ML080720471: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 2: Line 2:
| number = ML080720471
| number = ML080720471
| issue date = 03/18/2008
| issue date = 03/18/2008
| title = 04/08/2008 Notice of Licensee Meeting - Calvert Cliffs Nuclear Power Plant  Units 1 and 2, Annual Assessment Meeting for Cy 2007
| title = Notice of Licensee Meeting - Calvert Cliffs Nuclear Power Plant  Units 1 and 2, Annual Assessment Meeting for Cy 2007
| author name = Dentel G
| author name = Dentel G
| author affiliation = NRC/RGN-I/DRP/PB1
| author affiliation = NRC/RGN-I/DRP/PB1
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:March 18, 2008 MN No. 08-006 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING  
{{#Wiki_filter:March 18, 2008 MN No. 08-006 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING Licensee:            Constellation Energy, LLC Facility:            Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Docket No:            50-317 and 50-318 Date/Time:            April 8, 2008, at 2:00 pm Location:            Constellation Energy Joint Information Center 100 Skipjack Road Prince Frederick, MD 20678


Licensee: Constellation Energy, LLC 
==Purpose:==
 
The NRC requested an Annual Assessment Meeting with Constellation management to discuss the NRCs assessment of the safety performance of Calvert Cliffs Nuclear Power Plant for 2007. The NRCs assessment is documented in a letter dated March 3, 2008.
Facility: Calvert Cliffs Nuclear Power Plant, Units 1 and 2
Attendees:
 
NRC:         G. Dentel, Chief, Projects Branch 1, Division of Reactor Projects, Region I S. Kennedy, Senior Resident Inspector, Calvert Cliffs M. Davis, Resident Inspector, Calvert Cliffs J. Hawkins, Senior Project Engineer, Division of Reactor Projects Licensee:    J. Spina, Vice President D. Bauder, Plant General Manager E. Dean, Manager, Nuclear Operations M. Flaherty, Manager, Engineering Services Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
Docket No: 50-317 and 50-318
NRCs assessment letter can be found in ADAMS with an Accession Number of ML080610013.
This meeting notice with the enclosed meeting agenda is located in ADAMS with Accession Number ML080720471. ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.


Date/Time:  April 8, 2008, at 2:00 pm
2 Additional information relative to the NRCs Annual Assessment process and the safety performance of Calvert Cliffs Nuclear Power Plant can be found on the NRC Web Site at:
 
Location:  Constellation Energy Joint Information Center 100 Skipjack Road Prince Frederick, MD  20678
 
Purpose: The NRC requested an Annual Assessment Meeting with Constellation management to discuss the NRC's assessment of the safety performance of Calvert Cliffs Nuclear Power Plant for 2007. The NRC's assessment is documented in a letter dated March 3, 2008.
 
Attendees: NRC:  G. Dentel, Chief, Projects Branch 1, Division of Reactor Projects, Region I S. Kennedy, Senior Resident Inspector, Calvert Cliffs M. Davis, Resident Inspector, Calvert Cliffs J. Hawkins, Senior Project Engineer, Division of Reactor Projects
 
Licensee: J. Spina, Vice President D. Bauder, Plant General Manager E. Dean, Manager, Nuclear Operations M. Flaherty, Manager, Engineering Services
 
Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
 
NRC's assessment letter can be found in ADAMS with an Accession Number of ML080610013.
This meeting notice with the enclosed meeting agenda is located in ADAMS with Accession Number ML080720471. ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.
2Additional information relative to the NRC's Annual Assessment process and the safety performance of Calvert Cliffs Nuclear Power Plant can be found on the NRC Web Site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.
Meeting


Meeting Contact: Glenn T. Dentel, Chief - Projects Branch 1 (610) 337-5233 E-mail: GTD@nrc.gov
==Contact:==
 
Glenn T. Dentel, Chief - Projects Branch 1 (610) 337-5233 E-mail: GTD@nrc.gov
$ Handicapped persons requiring assistance to attend or participate in the meeting shall make   their requests known to the meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by via telephone to the NRC meeting contact.
$       Handicapped persons requiring assistance to attend or participate in the meeting shall make their requests known to the meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by via telephone to the NRC meeting contact.
Approved by: ___/RA/_______________                         Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects cc w/encl: M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer President, Calvert County Board of Commissioners C. W. Fleming, Esq., Senior Counsel, Nuclear Generation Group J. Gaines, Director, Licensing Director, Nuclear Regulatory Matters R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center S. Pattison, SLO (2) 3  Agenda NRC's Annual Assessment Meeting
Approved by: ___/RA/_______________
 
Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects cc w/encl:
Calvert Cliffs Nuclear Power Plant
M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer President, Calvert County Board of Commissioners C. W. Fleming, Esq., Senior Counsel, Nuclear Generation Group J. Gaines, Director, Licensing Director, Nuclear Regulatory Matters R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center S. Pattison, SLO (2)
 
Introduction  ...........................................................................................NRC (3 minutes)
 
Review of Reactor Oversight Process....................................................NRC (5 minutes)
 
National Summary of Plant Performance...............................................NRC (7 minutes)
Discussion of Calvert Cliffs Performance.............................................NRC (15 minutes)
 
Constellation's Response and Remarks..................................Constellation (15 minutes)
 
Closing Remarks....................................................................................NRC (5 minutes)
Short Break.....................................................................................................(5 minutes)
 
NRC to address public questions ....................NRC/Members of the Public (as needed) 3 Agenda NRC=s Annual Assessment Meeting Calvert Cliffs Nuclear Power Plant
 
Introduction  .................................................................................................................
......................................................NRC (3 minutes)
 
Review of Reactor Oversight Process............................................................................................
...................................NRC (5 minutes)
 
National Summary of Plant Perf ormanc e..........................................................................................
.................................NRC (7 minutes)
 
Discussion of Calvert Cliffs Performance.......................................................................................
.................................NRC (15 minutes)
 
Constellation's Response and Re marks.............................................................................................................Constellation (15 minutes)
 
Closing Remarks................................................................................................................
................................................NRC (5 minutes)
 
Short Break..................................................................................................................................................................................(5 minutes)
 
NRC to address public questions
...............................................................................................NRC/Members of the Public (as needed)  


Distribution w/encl: (VIA E-MAIL)  Executive Director for Operations, OEDO (RIDSEDOMAILCENTER RESOURCES)
3 Agenda NRCs Annual Assessment Meeting Calvert Cliffs Nuclear Power Plant Introduction ........................................................................................... NRC (3 minutes)
Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER RESOURCES)
Review of Reactor Oversight Process .................................................... NRC (5 minutes)
Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)
National Summary of Plant Performance ............................................... NRC (7 minutes)
Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD)
Discussion of Calvert Cliffs Performance ............................................. NRC (15 minutes)
Director, Division of Regulatory Improvement Programs, NRR (RIDSNRRDRIP)
Constellation's Response and Remarks.................................. Constellation (15 minutes)
Director, Division of Inspection Program Management, NRR (RIDSNRRDIPM)
Closing Remarks .................................................................................... NRC (5 minutes)
Director, Division of Licensing Project Management, NRR (RIDSNRRDLPM)
Short Break ..................................................................................................... (5 minutes)
Project Directorate I-1 (PD1/2), NRR (RIDSNRRDIPMLPDI)
NRC to address public questions .................... NRC/Members of the Public (as needed)
Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)
S. Collins, RA M. Dapas, DRA G. West, RI OEDO  J. Lubinski, NRR M. Kowal, NRR D. Pickett, PM, NRR A. Muniz, PM, NRR G. Dentel, DRP B. Bickett, DRP S. Kennedy, DRP, Senior Resident Inspector M. Davis, DRP, Resident Inspector C. Newgent, DRP, Resident OA D. Roberts, DRS M. Gamberoni, DRS D. Screnci, PAO N. Sheehan, PAO N. McNamara, SLO M. McLaughlin, SLO Region I Docket Room (w/concurrences)
Regional Administrator Secretary, RI Deputy Regional Administrator Secretary, RI DRP Division Secretary, RI DRS Division Secretary, RI DNMS Division Secretary, RI DRM Division Secretary, RI Region I Receptionist PMNS SUNSI Review Complete:      GTD            (Reviewer
=s Initials)  DOCUMENT NAME:T:\DRP\BRANCH1\ROP ASSESSMENT PROCESS DOCUMENTS\2008 ROP EOC STUFF\CALVERT EOC STUFF + ATTACHMENTS\CALVERT CLIFFS MEETING NOTICE 2008.DOC After declaring this document AAn Official Agency Record
@ it will be released to the Public. To receive a copy of this document, indicate in the box: 
" C" = Copy without attachment/enclosure  " E" = Copy with attachment/enclosure  " N" = No copy  OFFICE  RI/DRP    RI/DRP    NAME  *BBickett/KMT For/
GDentel/GTD


