| issue date = 04/03/2014
| issue date = 04/03/2014
| title = Status Update Letter in the Matter of Nextera Energy Seabrook, LLC, (Seabrook, Unit 1)
| title = Status Update Letter in the Matter of Nextera Energy Seabrook, LLC, (Seabrook, Unit 1)
| author name = Harris B G
| author name = Harris B
| author affiliation = NRC/OGC
| author affiliation = NRC/OGC
| addressee name = Kennedy M F, Ryerson P S, Wardwell R E
| addressee name = Kennedy M, Ryerson P, Wardwell R
| addressee affiliation = NRC/ASLBP
| addressee affiliation = NRC/ASLBP
| docket = 05000443
| docket = 05000443
Line 14: Line 14:
| page count = 2
| page count = 2
}}
}}
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 April 3, 2014 Administrative Judge                                Administrative Judge Paul S. Ryerson, Chair                              Dr. Richard E. Wardwell Atomic Safety and Licensing Board                    Atomic Safety and Licensing Board Mail Stop: T-3F23                                    Mail Stop: T-3F23 Washington, DC 20555-001                            Washington, DC 20555-0001 Administrative Judge Dr. Michael F. Kennedy Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of NEXTERA ENERGY SEABROOK, LLC (Seabrook Station, Unit 1)
Docket No. 50-443-LR
==Dear Administrative Judges:==
Pursuant to the Boards March 11, 2013 Memorandum and Order (Requiring Update of Staff's Project Schedule) in the Matter of NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1),
the Staff informs the Board that there have been no changes to its safety and environmental review schedules for the Seabrook license renewal application. The Staff currently anticipates publication of the Final Supplemental Environmental Impact Statement in July 2014. As previously noted, the Staff is currently unable to project a date for completion of the safety review.
Sincerely, Signed (electronically) by Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: April 3, 2014
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of                                        )
                                                        )
NEXTERA ENERGY SEABROOK, LLC                            )      Docket No. 50-443-LR
                                                        )
(Seabrook Station, Unit 1)                              )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing letter from Brian G. Harris to the Board, dated March 6, 2014, have been submitted through the E-filing System this 3rd day of April, 2014.
                                                        /Signed (electronically) by/
Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: April 3, 2014}}

Latest revision as of 21:10, 5 February 2020

Status Update Letter in the Matter of Nextera Energy Seabrook, LLC, (Seabrook, Unit 1)
ML14093A021
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 04/03/2014
From: Harris B
NRC/OGC
To: Kennedy M, Paul Ryerson, Richard Wardwell
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-443-LR, ASLBP 10-906-02-LR-BD01, RAS 25778
Download: ML14093A021 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 April 3, 2014 Administrative Judge Administrative Judge Paul S. Ryerson, Chair Dr. Richard E. Wardwell Atomic Safety and Licensing Board Atomic Safety and Licensing Board Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Dr. Michael F. Kennedy Atomic Safety and Licensing Board Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of NEXTERA ENERGY SEABROOK, LLC (Seabrook Station, Unit 1)

Docket No. 50-443-LR

Dear Administrative Judges:

Pursuant to the Boards March 11, 2013 Memorandum and Order (Requiring Update of Staff's Project Schedule) in the Matter of NextEra Energy Seabrook, LLC (Seabrook Station, Unit 1),

the Staff informs the Board that there have been no changes to its safety and environmental review schedules for the Seabrook license renewal application. The Staff currently anticipates publication of the Final Supplemental Environmental Impact Statement in July 2014. As previously noted, the Staff is currently unable to project a date for completion of the safety review.

Sincerely, Signed (electronically) by Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: April 3, 2014

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

NEXTERA ENERGY SEABROOK, LLC ) Docket No. 50-443-LR

)

(Seabrook Station, Unit 1) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing letter from Brian G. Harris to the Board, dated March 6, 2014, have been submitted through the E-filing System this 3rd day of April, 2014.

/Signed (electronically) by/

Brian G. Harris Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1392 E-mail: brian.harris@nrc.gov Date of signature: April 3, 2014