{{#Wiki_filter:August 17, 2022
{{#Wiki_filter:August 17, 2022
Mr. Ken J. Peters
Mr. Ken J. Peters
Senior Vice President and Chief Nuclear Officer
Senior Vice President and Chief Nuclear Officer
Line 24: Line 27:
P.O. Box 1002
P.O. Box 1002
Glen Rose, TX 76043
Glen Rose, TX 76043
SUBJECT:         COMANCHE PEAK NUCLEAR POWER PLANT - NOTIFICATION OF
 
                INSPECTION (NRC INSPECTION REPORT 05000445/2022004 AND
SUBJECT:     COMANCHE PEAK NUCLEAR POWER PLANT - NOTIFICATION OF
                05000446/2022004) AND REQUEST FOR INFORMATION
              INSPECTION (NRC INSPECTION REPORT 05000445/2022004 AND
              05000446/2022004) AND REQUEST FOR INFORMATION
 
Dear Mr. Peters:
Dear Mr. Peters:
During the week of October 24, 2022, two inspectors from the U.S. Nuclear Regulatory
During the week of October 24, 2022, two inspectors from the U.S. Nuclear Regulatory
Commissions (NRC) Region IV office will perform the baseline biennial requalification
Commissions (NRC) Region IV office will perform the baseline biennial requalification
inspection at Comanche Peak Nuclear Power Plant, using NRC Inspection
inspection at Comanche Peak Nuclear Power Plant, using NRC Inspection
Procedure 71111.11B, Licensed Operator Requalification Program.
Procedure 71111.11B, Licensed Operator Requalification Program.
Experience has shown that this inspection is a resource intensive inspection both for the NRC
Experience has shown that this inspection is a resource intensive inspection both for the NRC
inspectors and your staff. In order to minimize the impact to your onsite resources and to
inspectors and your staff. In order to minimize the impact to your onsite resources and to
ensure a productive inspection, we have enclosed a request for documents needed for this
ensure a productive inspection, we have enclosed a request for documents needed for this
inspection. These documents have been divided into three groups:
inspection. These documents have been divided into three groups:
        The first group (Section A of the enclosure) identifies information to be provided prior to
 
        the inspection to ensure that the inspectors are adequately prepared.
    The first group (Section A of the enclosure) identifies information to be provided prior to
        The second group (Section B of the enclosure) identifies the information the inspectors
      the inspection to ensure that the inspectors are adequately prepared.
        will need upon arrival at the site.
 
        The third group (Section C of this enclosure) identifies the items which are necessary to
    The second group (Section B of the enclosure) identifies the information the inspectors
        close out the inspection and are usually sent a few weeks after the team has left the site.
      will need upon arrival at the site.
 
    The third group (Section C of this enclosure) identifies the items which are necessary to
      close out the inspection and are usually sent a few weeks after the team has left the site.
 
It is important that all of these documents are up to date and complete in order to minimize the
It is important that all of these documents are up to date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
number of additional documents requested during the preparation and/or the onsite portions of
the inspection.
the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Mr. Terry Jank of your training organization.
that our regulatory contact for this inspection will be Mr. Terry Jank of your training organization.
Our inspection dates are subject to change based on your updated schedule of examination
Our inspection dates are subject to change based on your updated schedule of examination
activities. If there are any questions about this inspection or the material requested, please
activities. If there are any questions about this inspection or the material requested, please
contact the lead inspector, Bryan Bergeon at (817) 200-1415 (Bryan.Bergeon@nrc.gov).
contact the lead inspector, Bryan Bergeon at (817) 200-1415 (Bryan.Bergeon@nrc.gov).
 
