4/21/2016 - Notice of Category 3 Public Meeting - Annual Assessment of Safety Performance at the Calvert Cliffs Nuclear Power Plant for 2015
ML16076A115
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 03/15/2016
From: Anthony Dimitriadis
Reactor Projects Branch 1
To:
Exelon Generation Co
Dimitriadis A
References
MN 16-011
Download: ML16076A115 (3)


Text

MN No.16-011 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF PUBLIC MEETING March 15, 2016 Licensee: Exelon Generation Company, LLC Facility: Calvert Cliffs Nuclear Power Plant Docket Nos: 50-317 and 50-318 Date/Time: April 21, 2016 5:00 p.m. - 6:30 p.m.

Location: Springhill Suites 75 Sherry Lane Prince Frederick, MD 20687

Purpose:

The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRCs assessment of safety performance at Calvert Cliffs Nuclear Power Plant for 2015, as described in the annual assessment letter dated March 2, 2016. The NRC will respond to questions on specific performance issues at the plant and our role in ensuring safe plant operations.

NRC Attendees: A. Dimitriadis, Chief, Projects Branch 1, Division of Reactor Projects R. Clagg, Senior Resident Inspector A. Rosebrook, Senior Project Engineer Public Participation: This is a Category 3 Meeting. The NRC staff will hold an open house to discuss Exelons performance at Calvert Cliffs Nuclear Power Plant during calendar year 2015. NRC staff will be available, in an informational setting, to answer questions from members of the public and discuss issues or concerns related to Calvert Cliffs Nuclear Power Plant.

Meeting

Contact:

Anthony Dimitriadis, Chief, Projects Branch 1 610-337-6953 E-mail: Anthony.Dimitriadis@nrc.gov The NRCs annual assessment letter regarding performance at Calvert Cliffs Nuclear Power Plant during 2015 can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession Number ML16061A169. ADAMS is accessible from the NRC website at: http://www.nrc.gov/reading-rm/adams.html.

Additional information relative to the NRCs annual assessment process and the safety performance of Calvert Cliffs Nuclear Power Plant can be found on the NRCs website at:

http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

2 The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC website, http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html, and contains information regarding visitors and security.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in this meeting, or need the meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting.

Attendance by other NRC personnel at this meeting should be made known by April 19, 2016, via telephone to the NRC meeting contact.

Meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances.

Please confirm the meeting schedule on the NRC website under public meetings.

Approved by: /RA/

Anthony Dimitriadis, Chief Projects Branch 1 Division of Reactor Projects cc: Distribution via ListServ

ML16076A115 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME ARosebrook/AAR ADimitriadis/AD DATE 3/15/16 3/15/16 MN No.16-011 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF PUBLIC MEETING March 15, 2016 Licensee: Exelon Generation Company, LLC Facility: Calvert Cliffs Nuclear Power Plant Docket Nos: 50-317 and 50-318 Date/Time: April 21, 2016 5:00 p.m. - 6:30 p.m.

Location: Springhill Suites 75 Sherry Lane Prince Frederick, MD 20687

Purpose:

The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRCs assessment of safety performance at Calvert Cliffs Nuclear Power Plant for 2015, as described in the annual assessment letter dated March 2, 2016. The NRC will respond to questions on specific performance issues at the plant and our role in ensuring safe plant operations.

NRC Attendees: A. Dimitriadis, Chief, Projects Branch 1, Division of Reactor Projects R. Clagg, Senior Resident Inspector A. Rosebrook, Senior Project Engineer Public Participation: This is a Category 3 Meeting. The NRC staff will hold an open house to discuss Exelons performance at Calvert Cliffs Nuclear Power Plant during calendar year 2015. NRC staff will be available, in an informational setting, to answer questions from members of the public and discuss issues or concerns related to Calvert Cliffs Nuclear Power Plant.

Meeting

Contact:

Anthony Dimitriadis, Chief, Projects Branch 1 610-337-6953 E-mail: Anthony.Dimitriadis@nrc.gov The NRCs annual assessment letter regarding performance at Calvert Cliffs Nuclear Power Plant during 2015 can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession Number ML16061A169. ADAMS is accessible from the NRC website at: http://www.nrc.gov/reading-rm/adams.html.

Additional information relative to the NRCs annual assessment process and the safety performance of Calvert Cliffs Nuclear Power Plant can be found on the NRCs website at:

http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

2 The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC website, http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html, and contains information regarding visitors and security.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in this meeting, or need the meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis. Persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting.

Attendance by other NRC personnel at this meeting should be made known by April 19, 2016, via telephone to the NRC meeting contact.

Meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances.

Please confirm the meeting schedule on the NRC website under public meetings.

Approved by: /RA/

Anthony Dimitriadis, Chief Projects Branch 1 Division of Reactor Projects cc: Distribution via ListServ

ML16076A115 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME ARosebrook/AAR ADimitriadis/AD DATE 3/15/16 3/15/16