ML16120A596: Difference between revisions
StriderTol (talk | contribs) Created page by program invented by StriderTol |
StriderTol (talk | contribs) StriderTol Bot change |
||
| (3 intermediate revisions by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML16120A596 | | number = ML16120A596 | ||
| issue date = 04/18/2016 | | issue date = 04/18/2016 | ||
| title = | | title = Final Safety Analysis Report Update, Revision 32, Chapter 9 - Auxiliary Systems - Figures | ||
| author name = | | author name = | ||
| author affiliation = Entergy Nuclear Operations, Inc | | author affiliation = Entergy Nuclear Operations, Inc | ||
| Line 14: | Line 14: | ||
| document type = Drawing, Updated Final Safety Analysis Report (UFSAR) | | document type = Drawing, Updated Final Safety Analysis Report (UFSAR) | ||
| page count = 40 | | page count = 40 | ||
}} | }} | ||
=Text= | |||
{{#Wiki_filter:FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1 Revision 32 SYSTEM DIAGRAM SERVICE WATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1B Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER, SCREEN STRUCTURE AND CHLORINATOR | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-2 Revision 32 PIPING & INSTRUMENT DIAGRAM SHIELD COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-3 Revision 26 NORMAL OPERATING CONDITIONS COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-4 Revision 26 NORMAL OPERATING CONDITIONS MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-5 Revision 26 BOUNDING DESIGN COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-6 Revision 26 BOUNDING DESIGN CONDITIONS AND MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 1 Revision 30 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 2 Revision 27 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-8 Revision 32 PIPING & INSTRUMENT DIAGRAM SPENT FUEL POOL COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE AND INSTRUMENT AIR SYSTEMS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM MISCELLANEOUS GAS SUPPLY SYSTEMS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1A Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 2 Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-12 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-13 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER STEAM SUPPLY | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 1 Revision 28 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, SWITCHGEAR AND CABLE SPREADING ROOMS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTAINMENT BUILDING | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, RADWASTE AREA | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 4 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, MISCELLANEOUS BUILDINGS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 5 Revision 27 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 6 Revision 25 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 7 Revision 30 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 8 Revision 30 HEATING AND VENTILATION AIR FLOW DIAGRAM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 9 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND COOLING AUXILIARY BUILDING ADDITION | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-15 Revision 23 PIPING & INSTRUMENT DIAGRAM FLUID SYSTEM DIAGRAM POST ACCIDENT SAMPLE MONITOR SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-16 Revision 32 PIPING & INSTRUMENT DIAGRAM GAS ANALYZING SYSTEMS (CONTAINMENT HYDROGEN) | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-17 Revision 25 MONITORING AND SAMPLING SYSTEMS (RADWASTE ADDITION) | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1B Revision 31 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-19 Revision 21 BORON CONCENTRATION VS CORE LIFETIME | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-20 Revision 31 PALISADES PLANT SPENT FUEL STORAGE RACK ARRANGEMENT NEW FUEL ELEVATOR AND INSPECTION STAND 3.11 8 x 8** | |||
5 x 10 896*** | |||
* MAY ALSO BE USED FOR CONTROL ROD STORAGE | |||
**NOMINAL, SOME SPACES NOT INSTALLED FOR NFE AND INSPECTION STAND | |||
***PHYSICAL SPOTS. ONLY 892 LICENSED LOCATIONS DUE TO LACK OF ABILITY TO ACCESS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1 Revision 32 SYSTEM DIAGRAM SERVICE WATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1B Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER, SCREEN STRUCTURE AND CHLORINATOR | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-2 Revision 32 PIPING & INSTRUMENT DIAGRAM SHIELD COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-3 Revision 26 NORMAL OPERATING CONDITIONS COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-4 Revision 26 NORMAL OPERATING CONDITIONS MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-5 Revision 26 BOUNDING DESIGN COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-6 Revision 26 BOUNDING DESIGN CONDITIONS AND MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 1 Revision 30 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 2 Revision 27 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-8 Revision 32 PIPING & INSTRUMENT DIAGRAM SPENT FUEL POOL COOLING SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE AND INSTRUMENT AIR SYSTEMS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM MISCELLANEOUS GAS SUPPLY SYSTEMS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1A Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 2 Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-12 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-13 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER STEAM SUPPLY | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 1 Revision 28 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, SWITCHGEAR AND CABLE SPREADING ROOMS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTAINMENT BUILDING | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, RADWASTE AREA | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 4 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, MISCELLANEOUS BUILDINGS | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 5 Revision 27 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 6 Revision 25 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 7 Revision 30 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 8 Revision 30 HEATING AND VENTILATION AIR FLOW DIAGRAM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 9 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND COOLING AUXILIARY BUILDING ADDITION | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-15 Revision 23 PIPING & INSTRUMENT DIAGRAM FLUID SYSTEM DIAGRAM POST ACCIDENT SAMPLE MONITOR SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-16 Revision 32 PIPING & INSTRUMENT DIAGRAM GAS ANALYZING SYSTEMS (CONTAINMENT HYDROGEN) | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-17 Revision 25 MONITORING AND SAMPLING SYSTEMS (RADWASTE ADDITION) | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1B Revision 31 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-19 Revision 21 BORON CONCENTRATION VS CORE LIFETIME | |||
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-20 Revision 31 PALISADES PLANT SPENT FUEL STORAGE RACK ARRANGEMENT NEW FUEL ELEVATOR AND INSPECTION STAND 3.11 8 x 8** | |||
5 x 10 896*** | |||
* MAY ALSO BE USED FOR CONTROL ROD STORAGE | |||
**NOMINAL, SOME SPACES NOT INSTALLED FOR NFE AND INSPECTION STAND | |||
***PHYSICAL SPOTS. ONLY 892 LICENSED LOCATIONS DUE TO LACK OF ABILITY TO ACCESS}} | |||
Latest revision as of 00:35, 10 January 2025
| ML16120A596 | |
| Person / Time | |
|---|---|
| Site: | Palisades |
| Issue date: | 04/18/2016 |
| From: | Entergy Nuclear Operations |
| To: | Office of Nuclear Reactor Regulation |
| Shared Package | |
| ML16120A302 | List:
|
| References | |
| PNP 2016-015 | |
| Download: ML16120A596 (40) | |
Text
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1 Revision 32 SYSTEM DIAGRAM SERVICE WATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1B Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER, SCREEN STRUCTURE AND CHLORINATOR
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-2 Revision 32 PIPING & INSTRUMENT DIAGRAM SHIELD COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-3 Revision 26 NORMAL OPERATING CONDITIONS COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-4 Revision 26 NORMAL OPERATING CONDITIONS MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-5 Revision 26 BOUNDING DESIGN COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-6 Revision 26 BOUNDING DESIGN CONDITIONS AND MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 1 Revision 30 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 2 Revision 27 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-8 Revision 32 PIPING & INSTRUMENT DIAGRAM SPENT FUEL POOL COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE AND INSTRUMENT AIR SYSTEMS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM MISCELLANEOUS GAS SUPPLY SYSTEMS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1A Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 2 Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-12 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-13 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER STEAM SUPPLY
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 1 Revision 28 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, SWITCHGEAR AND CABLE SPREADING ROOMS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTAINMENT BUILDING
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, RADWASTE AREA
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 4 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, MISCELLANEOUS BUILDINGS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 5 Revision 27 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 6 Revision 25 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 7 Revision 30 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 8 Revision 30 HEATING AND VENTILATION AIR FLOW DIAGRAM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 9 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND COOLING AUXILIARY BUILDING ADDITION