K. Peters 2
K. Peters                                     2
PAPERWORK REDUCTION ACT STATEMENT  
PAPERWORK REDUCTION ACT STATEMENT
This letter contains mandatory information collections that are subject to the Paperwork
This letter contains mandatory information collections that are subject to the Paperwork  
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)  
approved these information collections (approval number 3150-0011). Send comments
approved these information collections (approval number 3150-0011). Send comments  
regarding this information collection to the Information Services Branch, Office of the Chief
regarding this information collection to the Information Services Branch, Office of the Chief  
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,  
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office  
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and  
Budget, Washington, DC 20503.
Budget, Washington, DC 20503.
Public Protection Notification
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
Public Protection Notification  
for information or an information collection requirement unless the requesting document
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request  
for information or an information collection requirement unless the requesting document  
displays a currently valid OMB control number.
displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter
and its enclosure will be available electronically for public inspection in the NRC Public
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter  
Document Room or from the Publicly Available Records (PARS) component of NRCs
and its enclosure will be available electronically for public inspection in the NRC Public  
document system (ADAMS). ADAMS is accessible from the NRC web site at
Document Room or from the Publicly Available Records (PARS) component of NRCs  
document system (ADAMS). ADAMS is accessible from the NRC web site at  
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                                  Sincerely,
Sincerely,
                                                                          Signed by Gepford, Heather
                                                                           
                                                                            on 08/17/22
Heather J. Gepford, Chief
                                                  Heather J. Gepford, Chief
Operations Branch  
                                                  Operations Branch
Division of Operating Reactor Safety
                                                  Division of Operating Reactor Safety
Docket No. 50-445; 50-446
Docket No. 50-445; 50-446
License No. NPF-87; NPF-89
License No. NPF-87; NPF-89
Enclosure:
Enclosure:
Biennial Requalification Inspection
Biennial Requalification Inspection
Request for Information
  Request for Information
Signed by Gepford, Heather
on 08/17/22




  ML22228A094
  ML22228A094
  OFFICE       OE:OB       C:OB
  OFFICE       OE:OB         C:OB
  NAME         BBergeon     HGepford
  NAME         BBergeon     HGepford
  SIGNATURE         BAB           HJG
  SIGNATURE       BAB         HJG
  DATE          08/16/2022   08/17/2022
  DATE          08/16/2022   08/17/2022
                                   
                                 
                                    Initial Request for Information
                                Initial Request for Information
                                  Biennial Requalification Inspection
                            Biennial Requalification Inspection
                                Comanche Peak Nuclear Power Plant
                            Comanche Peak Nuclear Power Plant
Inspection Report:                       5000445/2022004; 5000446/2022004
 
Inspection Dates:                         October 24, 2022 - October 28, 2022
Inspection Report:                             5000445/2022004; 5000446/2022004
Inspection Procedure:                     IP 71111.11B, Licensed Operator Requalification
 
                                          Program
Inspection Dates:                               October 24, 2022 - October 28, 2022
Lead Inspector:                           Bryan Bergeon, Operations Engineer
 
A. The following information is requested in order to support inspection preparation
Inspection Procedure:                       IP 71111.11B, Licensed Operator Requalification
    activities. These items are listed by section as they appear in the inspection module
                                    Program
    (i.e. 03.04a, 03.04b, etc.). Requested materials should be sent in an electronic format
 
    on CD/DVD in order to arrive at the Region IV office no later than October 10, 2022;
Lead Inspector:                                 Bryan Bergeon, Operations Engineer
    OR uploaded to the NRCs secure Box application no later than October 10, 2022.
 
            CD/DVD to: US Nuclear Regulatory Commission, Region IV
 
                            ATTN: Bryan Bergeon / Heather Gepford
A. The following information is requested in order to support inspection preparation
                            1600 E. Lamar Blvd
  activities. These items are listed by section as they appear in the inspection module
                            Arlington, TX 76011
  (i.e. 03.04a, 03.04b, etc.). Requested materials should be sent in an electronic format
    General Requests:
  on CD/DVD in order to arrive at the Region IV office no later than October 10, 2022;
            List of licensed operators (SRO & RO) by crew (operating & staff)
  OR uploaded to the NRCs secure Box application no later than October 10, 2022.
            Training and Operations Department organization charts (with qualified LOR
 
            evaluators identified)
        CD/DVD to: US Nuclear Regulatory Commission, Region IV
            Procedures that identify process for revising and maintaining LO continuing training
                        ATTN: Bryan Bergeon / Heather Gepford
            program up to date
                        1600 E. Lamar Blvd
            List of outstanding LOR program changes
                        Arlington, TX 76011
            List of plant events and industry operating experience incorporated into LOR
 
            program since last BRQ
  General Requests:
            Audits and/or self-assessment reports addressing the licensed operator
 
            requalification training program
        List of licensed operators (SRO & RO) by crew (operating & staff)
            Last 2 years of simulator review committee (or equivalent) meeting minutes
 
