ML082730908: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:Exelon Nuclear 200 Exelon Way Kennett Square, PA 19348 September 29, 2008 www.exeloncorp.com Nuclear 10 CFR 50.55a U.S.Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos.NPF-39 and NPF-85 NRC Docket Nos.50-352 and 50-353  
{{#Wiki_filter:Exelon Nuclear                       www.exeloncorp.com 200 Exelon Way                                                                                 Nuclear Kennett Square, PA 19348 10 CFR 50.55a September 29, 2008 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353


==Subject:==
==Subject:==
Relief Request RR-36 Associated with the Second Inservice Inspection (lSI)Interval  
Relief Request RR-36 Associated with the Second Inservice Inspection (lSI) Interval


==References:==
==References:==
: 1)    Letter from P. B. Cowan (Exelon Generation Company, LLC) to U. S.
Nuclear Regulatory Commission, "Submittal of Relief Requests Associated with the Second Inservice Inspection (lSI) Interval," dated January 28, 2008
: 2)    Letter from P. J. Bamford (U. S. Nuclear Regulatory Commission) to C. G. Pardee (Exelon Generation Company, LLC), "Limerick Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding Relief Requests Associated with the Second Inservice Inspection Interval," dated August 8,2008
: 3)    Letter from P. B. Cowan (Exelon Generation Company, LLC) to U. S.
Nuclear Regulatory Commission, "Response to Request for Additional Information Concerning Relief Requests Associated with the Second Inservice Inspection (lSI) Interval," dated September 8,2008 In the Reference 1 letter, in accordance with 10 CFR 50.55a, "Codes and standards," Exelon Generation Company, LLC (EGC), requested relief from the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components. These reliefs apply to the second 10-year interval II inservice inspection program, which concluded on January 31,2007.


1)Letter from P.B.Cowan (Exelon Generation Company, LLC)to U.S.Nuclear Regulatory Commission,"Submittal of Relief Requests Associated with the Second Inservice Inspection (lSI)Interval," dated January 28, 2008 2)Letter from P.J.Bamford (U.S.Nuclear Regulatory Commission) to C.G.Pardee (Exelon Generation Company, LLC),"Limerick Generating Station, Unit Nos.1 and2-Request for Additional Information Regarding Relief Requests Associated with the Second Inservice Inspection Interval," dated August 8,2008 3)Letter from P.B.Cowan (Exelon Generation Company, LLC)to U.S.Nuclear Regulatory Commission,"Response to Request for Additional I nformation Concerning Relief Requests Associated with the Second Inservice Inspection (lSI)Interval," dated September 8,2008 In the Reference 1 letter, in accordance with 10 CFR 50.55a,"Codes and standards," Exelon Generation Company, LLC (EGC), requested relief from the American Society of Mechanical Engineers(ASME)Boiler and Pressure Vessel Code, Section XI,"Rules for Inservice Inspection of Nuclear Power Plant Components.
Relief Request RR-36 Associated with the Second Inservice Inspection (lSI) Interval September 29, 2008 Page 2 Based on further discussions with the NRC, EGC hereby withdraws RR-36. The remainder of the relief requests in the Reference 1 submittal are not affected by this letter.
II These reliefs apply to the second 10-year interval inservice inspection program, which concluded on January 31,2007.
No commitments are contained in this letter.
Relief Request RR-36 Associated with the Second Inservice Inspection (lSI)Interval September 29, 2008 Page 2 Based on further discussions with the NRC, EGC hereby withdraws RR-36.The remainder of the relief requests in the Reference 1 submittal arenotaffected by this letter.No commitments are contained in this letter.Should you have any questions concerning this letter, please contact Tom Loomis at (610)5510.Respectfully, Pamela B.Cowan Director-Licensing&Regulatory Affairs Exelon Generation Company, LLC cc: S.J.Collins, Regional Administrator, Region I, USNRC E.M.DiPaolo, USNRC Senior Resident Inspector, LGS P.Bamford, Project Manager[LGS]USNRC}}
Should you have any questions concerning this letter, please contact Tom Loomis at (610) 765-5510.
Respectfully, 9;1)(~
Pamela B. Cowan Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC cc:     S. J. Collins, Regional Administrator, Region I, USNRC E. M. DiPaolo, USNRC Senior Resident Inspector, LGS P. Bamford, Project Manager [LGS] USNRC}}

Latest revision as of 12:29, 14 November 2019

Relief Request RR-36 Associated with the Second Inservice Inspection (Lsi) Interval
ML082730908
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 09/29/2008
From: Cowan P
Exelon Generation Co, Exelon Nuclear
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML082730908 (2)


Text

Exelon Nuclear www.exeloncorp.com 200 Exelon Way Nuclear Kennett Square, PA 19348 10 CFR 50.55a September 29, 2008 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353

Subject:

Relief Request RR-36 Associated with the Second Inservice Inspection (lSI) Interval

References:

1) Letter from P. B. Cowan (Exelon Generation Company, LLC) to U. S.

Nuclear Regulatory Commission, "Submittal of Relief Requests Associated with the Second Inservice Inspection (lSI) Interval," dated January 28, 2008

2) Letter from P. J. Bamford (U. S. Nuclear Regulatory Commission) to C. G. Pardee (Exelon Generation Company, LLC), "Limerick Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding Relief Requests Associated with the Second Inservice Inspection Interval," dated August 8,2008
3) Letter from P. B. Cowan (Exelon Generation Company, LLC) to U. S.

Nuclear Regulatory Commission, "Response to Request for Additional Information Concerning Relief Requests Associated with the Second Inservice Inspection (lSI) Interval," dated September 8,2008 In the Reference 1 letter, in accordance with 10 CFR 50.55a, "Codes and standards," Exelon Generation Company, LLC (EGC), requested relief from the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components. These reliefs apply to the second 10-year interval II inservice inspection program, which concluded on January 31,2007.

Relief Request RR-36 Associated with the Second Inservice Inspection (lSI) Interval September 29, 2008 Page 2 Based on further discussions with the NRC, EGC hereby withdraws RR-36. The remainder of the relief requests in the Reference 1 submittal are not affected by this letter.

No commitments are contained in this letter.

Should you have any questions concerning this letter, please contact Tom Loomis at (610) 765-5510.

Respectfully, 9;1)(~

Pamela B. Cowan Director - Licensing & Regulatory Affairs Exelon Generation Company, LLC cc: S. J. Collins, Regional Administrator, Region I, USNRC E. M. DiPaolo, USNRC Senior Resident Inspector, LGS P. Bamford, Project Manager [LGS] USNRC