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-15 Revision 23 PIPING & INSTRUMENT DIAGRAM FLUID SYSTEM DIAGRAM POST ACCIDENT SAMPLE MONITOR SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-16 Revision 32 PIPING & INSTRUMENT DIAGRAM GAS ANALYZING SYSTEMS (CONTAINMENT HYDROGEN)
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-17 Revision 25 MONITORING AND SAMPLING SYSTEMS (RADWASTE ADDITION)
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1B Revision 31 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-19 Revision 21 BORON CONCENTRATION VS CORE LIFETIME
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-20 Revision 31 PALISADES PLANT SPENT FUEL STORAGE RACK ARRANGEMENT NEW FUEL ELEVATOR AND INSPECTION STAND 3.11 8 x 8**
5 x 10 896***
- MAY ALSO BE USED FOR CONTROL ROD STORAGE
- NOMINAL, SOME SPACES NOT INSTALLED FOR NFE AND INSPECTION STAND
- PHYSICAL SPOTS. ONLY 892 LICENSED LOCATIONS DUE TO LACK OF ABILITY TO ACCESS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1 Revision 32 SYSTEM DIAGRAM SERVICE WATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 1B Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-1, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE WATER, SCREEN STRUCTURE AND CHLORINATOR
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-2 Revision 32 PIPING & INSTRUMENT DIAGRAM SHIELD COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-3 Revision 26 NORMAL OPERATING CONDITIONS COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-4 Revision 26 NORMAL OPERATING CONDITIONS MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-5 Revision 26 BOUNDING DESIGN COOLING COIL CENTERLINE Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-6 Revision 26 BOUNDING DESIGN CONDITIONS AND MID-SPAN OF TWO COOLING COILS Structural Concrete Sacrificial Concrete
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 1 Revision 30 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 2 Revision 27 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-7, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM COMPONENT COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-8 Revision 32 PIPING & INSTRUMENT DIAGRAM SPENT FUEL POOL COOLING SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM SERVICE AND INSTRUMENT AIR SYSTEMS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-9, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM MISCELLANEOUS GAS SUPPLY SYSTEMS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 1A Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-10, SHT 2 Revision 30 PIPING & INSTRUMENT DIAGRAM HIGH PRESSURE AIR OPERATED VALVES
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-11, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM FIRE PROTECTION SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-12 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-13 Revision 32 PIPING & INSTRUMENT DIAGRAM AUXILIARY FEEDWATER STEAM SUPPLY
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 1 Revision 28 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, SWITCHGEAR AND CABLE SPREADING ROOMS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 2 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTAINMENT BUILDING
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 3 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, RADWASTE AREA
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 4 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, MISCELLANEOUS BUILDINGS
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 5 Revision 27 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 6 Revision 25 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 7 Revision 30 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND AIR CONDITIONING, CONTROL ROOM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 8 Revision 30 HEATING AND VENTILATION AIR FLOW DIAGRAM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-14, SHT 9 Revision 32 PIPING & INSTRUMENT DIAGRAM HEATING, VENTILATION AND COOLING AUXILIARY BUILDING ADDITION
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-15 Revision 23 PIPING & INSTRUMENT DIAGRAM FLUID SYSTEM DIAGRAM POST ACCIDENT SAMPLE MONITOR SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-16 Revision 32 PIPING & INSTRUMENT DIAGRAM GAS ANALYZING SYSTEMS (CONTAINMENT HYDROGEN)
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-17 Revision 25 MONITORING AND SAMPLING SYSTEMS (RADWASTE ADDITION)
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1 Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1A Revision 32 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-18, SHT 1B Revision 31 PIPING & INSTRUMENT DIAGRAM CHEMICAL AND VOLUME CONTROL SYSTEM
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-19 Revision 21 BORON CONCENTRATION VS CORE LIFETIME
FSAR CHAPTER 9 - AUXILIARY SYSTEMS FIGURE 9-20 Revision 31 PALISADES PLANT SPENT FUEL STORAGE RACK ARRANGEMENT NEW FUEL ELEVATOR AND INSPECTION STAND 3.11 8 x 8**
5 x 10 896***
- MAY ALSO BE USED FOR CONTROL ROD STORAGE
- NOMINAL, SOME SPACES NOT INSTALLED FOR NFE AND INSPECTION STAND
- PHYSICAL SPOTS. ONLY 892 LICENSED LOCATIONS DUE TO LACK OF ABILITY TO ACCESS