| number = ML15195A193
| number = ML15195A193
| issue date = 07/13/2015
| issue date = 07/13/2015
| title = 2015/07/13 Indian Point Lr Hearing - (External_Sender) FW: Draft Phone Call Summary - IPEC LRA
| title = Lr Hearing - (External_Sender) FW: Draft Phone Call Summary - IPEC LRA
| author name =  
| author name =  
| author affiliation = - No Known Affiliation
| author affiliation = - No Known Affiliation
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:1 IPRenewal NPEmails From: Louie, Richard [rlouie@entergy.com]
{{#Wiki_filter:IPRenewal NPEmails From:                       Louie, Richard [rlouie@entergy.com]
Sent: Monday, July 13, 2015 6:57 AM To: Wentzel, Michael
Sent:                       Monday, July 13, 2015 6:57 AM To:                         Wentzel, Michael


==Subject:==
==Subject:==
[External_Sender] FW: Draft Phone Call Summary - IPEC LRA Attachments:
[External_Sender] FW: Draft Phone Call Summary - IPEC LRA Attachments:               070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review.docx Importance:                 High Follow Up Flag:             Follow up Due By:                     Tuesday, July 14, 2015 8:00 AM Flag Status:               Flagged
070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review.docx Importance:
: Mike, Please note below, a comment regarding the attached phone call summary.
High Follow Up Flag:
Rich From: TAYLOR, ANDREW C Sent: Monday, July 13, 2015 1:28 AM To: Louie, Richard Cc: Lach, David J
Follow up Due By: Tuesday, July 14, 2015 8:00 AM Flag Status:
FlaggedMike, Please note below, a comment regarding the attached phone call summary.  
 
Rich From: TAYLOR, ANDREW C Sent: Monday, July 13, 2015 1:28 AM To: Louie, Richard Cc: Lach, David J  


==Subject:==
==Subject:==
FW: Draft Phone Call Summary - IPEC LRA Importance:
FW: Draft Phone Call Summary - IPEC LRA Importance: High Rich -
High Rich -
After further review, we have determined that we do have comments on this phone call summary.
After further review, we have determined that we do have comments on this phone call summary.  
We need NRC to specify which statement in LR-ISG-2013-01 indicates that Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42 as claimed in DRAFT- RAI 3.0.3-16 Andy Andrew Taylor, P.E.
 
Acting Manager Entergy Nuclear License Renewal Services 479-858-3531 From: Louie, Richard Sent: Tuesday, July 07, 2015 7:58 AM To: TAYLOR, ANDREW C
We need NRC to specify which statement in LR-ISG-2013-01 indicates that "Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42
" as claimed in DRAFT- RAI 3.0.3-16  
 
Andy Andrew Taylor, P.E.
Acting Manager Entergy Nuclear License Renewal Services 479-858-3531  
 
From: Louie, Richard Sent: Tuesday, July 07, 2015 7:58 AM To: TAYLOR, ANDREW C  


==Subject:==
==Subject:==
FW: Draft Phone Call Summary  
FW: Draft Phone Call Summary
: Andy, 1


Andy, 2Let me know if you have any comments.  
Let me know if you have any comments.
 
Rich From: Wentzel, Michael [mailto:Michael.Wentzel@nrc.gov]
Rich From: Wentzel, Michael [mailto:Michael.Wentzel@nrc.gov
Sent: Tuesday, July 07, 2015 8:42 AM To: Louie, Richard
Sent: Tuesday, July 07, 2015 8:42 AM To: Louie, Richard  


==Subject:==
==Subject:==
Draft Phone Call Summary
Draft Phone Call Summary
: Rich, Attached is a draft of the phone call summary from our phone call last week. Please let me know if you have any comments.
: Rich, Attached is a draft of the phone call summary from our phone call last week. Please let me know if you have any comments.
: Thanks, Mike Michael Wentzel Project Manager NRR/DLR/RPB2 (301) 415-6459 michael.wentzel@nrc.gov
: Thanks, Mike Michael Wentzel Project Manager NRR/DLR/RPB2 (301) 415-6459 michael.wentzel@nrc.gov 2


Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 5225   Mail Envelope Properties   (CB159DC717B797428E92782CE3B5F40B0F16BF9B)
Hearing Identifier:     IndianPointUnits2and3NonPublic_EX Email Number:           5225 Mail Envelope Properties       (CB159DC717B797428E92782CE3B5F40B0F16BF9B)