            Last 2 years of Curriculum Review Committee (or equivalent) meeting minutes
        Training and Operations Department organization charts (with qualified LOR
            A summary report of all condition reports related to operator actions/errors in the
          evaluators identified)
            control room
 
        Procedures that identify process for revising and maintaining LO continuing training
          program up to date
 
        List of outstanding LOR program changes


      Any revised requalification training that was based on licensed operator performance
        List of plant events and industry operating experience incorporated into LOR
          program since last BRQ
 
        Audits and/or self-assessment reports addressing the licensed operator
          requalification training program
 
        Last 2 years of simulator review committee (or equivalent) meeting minutes
 
        Last 2 years of Curriculum Review Committee (or equivalent) meeting minutes
 
        A summary report of all condition reports related to operator actions/errors in the
          control room
    Any revised requalification training that was based on licensed operator performance
       issues
       issues
03.04a: Biennial Requalification Written Examinations
 
      The current and approved biennial written examination schedule
03.04a: Biennial Requalification Written Examinations
      The current requalification cycle written examination results for both SRO & RO that
 
    The current and approved biennial written examination schedule
 
    The current requalification cycle written examination results for both SRO & RO that
       have already been administered up to the week prior to the inspection team arrival
       have already been administered up to the week prior to the inspection team arrival
       onsite.
       onsite.
      All written examinations that have been approved for administration up to and
 
       including the week before the inspection team is onsite. This will need to have
    All written examinations that have been approved for administration up to and
       including the week before the inspection team is onsite. This will need to have
       adequate password protection or double envelope protection if mailed via regular
       adequate password protection or double envelope protection if mailed via regular
       mail per NUREG-1021.
       mail per NUREG-1021.
      The current requalification cycle examination methodology (sample plan)
 
03.04b: Annual Requalification Operating Tests
    The current requalification cycle examination methodology (sample plan)
      The schedule for the operating tests (JPMs & scenarios) to be given the week of
 
03.04b: Annual Requalification Operating Tests
 
    The schedule for the operating tests (JPMs & scenarios) to be given the week of
       October 24, 2022
       October 24, 2022
      The operating tests (JPMs & scenarios) (password protected and provide separately
 
    The operating tests (JPMs & scenarios) (password protected and provide separately
       via telephone at later date) to be given the week of October 24, 2022
       via telephone at later date) to be given the week of October 24, 2022
      Current requalification cycle operating tests (SRO & RO) and results up to the week
 
    Current requalification cycle operating tests (SRO & RO) and results up to the week
       prior to the inspection team arrival onsite
       prior to the inspection team arrival onsite
      All 2021 NRC required annual operating tests
 
      Current requalification cycle operating test methodology (sample plan)
    All 2021 NRC required annual operating tests
03.04c: Administration of an Annual Requalification Operating Test
 
      All procedures used to administer the annual operating test
    Current requalification cycle operating test methodology (sample plan)
      All procedures used to assess operator performance
 
      All procedures that describe conduct of simulator training
03.04c: Administration of an Annual Requalification Operating Test
      All procedures used to test, operate, and maintain the simulator
 
03.04d: Requalification Examination Security
    All procedures used to administer the annual operating test
      Submit any tracking tools that you use as a means to prevent excessive overlap on
 
    All procedures used to assess operator performance
 
    All procedures that describe conduct of simulator training
 
    All procedures used to test, operate, and maintain the simulator
 
03.04d: Requalification Examination Security
 
    Submit any tracking tools that you use as a means to prevent excessive overlap on
       the written examinations and also meet the intent of sampling all required topics on a
       the written examinations and also meet the intent of sampling all required topics on a
       periodic basis.
       periodic basis.
 
