hazards Information Developed in Response to State of California Assembly Bill 1632
| author name = Lingam S P
| author name = Lingam S
| author affiliation = NRC/NRR/DORL/LPLIV-1
| author affiliation = NRC/NRR/DORL/LPLIV-1
| addressee name = Halpin E D
| addressee name = Halpin E
| addressee affiliation = Pacific Gas & Electric Co
| addressee affiliation = Pacific Gas & Electric Co
| docket = 05000275, 05000323
| docket = 05000275, 05000323
| license number = DPR-080, DPR-082
| license number = DPR-080, DPR-082
| contact person = Oesterle E R
| contact person = Oesterle E
| case reference number = TAC MF4750, TAC MF4751
| case reference number = TAC MF4750, TAC MF4751
| document type = Letter
| document type = Letter
| page count = 2
| page count = 2
| project = TAC:MF4750, TAC:MF4751
| project = TAC:MF4750, TAC:MF4751
| stage = Other
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 15, 2014 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424 SUBJECT: DIABLO CANYON POWER PLANT, UNITS 1 AND 2-NEW SEISMIC HAZARDS INFORMATION DEVELOPED IN RESPONSE TO STATE OF CALIFORNIA ASSEMBLY BILL 1632 (TAC NOS. MF4750 AND MF4751) Dear Mr. Halpin: The purpose of this letter is to acknowledge receipt of your letter and enclosed report, "Central California Seismic Imaging Project" (CCSIP) dated September 10, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 14260A106), which provided information related to the advanced seismic studies performed at Diablo Canyon Power Plant, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) understands that Pacific Gas and Electric Company (PG&E) will also use the CCSIP report for its response to the NRC's March 12, 2012 (ADAMS Accession No. ML 12056A046), request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50, Section 50.54(f), regarding seismic hazard re-evaluation. PG&E's scheduled response date is March 2015. Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv Sincerely, Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation December 15, 2014 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424 SUBJECT: DIABLO CANYON POWER PLANT, UNITS 1 AND 2-NEW SEISMIC HAZARDS INFORMATION DEVELOPED IN RESPONSE TO STATE OF CALIFORNIA ASSEMBLY BILL 1632 (TAC NOS. MF4750 AND MF4751) Dear Mr. Halpin: The purpose of this letter is to acknowledge receipt of your letter and enclosed report, "Central California Seismic Imaging Project" (CCSIP) dated September 10, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 14260A106), which provided information related to the advanced seismic studies performed at Diablo Canyon Power Plant, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) understands that Pacific Gas and Electric Company (PG&E) will also use the CCSIP report for its response to the NRC's March 12, 2012 (ADAMS Accession No. ML 12056A046), request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50, Section 50.54(f), regarding seismic hazard re-evaluation. PG&E's scheduled response date is March 2015. Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv DISTRIBUTION: PUBLIC LPL4-1 Reading RidsAcrsAcnw _MaiiCTR Resource RidsNrrDoriLpl4-1 Resource RidsNrrDeEmcb Resource RidsNrrJLD Resource RidsNrrLAJ Burkhardt Resource RidsNrrPMDiabloCanyon Resource RidsRgn4MaiiCenter Resource ADAMS Accession No
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 15, 2014 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424
* ML 14330A311 .. OFFICE N RR/DORL/LPL4-1 /PM NAME SLingam DATE 12/10/14 OFFICE OGC (NLO) NAME DRoth DATE 12/10/14 Sincerely, /RAJ Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation NRR/DORLILPL4-1 /LA NRR/DORLILPL4-1/BC (A) JBurkhardt EOesterle 12/10/14 12/10/14 NRR/DORL!DD NRR/DORL/LPL4-1/PM GWilson SLing am 12/15/14 12/15/14 OFFICIAL RECORD COPY 
 
}}
==SUBJECT:==
DIABLO CANYON POWER PLANT, UNITS 1 AND 2- NEW SEISMIC HAZARDS INFORMATION DEVELOPED IN RESPONSE TO STATE OF CALIFORNIA ASSEMBLY BILL 1632 (TAC NOS. MF4750 AND MF4751)
 