==Subject:==
==Subject:==
[External_Sender] FW: Draft Phone Call Summary - IPEC LRA Sent Date:   7/13/2015 6:56:51 AM Received Date: 7/13/2015 6:56:56 AM From:   Louie, Richard Created By:   rlouie@entergy.com Recipients:     "Wentzel, Michael" <Michael.Wentzel@nrc.gov>
[External_Sender] FW: Draft Phone Call Summary - IPEC LRA Sent Date:               7/13/2015 6:56:51 AM Received Date:           7/13/2015 6:56:56 AM From:                   Louie, Richard Created By:             rlouie@entergy.com Recipients:
Tracking Status: None  
"Wentzel, Michael" <Michael.Wentzel@nrc.gov>
Tracking Status: None Post Office:            JDCXMETSP003.etrsouth.corp.entergy.com Files                            Size                    Date & Time MESSAGE                          1339                    7/13/2015 6:56:56 AM 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review.docx                  81821 Options Priority:                        High Return Notification:            No Reply Requested:                No Sensitivity:                    Normal Expiration Date:
Recipients Received:            Follow up By 7/14/2015 8:00:00 AM


Post OfficeJDCXMETSP003.etrsouth.corp.entergy.com Files     Size     Date & Time MESSAGE   1339      7/13/2015 6:56:56 AM 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review.docx   81821 
UNITTED STATES  S NUCCLEARREGU    ULATORY CO    OMMISSION WASHINGT TON, D.C. 20555 5-0001 LICENSE  EEEnterggy Nuclear Operations, O              Inc.
FACILITY  Y:    Indian n Point Nucle ear Generating Unit Noss. 2 and 3 SUBJEC  CT:    SUMM MARY OF TELEPHONE          E CONFERE    ENCE CALL HELD ON JULY    J      1, 2015, BETW WEEN THE U.S. U    NUCLE  EAR REGUL    LATORY CO    OMMISSION AND ENTE ERGY NUCL    LEAR OPER    RATIONS, IN    NC. CONCER    RNING THE  E DRAFT REQU UEST FOR ADDITIONA A          AL INFORMA     ATION FOR THE REVIE      EW OF THE INDIAAN POINT NUCLEAR GENERATING              G UNIT NOS  S. 2 AND 3, LICENSE RENE EWAL APPL    LICATION, SET S     2015-02 2 (TAC NOS  S. MD5407 ANDA    MD540  08)
The U.S.. Nuclear Re egulatory Co ommission (N  NRC) staff and represen   ntatives of Enntergy Nucleear Operations, Inc., (Enntergy)held a telephone conference call on July 1, 2015,to discuss d        and clarify the e NRC staffs request foor additional information (RAI) conce    erning the Indian Point Nuclear Generating G          Unit U Nos. 2 and a 3 licensse renewal applicationsa      afety review.
Enclosurre 1 providess a listing of the participaants and Enclosure 2 co  ontains a listing of the RAAIs discusse ed with Enterrgy, includingg a brief desscription of th he status.
Entergy had h an oppo  ortunity to coomment on this t    summaryy.
Michael We  entzel, Project Manager Projects Braanch 2 Division of License L        Rennewal Office of Nuuclear Reacttor Regulatioon Docket Nos.
N   50-247 and 50-286 Enclosurre:
As stated d cc w/enccl: Listserv


Options  Priority:    High  Return Notification:    No  Reply Requested:    No  Sensitivity:    Normal  Expiration Date:      Recipients Received:  Follow up By 7/14/2015 8:00:00 AM 
                                    *concurrence via e-mail OFFICE     LA:DLR             PM:RPB2:DLR         BC:RPB1:DLR     PM:RPB2:DLR NAME                           MWentzel           YDiaz           MWentzel DATE
 
LICENS E FACILIT Y SUBJE C The U.S.Operatio clarify th e Nuclear G Enclosu rdiscuss e Entergy h 
 
