IR 05000528/2011501: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 02/28/2012 | | issue date = 02/28/2012 | ||
| title = IR 05000528-11-501, 05000529-11-501 & 05000530-11-501, on 12/31/2011, Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - NRC Emergency Preparedness Annual Report | | title = IR 05000528-11-501, 05000529-11-501 & 05000530-11-501, on 12/31/2011, Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - NRC Emergency Preparedness Annual Report | ||
| author name = Hay M | | author name = Hay M | ||
| author affiliation = NRC/RGN-IV/DRS/PSB-1 | | author affiliation = NRC/RGN-IV/DRS/PSB-1 | ||
| addressee name = Edington R | | addressee name = Edington R | ||
| addressee affiliation = Arizona Public Service Co | | addressee affiliation = Arizona Public Service Co | ||
| docket = 05000528, 05000529, 05000530 | | docket = 05000528, 05000529, 05000530 | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:UNITE D S TATE S NUC LEAR RE GULATOR Y C OMMI S SI ON ary 28, 2012 | ||
==SUBJECT:== | |||
PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 - | |||
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000528/2011501, 05000529/2011501, AND 05000530/2011501 | NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000528/2011501, 05000529/2011501, AND 05000530/2011501 | ||
==Dear Mr. Edington:== | ==Dear Mr. Edington:== | ||
On December 31, 2011, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Palo Verde Nuclear Generating Station, Units 1, 2 and 3. This inspection began on January 1, 2011. Issuance of this letter closes NRC Inspection Report 05000528/2011501, 05000529/2011501, and 05000530/2011501. Observations and findings in these areas were provided in the quarterly integrated reports for your site. | On December 31, 2011, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Palo Verde Nuclear Generating Station, Units 1, 2 and 3. This inspection began on January 1, 2011. Issuance of this letter closes NRC Inspection Report 05000528/2011501, 05000529/2011501, and 05000530/2011501. Observations and findings in these areas were provided in the quarterly integrated reports for your site. | ||
In accordance with 10 CFR 2.390 of the | In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
cc via Electronic Distribution | Sincerely, | ||
/RA/ | |||
Michael C. Hay, Chief Plant Support Branch 1 Division of Reactor Safety Dockets: 50-528; 50-529; 50-530 Licenses: NPF-41; NPF-51; NPF-74 cc via Electronic Distribution | |||
Electronic distribution by RIV: | Arizona Public Service Company -2-Electronic distribution by RIV: | ||
Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov) | Regional Administrator (Elmo.Collins@nrc.gov) | ||
Deputy Regional Administrator (Art.Howell@nrc.gov) | |||
DRP Director (Kriss.Kennedy@nrc.gov) | DRP Director (Kriss.Kennedy@nrc.gov) | ||
DRP Deputy Director (Troy.Pruett@nrc.gov) | DRP Deputy Director (Troy.Pruett@nrc.gov) | ||
Line 49: | Line 46: | ||
Project Engineer, DRP/D (David.You@nrc.gov) | Project Engineer, DRP/D (David.You@nrc.gov) | ||
Project Engineer, DRP/D (Brian.Parks@nrc.gov) | Project Engineer, DRP/D (Brian.Parks@nrc.gov) | ||
Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) | Public Affairs Officer (Victor.Dricks@nrc.gov) | ||
Public Affairs Officer (Lara.Uselding@nrc.gov) | |||
Project Manager (Lauren.Gibson@nrc.gov) | Project Manager (Lauren.Gibson@nrc.gov) | ||
Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov) | Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov) | ||
Line 56: | Line 54: | ||
Congressional Affairs Officer (Jenny.Weil@nrc.gov) | Congressional Affairs Officer (Jenny.Weil@nrc.gov) | ||
OEMail Resource ROPreports RIV/ETA: OEDO (Lydia.Chang@nrc.gov) | OEMail Resource ROPreports RIV/ETA: OEDO (Lydia.Chang@nrc.gov) | ||
DRS/TSB STA (Dale.Powers@nrc.gov) | DRS/TSB STA (Dale.Powers@nrc.gov) | ||
ADAMS: No x Yes x SUNSI Review Complete Reviewer Initials: MCH x Publicly Available x Non-Sensitive Non-publicly Available Sensitive C:PSB-1 MCHay | |||
ADAMS: No x Yes x SUNSI Review Complete Reviewer Initials: MCH x Publicly Available x Non-Sensitive Non-publicly Available Sensitive C:PSB-1 MCHay /RA/ 2/28/12 | /RA/ | ||
2/28/12 | |||
}} | }} |
Latest revision as of 07:40, 12 November 2019
ML120590985 | |
Person / Time | |
---|---|
Site: | Palo Verde |
Issue date: | 02/28/2012 |
From: | Hay M Plant Support Branch-1 |
To: | Edington R Arizona Public Service Co |
References | |
IR-11-501 | |
Download: ML120590985 (2) | |
Text
UNITE D S TATE S NUC LEAR RE GULATOR Y C OMMI S SI ON ary 28, 2012
SUBJECT:
PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -
NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000528/2011501, 05000529/2011501, AND 05000530/2011501
Dear Mr. Edington:
On December 31, 2011, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Palo Verde Nuclear Generating Station, Units 1, 2 and 3. This inspection began on January 1, 2011. Issuance of this letter closes NRC Inspection Report 05000528/2011501, 05000529/2011501, and 05000530/2011501. Observations and findings in these areas were provided in the quarterly integrated reports for your site.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Michael C. Hay, Chief Plant Support Branch 1 Division of Reactor Safety Dockets: 50-528; 50-529; 50-530 Licenses: NPF-41; NPF-51; NPF-74 cc via Electronic Distribution
Arizona Public Service Company -2-Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Art.Howell@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Tom.Blount@nrc.gov)
Senior Resident Inspector (Tony.Brown@nrc.gov)
Resident Inspector (Mica.Baquera@nrc.gov)
Branch Chief, DRP/D (Ryan.Lantz@nrc.gov)
PV Administrative Assistant (Regina.McFadden@nrc.gov)
Project Engineer, DRP/D (David.You@nrc.gov)
Project Engineer, DRP/D (Brian.Parks@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Lauren.Gibson@nrc.gov)
Acting Branch Chief, DRS/TSB (Ryan.Alexander@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource ROPreports RIV/ETA: OEDO (Lydia.Chang@nrc.gov)
DRS/TSB STA (Dale.Powers@nrc.gov)
ADAMS: No x Yes x SUNSI Review Complete Reviewer Initials: MCH x Publicly Available x Non-Sensitive Non-publicly Available Sensitive C:PSB-1 MCHay
/RA/
2/28/12