ML070600317: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML070600317 | | number = ML070600317 | ||
| issue date = 03/01/2007 | | issue date = 03/01/2007 | ||
| title = | | title = Inspection / Activity Plan, 03/01/2007 - 09/30/2008, Report 22 | ||
| author name = | | author name = | ||
| author affiliation = NRC/RGN-II/DRP | | author affiliation = NRC/RGN-II/DRP | ||
Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Brunswick Inspection / Activity Plan 03/01/2007 | {{#Wiki_filter:Page 1 of 2 Brunswick 03/01/2007 10:29:11 Inspection / Activity Plan Report 22 03/01/2007 - 09/30/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RP OCCUPATIONAL BASELINE INSP- WK1 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/05/2007 03/09/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/05/2007 03/09/2007 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/05/2007 03/09/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/05/2007 03/09/2007 Baseline Inspections EB3-ISI - U2 INSERVICE INSPECTION 1 2 IP 7111108G Inservice Inspection Activities - BWR 03/12/2007 03/16/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL OCCUPATIONAL INSP- WK2 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/19/2007 03/23/2007 Baseline Inspections OL PREP - INITIAL EXAM PREP 3 1 V23267 BRUNSWICK/JULY 2007 EXAM AT POWER FACILITIES 06/25/2007 06/29/2007 Not Applicable OL EXAM - INITIAL EXAM 4 1 V23267 BRUNSWICK/JULY 2007 EXAM AT POWER FACILITIES 07/16/2007 07/27/2007 Not Applicable EB1-CDBI - COMPONENT DESIGN BASES INSPECTION 7 1, 2 IP 7111121 Component Design Bases Inspection 10/22/2007 10/26/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 12/10/2007 12/14/2007 Baseline Inspections PSB1-EP - EP INSP 1 1, 2 IP 7111402 Alert and Notification System Testing 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 71151-EP01 Drill/Exercise Performance 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 11/26/2007 11/30/2007 Baseline Inspections EB3-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 01/28/2008 02/01/2008 Baseline Inspections EB3-ISI - UNIT 1 - ISI 1 1 IP 7111108G Inservice Inspection Activities - BWR 03/10/2008 03/14/2008 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE WEEK 1 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/10/2008 03/14/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/10/2008 03/14/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures. | ||
-09/30/2008 | |||
This report shows only on-site and announced inspection procedures. | Page 2 of 2 Brunswick 03/01/2007 10:29:11 Inspection / Activity Plan Report 22 03/01/2007 - 09/30/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RP OCCUPATIONAL BASELINE WEEK 1 2 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 03/10/2008 03/14/2008 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 03/10/2008 03/14/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/10/2008 03/14/2008 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE WEEK 2 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 71151-PR01 RETS/ODCM Radiological Effluent 03/24/2008 03/28/2008 Baseline Inspections EB1-MODS - MODIFICATIONS-10CFR50.59 4 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 04/14/2008 04/18/2008 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 04/14/2008 04/18/2008 Baseline Inspections EB3-ME - MAINTENANCE EFFECTIVENESS 1 1, 2 IP 7111112B Maintenance Effectiveness 05/19/2008 05/23/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. | ||
Brunswick Inspection / Activity Plan 03/01/2007 | |||
-09/30/2008 | |||
This report shows only on-site and announced inspection procedures.}} | This report shows only on-site and announced inspection procedures.}} |
Latest revision as of 10:03, 23 November 2019
ML070600317 | |
Person / Time | |
---|---|
Site: | Brunswick |
Issue date: | 03/01/2007 |
From: | Division Reactor Projects II |
To: | Carolina Power & Light Co |
Shared Package | |
ML070600304 | List: |
References | |
Download: ML070600317 (2) | |
Text
Page 1 of 2 Brunswick 03/01/2007 10:29:11 Inspection / Activity Plan Report 22 03/01/2007 - 09/30/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RP OCCUPATIONAL BASELINE INSP- WK1 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/05/2007 03/09/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/05/2007 03/09/2007 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/05/2007 03/09/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/05/2007 03/09/2007 Baseline Inspections EB3-ISI - U2 INSERVICE INSPECTION 1 2 IP 7111108G Inservice Inspection Activities - BWR 03/12/2007 03/16/2007 Baseline Inspections PSB1-RP - RP OCCUPATIONAL OCCUPATIONAL INSP- WK2 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/19/2007 03/23/2007 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/19/2007 03/23/2007 Baseline Inspections OL PREP - INITIAL EXAM PREP 3 1 V23267 BRUNSWICK/JULY 2007 EXAM AT POWER FACILITIES 06/25/2007 06/29/2007 Not Applicable OL EXAM - INITIAL EXAM 4 1 V23267 BRUNSWICK/JULY 2007 EXAM AT POWER FACILITIES 07/16/2007 07/27/2007 Not Applicable EB1-CDBI - COMPONENT DESIGN BASES INSPECTION 7 1, 2 IP 7111121 Component Design Bases Inspection 10/22/2007 10/26/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 11/05/2007 11/09/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 12/10/2007 12/14/2007 Baseline Inspections PSB1-EP - EP INSP 1 1, 2 IP 7111402 Alert and Notification System Testing 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 71151-EP01 Drill/Exercise Performance 11/26/2007 11/30/2007 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 11/26/2007 11/30/2007 Baseline Inspections EB3-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 01/28/2008 02/01/2008 Baseline Inspections EB3-ISI - UNIT 1 - ISI 1 1 IP 7111108G Inservice Inspection Activities - BWR 03/10/2008 03/14/2008 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE WEEK 1 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/10/2008 03/14/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/10/2008 03/14/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.
Page 2 of 2 Brunswick 03/01/2007 10:29:11 Inspection / Activity Plan Report 22 03/01/2007 - 09/30/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PSB1-RP - RP OCCUPATIONAL BASELINE WEEK 1 2 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 03/10/2008 03/14/2008 Baseline Inspections 1, 2 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 03/10/2008 03/14/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/10/2008 03/14/2008 Baseline Inspections PSB1-RP - RP OCCUPATIONAL BASELINE WEEK 2 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 03/24/2008 03/28/2008 Baseline Inspections 1, 2 IP 71151-PR01 RETS/ODCM Radiological Effluent 03/24/2008 03/28/2008 Baseline Inspections EB1-MODS - MODIFICATIONS-10CFR50.59 4 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 04/14/2008 04/18/2008 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 04/14/2008 04/18/2008 Baseline Inspections EB3-ME - MAINTENANCE EFFECTIVENESS 1 1, 2 IP 7111112B Maintenance Effectiveness 05/19/2008 05/23/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.