    Submit any tracking tools that you use as a means to prevent excessive overlap on
      Submit any tracking tools that you use as a means to prevent excessive overlap on
       the operating tests and also meet the intent of sampling all required malfunctions
       the operating tests and also meet the intent of sampling all required malfunctions
       (including major events, instrument/component malfunctions, TS calls, etc.) on a
       (including major events, instrument/component malfunctions, TS calls, etc.) on a
       periodic basis.
       periodic basis.
      All procedures that describe examination security, including procedures used to
 
    All procedures that describe examination security, including procedures used to
       develop the examinations that include guidelines on overlap between examinations
       develop the examinations that include guidelines on overlap between examinations
       in current exam cycle tests and prior year examinations
       in current exam cycle tests and prior year examinations
      List of all condition reports since the last biennial requalification inspection related to
 
    List of all condition reports since the last biennial requalification inspection related to
       examination security and overlap
       examination security and overlap
03.04e: Remedial Training and Re-Examinations
 
      List of remedial training conducted or planned since last requalification exam
03.04e: Remedial Training and Re-Examinations
 
    List of remedial training conducted or planned since last requalification exam
       (includes training provided to operators to enable passing requalification exam and
       (includes training provided to operators to enable passing requalification exam and
       training provided to correct generic or individual weaknesses observed during
       training provided to correct generic or individual weaknesses observed during
       previous requalification exam cycle)
       previous requalification exam cycle)
      Remediation plans (lesson plans, reference materials, and attendance
 
    Remediation plans (lesson plans, reference materials, and attendance
       documentation)
       documentation)
03.04f: Operator License Conditions
 
      All procedures and program documentation for maintaining active operator licenses,
03.04f: Operator License Conditions
 
    All procedures and program documentation for maintaining active operator licenses,
       tracking training attendance, and ensuring medical fitness of licensed operators
       tracking training attendance, and ensuring medical fitness of licensed operators
      All procedures and associated documentation that supports reactivation of any
 
    All procedures and associated documentation that supports reactivation of any
       SRO/RO license (operating or staff crew) since the last biennial inspection
       SRO/RO license (operating or staff crew) since the last biennial inspection
03.04g: Control Room Simulator
 
      All simulator management and configuration procedures if not already provided
03.04g: Control Room Simulator
      Simulator discrepancy report summary list for all open discrepancy reports and
 
    All simulator management and configuration procedures if not already provided
 
    Simulator discrepancy report summary list for all open discrepancy reports and
       summary list for those items closed between October 1, 2020 and October 10, 2022
       summary list for those items closed between October 1, 2020 and October 10, 2022
      Primary parameters tested in order to verify core physics parameters (such as
 
       moderator temperature coefficient, integral rod worth)). The applicable reference
    Primary parameters tested in order to verify core physics parameters (such as
       moderator temperature coefficient, integral rod worth)). The applicable reference
       graphs from the plant physics data book (electronic or other means as available)
       graphs from the plant physics data book (electronic or other means as available)
       should also be included as well as the test procedures used and the acceptance
       should also be included as well as the test procedures used and the acceptance
       criteria with results.
       criteria with results.
      All simulator modification packages that are on hold, delayed, or not completed in the
 
    All simulator modification packages that are on hold, delayed, or not completed in the
       last 2 years
       last 2 years
      A list of simulator modification packages completed in the last two-year window


B. The following information is requested in order to support the onsite inspection
    A list of simulator modification packages completed in the last two-year window
   activities. Requested materials should be available to the inspection team, either
B. The following information is requested in order to support the onsite inspection
   activities. Requested materials should be available to the inspection team, either
   electronically or hardcopy, upon site arrival on October 24, 2022.
   electronically or hardcopy, upon site arrival on October 24, 2022.
   03.03: Requalification Exam Results / 03.04a and 03.04b: Biennial Requalification Written
 
   03.03: Requalification Exam Results / 03.04a and 03.04b: Biennial Requalification Written
           Exam and Annual Requalification Operating Tests Quality
           Exam and Annual Requalification Operating Tests Quality
          All operating tests (JPMs & scenarios) to be given in all subsequent weeks after
 
        All operating tests (JPMs & scenarios) to be given in all subsequent weeks after
           onsite week, if available
           onsite week, if available
          All results up to the day the team leaves the site
 
