|
|
Line 32: |
Line 32: |
| Please contact your Chief Examiner, T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level Reactor Operator (RO) or Senior Reactor | | Please contact your Chief Examiner, T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level Reactor Operator (RO) or Senior Reactor |
|
| |
|
| December 3, 2015 R. Braun Operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. | | December 3, 2015 |
| | |
| | Operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. |
| Sincerely, | | Sincerely, |
|
| |
|
Line 55: |
Line 57: |
| Please contact your Chief Examiner, T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level Reactor Operator (RO) or Senior Reactor | | Please contact your Chief Examiner, T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level Reactor Operator (RO) or Senior Reactor |
|
| |
|
| December 3, 2015 R. Braun Operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. | | December 3, 2015 |
| | |
| | Operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant. |
| Sincerely, | | Sincerely, |
|
| |
|
Similar Documents at Salem |
---|
Category:Letter
MONTHYEARIR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 LR-N24-0038, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities 2024-09-25
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000272/20223012022-04-27027 April 2022 Initial Operator Licensing Examination Report 05000272/2022301 and 05000311/2022301 IR 05000272/20203012020-09-16016 September 2020 Initial Operator Licensing Examination Report 05000272/2020301 and 05000311/2020301 IR 05000311/20193012019-02-14014 February 2019 Initial Operator Licensing Examination Report 05000272 and 05000311/2019301 IR 05000272/20183012018-03-22022 March 2018 Initial Operator Licensing Examination Report 05000272/2018301; 05000311/2018301 IR 05000272/20173012017-03-0707 March 2017 NRC Initial Operator Licensing Examination Report Er 05000272/2017-301; 05000311/2017-301 IR 05000272/20163012016-02-22022 February 2016 Er 05000272/2016301 and 05000311/2016301, 12/14-21/2015, Salem Nuclear Generating Station Units 1 and 2 Initial Operator Licensing Examination Report ML15342A4482015-12-0303 December 2015 Initial Operator Licensing Operating Test and Written Examination Approval - Salem Nuclear Generating Station, Units 1 and 2 IR 05000272/20143012015-01-20020 January 2015 Er 05000272/2014301; 05000311/2014301; 12/08/2014 to 12/19/2014; Salem Nuclear Generating Station Units 1 and 2; Initial Operator Licensing Examination Report IR 05000272/20113012011-12-0202 December 2011 NRC Initial Operator Licensing Examination Report 05000272/2011301; 05000311/2011301 NTD-05-046, Response to NRC Form 536 (RIS 2005-19) Operator Licensing Examination Data2005-10-31031 October 2005 Response to NRC Form 536 (RIS 2005-19) Operator Licensing Examination Data ML0220000482002-07-10010 July 2002 Response to NRC Form 536 (RIS 2002-9) Operator Licensing Examination Data 2022-04-27
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713
Mr. Robert Braun President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P. O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
INITIAL OPERATOR LICENSING OPERATING TEST AND WRITTEN EXAMINATION APPROVAL - SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2
Dear Mr. Braun:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Salem facility.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. E. Parker, Director of Training. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with NUREG-1021, "Operator Licensing Examinations Standards for Power Reactors," Revision 10, on December 21, 2015. The NRC staff will administer the operating tests during the weeks of December 14 and 21, 2015. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (610) 337-5306.
Please contact your Chief Examiner, T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level Reactor Operator (RO) or Senior Reactor
December 3, 2015
Operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely,
/RA/ Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-272, 50-311 License Nos. DPR-70, DPR-75
cc w/encl: Distribution via ListServ
ML15342A448 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRS/OB RI/DRS/OB NAME TFish/TF DEJackson/DEJ DATE 12/01/2015 12/03/2015 UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713
Mr. Robert Braun President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P. O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
INITIAL OPERATOR LICENSING OPERATING TEST AND WRITTEN EXAMINATION APPROVAL - SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2
Dear Mr. Braun:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at the Salem facility.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. E. Parker, Director of Training. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with NUREG-1021, "Operator Licensing Examinations Standards for Power Reactors," Revision 10, on December 21, 2015. The NRC staff will administer the operating tests during the weeks of December 14 and 21, 2015. This examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (610) 337-5306.
Please contact your Chief Examiner, T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level Reactor Operator (RO) or Senior Reactor
December 3, 2015
Operator (SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.
Sincerely,
/RA/ Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-272, 50-311 License Nos. DPR-70, DPR-75
cc w/encl: Distribution via ListServ
ML15342A448 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRS/OB RI/DRS/OB NAME TFish/TF DEJackson/DEJ DATE 12/01/2015 12/03/2015