==Dear Mr. Halpin:==
 
The purpose of this letter is to acknowledge receipt of your letter and enclosed report, "Central California Seismic Imaging Project" (CCSIP) dated September 10, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14260A106), which provided information related to the advanced seismic studies performed at Diablo Canyon Power Plant, Units 1 and 2.
The U.S. Nuclear Regulatory Commission (NRC) understands that Pacific Gas and Electric Company (PG&E) will also use the CCSIP report for its response to the NRC's March 12, 2012 (ADAMS Accession No. ML12056A046), request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50, Section 50.54(f), regarding seismic hazard re-evaluation.
PG&E's scheduled response date is March 2015.
Sincerely,
                                              ~cr*~
Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv
 
ML12056A046), request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50, Section 50.54(f), regarding seismic hazard re-evaluation.
PG&E's scheduled response date is March 2015.
Sincerely,
                                            /RAJ Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL4-1 Reading RidsAcrsAcnw_MaiiCTR Resource RidsNrrDoriLpl4-1 Resource RidsNrrDeEmcb Resource RidsNrrJLD Resource RidsNrrLAJ Burkhardt Resource RidsNrrPMDiabloCanyon Resource RidsRgn4MaiiCenter Resource ADAMS Accession No
* ML14330A311 OFFICE     NRR/DORL/LPL4-1 /PM         NRR/DORLILPL4-1 /LA           NRR/DORLILPL4-1/BC (A)
NAME        SLingam                      JBurkhardt                   EOesterle DATE        12/10/14                     12/10/14                     12/10/14 OFFICE      OGC        (NLO)            NRR/DORL!DD                   NRR/DORL/LPL4-1/PM NAME        DRoth                        GWilson                       SLing am DATE        12/10/14                    12/15/14                     12/15/14}}

Latest revision as of 17:53, 19 March 2020

Results of NRC Assessment of New Seismic Hazards Information Developed in Response to State of California Assembly Bill 1632
ML14330A311
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 12/15/2014
From: Siva Lingam
Plant Licensing Branch IV
To: Halpin E
Pacific Gas & Electric Co
Oesterle E
References
TAC MF4750, TAC MF4751
Download: ML14330A311 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 15, 2014 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424

SUBJECT:

DIABLO CANYON POWER PLANT, UNITS 1 AND 2- NEW SEISMIC HAZARDS INFORMATION DEVELOPED IN RESPONSE TO STATE OF CALIFORNIA ASSEMBLY BILL 1632 (TAC NOS. MF4750 AND MF4751)

Dear Mr. Halpin:

The purpose of this letter is to acknowledge receipt of your letter and enclosed report, "Central California Seismic Imaging Project" (CCSIP) dated September 10, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14260A106), which provided information related to the advanced seismic studies performed at Diablo Canyon Power Plant, Units 1 and 2.

The U.S. Nuclear Regulatory Commission (NRC) understands that Pacific Gas and Electric Company (PG&E) will also use the CCSIP report for its response to the NRC's March 12, 2012 (ADAMS Accession No. ML12056A046), request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50, Section 50.54(f), regarding seismic hazard re-evaluation.

PG&E's scheduled response date is March 2015.

Sincerely,

~cr*~

Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv

ML12056A046), request for information pursuant to Title 10 of the Code of Federal Regulations, Part 50, Section 50.54(f), regarding seismic hazard re-evaluation.

PG&E's scheduled response date is March 2015.

Sincerely,

/RAJ Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC LPL4-1 Reading RidsAcrsAcnw_MaiiCTR Resource RidsNrrDoriLpl4-1 Resource RidsNrrDeEmcb Resource RidsNrrJLD Resource RidsNrrLAJ Burkhardt Resource RidsNrrPMDiabloCanyon Resource RidsRgn4MaiiCenter Resource ADAMS Accession No

  • ML14330A311 OFFICE NRR/DORL/LPL4-1 /PM NRR/DORLILPL4-1 /LA NRR/DORLILPL4-1/BC (A)

NAME SLingam JBurkhardt EOesterle DATE 12/10/14 12/10/14 12/10/14 OFFICE OGC (NLO) NRR/DORL!DD NRR/DORL/LPL4-1/PM NAME DRoth GWilson SLing am DATE 12/10/14 12/15/14 12/15/14