   03.04f: Conformance with Operator License Conditions
        All results up to the day the team leaves the site
          Access to licensed operators records (operating and staff crews)
 
          Access to licensed operators training attendance records
   03.04f: Conformance with Operator License Conditions
          Access to licensed operators medical records
 
   03.04g: Control Room Simulator Performance
        Access to licensed operators records (operating and staff crews)
          Simulator discrepancies from October 1, 2020 to October 24, 2022. This should
 
        Access to licensed operators training attendance records
 
        Access to licensed operators medical records
 
   03.04g: Control Room Simulator Performance
 
        Simulator discrepancies from October 1, 2020 to October 24, 2022. This should
           include all open and closed simulator discrepancy reports, including the
           include all open and closed simulator discrepancy reports, including the
           documentation/justification for closure.
           documentation/justification for closure.
          Acceptance test documentation, including hardware and software model revisions at
 
        Acceptance test documentation, including hardware and software model revisions at
           the time of acceptance (as available)
           the time of acceptance (as available)
          Documentation that validates current models, including the thermal-hydraulics and
 
        Documentation that validates current models, including the thermal-hydraulics and
           neutronics models, to the actual plant
           neutronics models, to the actual plant
          All current model deficiencies, including FSAR vs Design differences in the simulator
 
        All current model deficiencies, including FSAR vs Design differences in the simulator
           (any documentation on this)
           (any documentation on this)
          Summary list of modifications from October 1, 2020 to October 24, 2022
 
          Plant modifications (both hardware and software) completed on the simulator by due
        Summary list of modifications from October 1, 2020 to October 24, 2022
 
        Plant modifications (both hardware and software) completed on the simulator by due
           date from October 1, 2020 to October 24, 2022
           date from October 1, 2020 to October 24, 2022
          Simulator differences Lesson plan used in training (current to October 24, 2022)
 
          The complete book of all simulator annual performance test packages (usually in a
        Simulator differences Lesson plan used in training (current to October 24, 2022)
 
        The complete book of all simulator annual performance test packages (usually in a
           single book but may be electronic or in single test packages), complete with all
           single book but may be electronic or in single test packages), complete with all
           transient tests, steady state tests, and malfunction tests. This should also include
           transient tests, steady state tests, and malfunction tests. This should also include
           the test procedures for each test, the acceptance criteria, and results. For each
           the test procedures for each test, the acceptance criteria, and results. For each
           transient test, the reference chart should be included or an equivalent subject matter
           transient test, the reference chart should be included or an equivalent subject matter
           expert review versus the simulator results with a write-up for any differences beyond
           expert review versus the simulator results with a write-up for any differences beyond
           the ANSI standard requirements.
           the ANSI standard requirements.
         All test packages used to verify core physics parameters (such as moderator
         All test packages used to verify core physics parameters (such as moderator
           temperature coefficient and integral rod worth). The applicable reference graphs
           temperature coefficient and integral rod worth). The applicable reference graphs
           from the plant physics data book (electronic or other means as available) should also
           from the plant physics data book (electronic or other means as available) should also
           be included as well as the test procedures used and the acceptance criteria with
           be included as well as the test procedures used and the acceptance criteria with
           results.
           results.
         All simulator tests, configuration management, and related documents available in
         All simulator tests, configuration management, and related documents available in
           the room for inspectors to review. This includes training needs analysis packages,
           the room for inspectors to review. This includes training needs analysis packages,
           simulator review committee meeting minutes, etc.
           simulator review committee meeting minutes, etc.
         Current copy of ANSI 3.5 standard you are committed to for simulator testing
         Current copy of ANSI 3.5 standard you are committed to for simulator testing
C. Comanche Peak Nuclear Power Plant is required to send the final results summary
 
C. Comanche Peak Nuclear Power Plant is required to send the final results summary
   (see Table 1 below) and any remaining exams and operating tests that have not been
   (see Table 1 below) and any remaining exams and operating tests that have not been
   reviewed to the regional office lead inspector for this inspection for final review and
   reviewed to the regional office lead inspector for this inspection for final review and
   comparison against the Significance Determination Tools in order to communicate
   comparison against the Significance Determination Tools in order to communicate
   the exit results for the inspection.
   the exit results for the inspection.
      TABLE 1: EXAMINATION RESULTS
 