DATE 03/18/08 03/18/08
3 Agenda NRC=s Annual Assessment Meeting Calvert Cliffs Nuclear Power Plant Introduction ....................................................................................................................................................................... NRC (3 minutes)
* By telecon OFFICIAL RECORD COPY}}
Review of Reactor Oversight Process ............................................................................................................................... NRC (5 minutes)
National Summary of Plant Performance........................................................................................................................... NRC (7 minutes)
Discussion of Calvert Cliffs Performance ........................................................................................................................ NRC (15 minutes)
Constellation's Response and Remarks .............................................................................................................Constellation (15 minutes)
Closing Remarks ................................................................................................................................................................ NRC (5 minutes)
Short Break .................................................................................................................................................................................. (5 minutes)
NRC to address public questions ............................................................................................... NRC/Members of the Public (as needed)
J. Lubinski, NRR Distribution w/encl: (VIA E-MAIL)                                                                            M. Kowal, NRR Executive Director for Operations, OEDO                                                                      D. Pickett, PM, NRR (RIDSEDOMAILCENTER RESOURCES)                                                                                A. Muniz, PM, NRR Deputy Executive Director for Reactor Programs, OEDO                                                        G. Dentel, DRP (RIDSEDOMAILCENTER RESOURCES)                                                                                B. Bickett, DRP Director, Office of Nuclear Reactor Regulation, NRR                                                          S. Kennedy, DRP, Senior Resident Inspector (RIDSNRROD)                                                                                                  M. Davis, DRP, Resident Inspector Deputy Director, Office of Nuclear Reactor Regulation,                                                      C. Newgent, DRP, Resident OA NRR/ADPR (RIDSNRROD)                                                                                        D. Roberts, DRS Director, Division of Regulatory Improvement Programs,                                                      M. Gamberoni, DRS NRR (RIDSNRRDRIP)                                                                                            D. Screnci, PAO Director, Division of Inspection Program Management, NRR                                                    N. Sheehan, PAO (RIDSNRRDIPM)                                                                                                N. McNamara, SLO Director, Division of Licensing Project Management, NRR                                                      M. McLaughlin, SLO (RIDSNRRDLPM)                                                                                                Region I Docket Room (w/concurrences)
Project Directorate I-1 (PD1/2), NRR (RIDSNRRDIPMLPDI)                                                      Regional Administrator Secretary, RI Asst. General Counsel Materials Litigation and Enforcement,                                                  Deputy Regional Administrator Secretary, RI OGC (RIDSOGCMAILCENTER)                                                                                      DRP Division Secretary, RI S. Collins, RA                                                                                              DRS Division Secretary, RI M. Dapas, DRA                                                                                                DNMS Division Secretary, RI G. West, RI OEDO                                                                                            DRM Division Secretary, RI Region I Receptionist PMNS SUNSI Review Complete:                    GTD                (Reviewer=s Initials)
DOCUMENT NAME:T:\DRP\BRANCH1\ROP ASSESSMENT PROCESS DOCUMENTS\2008 ROP EOC STUFF\CALVERT EOC STUFF +
ATTACHMENTS\CALVERT CLIFFS MEETING NOTICE 2008.DOC After declaring this document AAn Official Agency Record@ it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" =
No copy OFFICE            RI/DRP                                              RI/DRP NAME              *BBickett/KMT For/                                  GDentel/GTD DATE             03/18/08                                           03/18/08
* By telecon                                                                 OFFICIAL RECORD COPY}}

Latest revision as of 07:49, 7 December 2019

Notice of Licensee Meeting - Calvert Cliffs Nuclear Power Plant Units 1 and 2, Annual Assessment Meeting for Cy 2007
ML080720471
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 03/18/2008
From: Glenn Dentel
Reactor Projects Branch 1
To:
Constellation Energy Nuclear Group
Dentel, G RGN-I/DRP/BR1/610-337-5233
References
Download: ML080720471 (4)


Text

March 18, 2008 MN No.08-006 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING Licensee: Constellation Energy, LLC Facility: Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Docket No: 50-317 and 50-318 Date/Time: April 8, 2008, at 2:00 pm Location: Constellation Energy Joint Information Center 100 Skipjack Road Prince Frederick, MD 20678

Purpose:

The NRC requested an Annual Assessment Meeting with Constellation management to discuss the NRCs assessment of the safety performance of Calvert Cliffs Nuclear Power Plant for 2007. The NRCs assessment is documented in a letter dated March 3, 2008.

Attendees:

NRC: G. Dentel, Chief, Projects Branch 1, Division of Reactor Projects, Region I S. Kennedy, Senior Resident Inspector, Calvert Cliffs M. Davis, Resident Inspector, Calvert Cliffs J. Hawkins, Senior Project Engineer, Division of Reactor Projects Licensee: J. Spina, Vice President D. Bauder, Plant General Manager E. Dean, Manager, Nuclear Operations M. Flaherty, Manager, Engineering Services Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

NRCs assessment letter can be found in ADAMS with an Accession Number of ML080610013.