        1. Total number of licensed operators.
      TABLE 1: EXAMINATION RESULTS
        2. Number of licensed operators administered a requalification
 
        1. Total number of licensed operators.
        2. Number of licensed operators administered a requalification
             examination required by 10 CFR 55.59(a).
             examination required by 10 CFR 55.59(a).
        3. Number of individual licensed operators who failed any portion of a
        3. Number of individual licensed operators who failed any portion of a
             requalification examination (written, JPM, or individual simulator
             requalification examination (written, JPM, or individual simulator
             scenario failures).
             scenario failures).
        4. Divide line 3 by line 2 to obtain the individual requalification
        4. Divide line 3 by line 2 to obtain the individual requalification
             examination failure rate. Line 3/Line 2.                                       %
             examination failure rate. Line 3/Line 2.                                     %
        5. Number of crews administered simulator scenarios as part of a
        5. Number of crews administered simulator scenarios as part of a
             requalification examination required by 10 CFR 55.59(a).
             requalification examination required by 10 CFR 55.59(a).
        6. Number of crews who performed unsatisfactorily on the
        6. Number of crews who performed unsatisfactorily on the
             simulator scenarios.
             simulator scenarios.
        7. Divide line 6 by line 5 to obtain the crew simulator scenario
        7. Divide line 6 by line 5 to obtain the crew simulator scenario
             failure rate. Line 6/Line 5.                                                   %
             failure rate. Line 6/Line 5.                                                 %
}}
}}

Latest revision as of 05:14, 16 November 2024

Notification of Inspection (NRC Inspection Report 05000445/2022004 and 05000446/2022004) and Request for Information
ML22228A094
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/17/2022
From: Heather Gepford
NRC/RGN-IV/DORS/OB
To: Peters K
Vistra Operations Company
Bergeon B
References
IR 2022004
Download: ML22228A094 (8)


See also: IR 05000445/2022004

Text

August 17, 2022

Mr. Ken J. Peters

Senior Vice President and Chief Nuclear Officer

Attention: Regulatory Affairs

Vistra Operations Company LLC

P.O. Box 1002

Glen Rose, TX 76043

SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT - NOTIFICATION OF

INSPECTION (NRC INSPECTION REPORT 05000445/2022004 AND

05000446/2022004) AND REQUEST FOR INFORMATION

Dear Mr. Peters:

During the week of October 24, 2022, two inspectors from the U.S. Nuclear Regulatory

Commissions (NRC) Region IV office will perform the baseline biennial requalification

inspection at Comanche Peak Nuclear Power Plant, using NRC Inspection

Procedure 71111.11B, Licensed Operator Requalification Program.

Experience has shown that this inspection is a resource intensive inspection both for the NRC

inspectors and your staff. In order to minimize the impact to your onsite resources and to

ensure a productive inspection, we have enclosed a request for documents needed for this

inspection. These documents have been divided into three groups:

The first group (Section A of the enclosure) identifies information to be provided prior to

the inspection to ensure that the inspectors are adequately prepared.

The second group (Section B of the enclosure) identifies the information the inspectors

will need upon arrival at the site.

The third group (Section C of this enclosure) identifies the items which are necessary to

close out the inspection and are usually sent a few weeks after the team has left the site.

It is important that all of these documents are up to date and complete in order to minimize the

number of additional documents requested during the preparation and/or the onsite portions of

the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Mr. Terry Jank of your training organization.

Our inspection dates are subject to change based on your updated schedule of examination

activities. If there are any questions about this inspection or the material requested, please

contact the lead inspector, Bryan Bergeon at (817) 200-1415 (Bryan.Bergeon@nrc.gov).

K. Peters 2

PAPERWORK REDUCTION ACT STATEMENT

This letter contains mandatory information collections that are subject to the Paperwork

Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)

approved these information collections (approval number 3150-0011). Send comments

regarding this information collection to the Information Services Branch, Office of the Chief

Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,

DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office

of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and

Budget, Washington, DC 20503.

Public Protection Notification

The NRC may not conduct nor sponsor, and a person is not required to respond to, a request

for information or an information collection requirement unless the requesting document

displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter

and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Heather J. Gepford, Chief

Operations Branch

Division of Operating Reactor Safety

Docket No. 50-445; 50-446

License No. NPF-87; NPF-89

Enclosure:

Biennial Requalification Inspection

Request for Information

Signed by Gepford, Heather

on 08/17/22

ML22228A094

OFFICE OE:OB C:OB

NAME BBergeon HGepford

SIGNATURE BAB HJG

DATE 08/16/2022 08/17/2022

Initial Request for Information

Biennial Requalification Inspection

Comanche Peak Nuclear Power Plant

Inspection Report: 5000445/2022004; 5000446/2022004

Inspection Dates: October 24, 2022 - October 28, 2022

Inspection Procedure: IP 71111.11B, Licensed Operator Requalification

Program

Lead Inspector: Bryan Bergeon, Operations Engineer

A. The following information is requested in order to support inspection preparation

activities. These items are listed by section as they appear in the inspection module

(i.e. 03.04a, 03.04b, etc.). Requested materials should be sent in an electronic format

on CD/DVD in order to arrive at the Region IV office no later than October 10, 2022;

OR uploaded to the NRCs secure Box application no later than October 10, 2022.

CD/DVD to: US Nuclear Regulatory Commission, Region IV

ATTN: Bryan Bergeon / Heather Gepford

1600 E. Lamar Blvd

Arlington, TX 76011

General Requests:

List of licensed operators (SRO & RO) by crew (operating & staff)

Training and Operations Department organization charts (with qualified LOR

evaluators identified)

Procedures that identify process for revising and maintaining LO continuing training

program up to date

List of outstanding LOR program changes

List of plant events and industry operating experience incorporated into LOR

program since last BRQ

Audits and/or self-assessment reports addressing the licensed operator

requalification training program

Last 2 years of simulator review committee (or equivalent) meeting minutes

Last 2 years of Curriculum Review Committee (or equivalent) meeting minutes

A summary report of all condition reports related to operator actions/errors in the

control room

Any revised requalification training that was based on licensed operator performance

issues

03.04a: Biennial Requalification Written Examinations

The current and approved biennial written examination schedule

The current requalification cycle written examination results for both SRO & RO that

have already been administered up to the week prior to the inspection team arrival

onsite.

All written examinations that have been approved for administration up to and

including the week before the inspection team is onsite. This will need to have

adequate password protection or double envelope protection if mailed via regular

mail per NUREG-1021.

The current requalification cycle examination methodology (sample plan)

03.04b: Annual Requalification Operating Tests

The schedule for the operating tests (JPMs & scenarios) to be given the week of

October 24, 2022

The operating tests (JPMs & scenarios) (password protected and provide separately

via telephone at later date) to be given the week of October 24, 2022

Current requalification cycle operating tests (SRO & RO) and results up to the week

prior to the inspection team arrival onsite

All 2021 NRC required annual operating tests

Current requalification cycle operating test methodology (sample plan)

03.04c: Administration of an Annual Requalification Operating Test

All procedures used to administer the annual operating test

All procedures used to assess operator performance

All procedures that describe conduct of simulator training

All procedures used to test, operate, and maintain the simulator

03.04d: Requalification Examination Security

Submit any tracking tools that you use as a means to prevent excessive overlap on

the written examinations and also meet the intent of sampling all required topics on a

periodic basis.

Submit any tracking tools that you use as a means to prevent excessive overlap on

the operating tests and also meet the intent of sampling all required malfunctions

(including major events, instrument/component malfunctions, TS calls, etc.) on a

periodic basis.