This meeting notice with the enclosed meeting agenda is located in ADAMS with Accession Number ML080720471. ADAMS is accessible from the NRC Web Site at http://www.nrc.gov/reading-rm/adams.html.

2 Additional information relative to the NRCs Annual Assessment process and the safety performance of Calvert Cliffs Nuclear Power Plant can be found on the NRC Web Site at:

http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Meeting

Contact:

Glenn T. Dentel, Chief - Projects Branch 1 (610) 337-5233 E-mail: GTD@nrc.gov

$ Handicapped persons requiring assistance to attend or participate in the meeting shall make their requests known to the meeting contact no later than 2 business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by via telephone to the NRC meeting contact.

Approved by: ___/RA/_______________

Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects cc w/encl:

M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer President, Calvert County Board of Commissioners C. W. Fleming, Esq., Senior Counsel, Nuclear Generation Group J. Gaines, Director, Licensing Director, Nuclear Regulatory Matters R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center S. Pattison, SLO (2)

3 Agenda NRCs Annual Assessment Meeting Calvert Cliffs Nuclear Power Plant Introduction ........................................................................................... NRC (3 minutes)

Review of Reactor Oversight Process .................................................... NRC (5 minutes)

National Summary of Plant Performance ............................................... NRC (7 minutes)

Discussion of Calvert Cliffs Performance ............................................. NRC (15 minutes)

Constellation's Response and Remarks.................................. Constellation (15 minutes)

Closing Remarks .................................................................................... NRC (5 minutes)

Short Break ..................................................................................................... (5 minutes)

NRC to address public questions .................... NRC/Members of the Public (as needed)

3 Agenda NRC=s Annual Assessment Meeting Calvert Cliffs Nuclear Power Plant Introduction ....................................................................................................................................................................... NRC (3 minutes)

Review of Reactor Oversight Process ............................................................................................................................... NRC (5 minutes)

National Summary of Plant Performance........................................................................................................................... NRC (7 minutes)

Discussion of Calvert Cliffs Performance ........................................................................................................................ NRC (15 minutes)

Constellation's Response and Remarks .............................................................................................................Constellation (15 minutes)

Closing Remarks ................................................................................................................................................................ NRC (5 minutes)

Short Break .................................................................................................................................................................................. (5 minutes)

NRC to address public questions ............................................................................................... NRC/Members of the Public (as needed)

J. Lubinski, NRR Distribution w/encl: (VIA E-MAIL) M. Kowal, NRR Executive Director for Operations, OEDO D. Pickett, PM, NRR (RIDSEDOMAILCENTER RESOURCES) A. Muniz, PM, NRR Deputy Executive Director for Reactor Programs, OEDO G. Dentel, DRP (RIDSEDOMAILCENTER RESOURCES) B. Bickett, DRP Director, Office of Nuclear Reactor Regulation, NRR S. Kennedy, DRP, Senior Resident Inspector (RIDSNRROD) M. Davis, DRP, Resident Inspector Deputy Director, Office of Nuclear Reactor Regulation, C. Newgent, DRP, Resident OA NRR/ADPR (RIDSNRROD) D. Roberts, DRS Director, Division of Regulatory Improvement Programs, M. Gamberoni, DRS NRR (RIDSNRRDRIP) D. Screnci, PAO Director, Division of Inspection Program Management, NRR N. Sheehan, PAO (RIDSNRRDIPM) N. McNamara, SLO Director, Division of Licensing Project Management, NRR M. McLaughlin, SLO (RIDSNRRDLPM) Region I Docket Room (w/concurrences)

Project Directorate I-1 (PD1/2), NRR (RIDSNRRDIPMLPDI) Regional Administrator Secretary, RI Asst. General Counsel Materials Litigation and Enforcement, Deputy Regional Administrator Secretary, RI OGC (RIDSOGCMAILCENTER) DRP Division Secretary, RI S. Collins, RA DRS Division Secretary, RI M. Dapas, DRA DNMS Division Secretary, RI G. West, RI OEDO DRM Division Secretary, RI Region I Receptionist PMNS SUNSI Review Complete: GTD (Reviewer=s Initials)

DOCUMENT NAME:T:\DRP\BRANCH1\ROP ASSESSMENT PROCESS DOCUMENTS\2008 ROP EOC STUFF\CALVERT EOC STUFF +

ATTACHMENTS\CALVERT CLIFFS MEETING NOTICE 2008.DOC After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" =

No copy OFFICE RI/DRP RI/DRP NAME *BBickett/KMT For/ GDentel/GTD DATE 03/18/08 03/18/08

  • By telecon OFFICIAL RECORD COPY