All procedures that describe examination security, including procedures used to

develop the examinations that include guidelines on overlap between examinations

in current exam cycle tests and prior year examinations

List of all condition reports since the last biennial requalification inspection related to

examination security and overlap

03.04e: Remedial Training and Re-Examinations

List of remedial training conducted or planned since last requalification exam

(includes training provided to operators to enable passing requalification exam and

training provided to correct generic or individual weaknesses observed during

previous requalification exam cycle)

Remediation plans (lesson plans, reference materials, and attendance

documentation)

03.04f: Operator License Conditions

All procedures and program documentation for maintaining active operator licenses,

tracking training attendance, and ensuring medical fitness of licensed operators

All procedures and associated documentation that supports reactivation of any

SRO/RO license (operating or staff crew) since the last biennial inspection

03.04g: Control Room Simulator

All simulator management and configuration procedures if not already provided

Simulator discrepancy report summary list for all open discrepancy reports and

summary list for those items closed between October 1, 2020 and October 10, 2022

Primary parameters tested in order to verify core physics parameters (such as

moderator temperature coefficient, integral rod worth)). The applicable reference

graphs from the plant physics data book (electronic or other means as available)

should also be included as well as the test procedures used and the acceptance

criteria with results.

All simulator modification packages that are on hold, delayed, or not completed in the

last 2 years

A list of simulator modification packages completed in the last two-year window

B. The following information is requested in order to support the onsite inspection

activities. Requested materials should be available to the inspection team, either

electronically or hardcopy, upon site arrival on October 24, 2022.

03.03: Requalification Exam Results / 03.04a and 03.04b: Biennial Requalification Written

Exam and Annual Requalification Operating Tests Quality

All operating tests (JPMs & scenarios) to be given in all subsequent weeks after

onsite week, if available

All results up to the day the team leaves the site

03.04f: Conformance with Operator License Conditions

Access to licensed operators records (operating and staff crews)

Access to licensed operators training attendance records

Access to licensed operators medical records

03.04g: Control Room Simulator Performance

Simulator discrepancies from October 1, 2020 to October 24, 2022. This should

include all open and closed simulator discrepancy reports, including the

documentation/justification for closure.

Acceptance test documentation, including hardware and software model revisions at

the time of acceptance (as available)

Documentation that validates current models, including the thermal-hydraulics and

neutronics models, to the actual plant

All current model deficiencies, including FSAR vs Design differences in the simulator

(any documentation on this)

Summary list of modifications from October 1, 2020 to October 24, 2022

Plant modifications (both hardware and software) completed on the simulator by due

date from October 1, 2020 to October 24, 2022

Simulator differences Lesson plan used in training (current to October 24, 2022)

The complete book of all simulator annual performance test packages (usually in a

single book but may be electronic or in single test packages), complete with all

transient tests, steady state tests, and malfunction tests. This should also include

the test procedures for each test, the acceptance criteria, and results. For each

transient test, the reference chart should be included or an equivalent subject matter

expert review versus the simulator results with a write-up for any differences beyond

the ANSI standard requirements.

All test packages used to verify core physics parameters (such as moderator

temperature coefficient and integral rod worth). The applicable reference graphs

from the plant physics data book (electronic or other means as available) should also

be included as well as the test procedures used and the acceptance criteria with

results.

All simulator tests, configuration management, and related documents available in

the room for inspectors to review. This includes training needs analysis packages,

simulator review committee meeting minutes, etc.

Current copy of ANSI 3.5 standard you are committed to for simulator testing

C. Comanche Peak Nuclear Power Plant is required to send the final results summary

(see Table 1 below) and any remaining exams and operating tests that have not been

reviewed to the regional office lead inspector for this inspection for final review and

comparison against the Significance Determination Tools in order to communicate

the exit results for the inspection.

TABLE 1: EXAMINATION RESULTS

1. Total number of licensed operators.

2. Number of licensed operators administered a requalification

examination required by 10 CFR 55.59(a).

3. Number of individual licensed operators who failed any portion of a

requalification examination (written, JPM, or individual simulator

scenario failures).

4. Divide line 3 by line 2 to obtain the individual requalification

examination failure rate. Line 3/Line 2.  %

5. Number of crews administered simulator scenarios as part of a

requalification examination required by 10 CFR 55.59(a).

6. Number of crews who performed unsatisfactorily on the

simulator scenarios.

7. Divide line 6 by line 5 to obtain the crew simulator scenario

failure rate. Line 6/Line 5.  %