Docket N Enclosu r A s state d cc w/en c EE: Enter g Y: India n CT: SUM M BET W ENT E REQ U INDI A REN E. Nuclear R e ns, Inc., (E n e NRC staff
'G enerating U re 1 provide s e d with Ente r had an opp o Nos. 50-247 re: d cl:  Listserv NU C gy Nuclear O n Point Nucl e MARY OF T WEEN THE U ERGY NUC L UEST FOR A AN POINT N EWAL APP L egulatory C o n tergy)held as request f o U nit Nos. 2 a s a listing of r gy, includin g o rtunity to c o and 50-286 UNI T CLEARREG UWASHING T O perations, e ar GeneratELEPHON E U.S. NUCL E LEAR OPE R ADDITION AUCLEAR G LICATION, S o mmission (N a telephone or additional a nd 3 licen s the particip a g a brief de s o mment on t TED STATE S ULATORY C O TON, D.C. 2055 5  Inc. ing Unit No s E CONFER E EAR REGU L R ATIONS, I N AL INFORM AENERATIN G SET 2015-0 2 N RC) staff aconference information se renewal a ants and En scription of t h t his summar y Michael W e Projects Br a Division of L Office of N u S O MMISSION 5-0001 s. 2 and 3 ENCE CALL LATORY C O NC. CONCE R A TION FOR G UNIT NO S 2 (TAC NO Snd represe ncall on July (RAI) conc e pplications aclosure 2 c o he status.
: y. e ntzel, Proje anch 2  L icense Re n u clear Reac tHELD ON J OMMISSION RNING TH E THE REVI E S. 2 AND 3, S. MD5407 A n tatives of E n 1, 2015,to d erning the In afety review.
ontains a list ct Manager newal t or Regulati o J ULY 1, 201AND E DRAFT EW OF THE LICENSE A ND MD54 0 n tergy Nucl e discuss and dian Point ing of the R A o n 5, 0 8) e ar A Is 
 
*concurrence via e-mail OFFICE LA:DLR PM:RPB2:DLR BC:RPB1:DLR PM:RPB2:DLR NAME MWentzel YDiaz MWentzel DATE    


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC. CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION, SET 2015-02 (TAC NOS. MD5407 AND MD5408)  
OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC. CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION, SET 2015-02 (TAC NOS. MD5407 AND MD5408)
 
DISTRIBUTION:
DISTRIBUTION
HARD COPY:
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource  
DLR RF E-MAIL:
 
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsOgcMailCenter Resource MWentzel              JWeil, OCA BFu                  MGray, RI WHolsten              ABurritt, RI YDiaz                DonaldJackson, RI DMorey                MModes, RI DPickett              NSheehan, RI OPA STurk, OGC            DScrenci, RI OPA BMizuno, OGC          DTifft, RI DRoth, OGC            NMcNamara, RI BHarris, OGC          GNewman, RI SBurnell, OPA        JSStewart, RI DMcIntyre, OPA        BPinson, RI
RidsNrrDlrRpb1 Resource  
 
RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource  


RidsNrrDlrRapb Resource
TELEPHONE CONFERENCE CALL INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JULY 1, 2015 PARTICIPANTS:                            AFFILIATIONS:
Bart Fu                                  U.S. Nuclear Regulatory Commission (NRC)
Bill Holsten                            NRC Michael Wentzel                          NRC Stephen Eric Clair                      Entergy Nuclear Operations, Inc. (Entergy)
Dave Lach                                Entergy Rich Louie                              Entergy Andy Taylor                              Entergy Dave Wootten                            Entergy ENCLOSURE 1


RidsNrrDlrRerb Resource
TELEPHONE CONFERENCE CALL CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION (RAI), SET 2015-02 RELATED TO INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 (IP2 and IP3)
 
LICENSE RENEWAL APPLICATION DOCKET NOS. 50-247 AND 50-286 REGARDING LR-ISG-2013-01 JULY 1, 2015 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Operations, Inc., (Entergy) held a telephone conference call on July 1, 2015, to discuss and clarify the following requests for additional information (RAIs) concerning the license renewal application safety review.
RidsNrrDlrRsrg Resource
RAI 3.0.3-16
 
RidsOgcMailCenter Resource ------------- MWentzel JWeil, OCA BFu MGray, RI WHolsten ABurritt, RI YDiaz DonaldJackson, RI DMorey MModes, RI DPickett NSheehan, RI OPA STurk, OGC DScrenci, RI OPA BMizuno, OGC DTifft, RI DRoth, OGC NMcNamara, RI BHarris, OGC GNewman, RI SBurnell, OPA JSStewart, RI DMcIntyre, OPA BPinson, RI
 
ENCLOSURE 1 TELEPHONE CONFERENCE CALL INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JULY 1, 2015
 
PARTICIPANTS
: A FFILIATIONS
:Bart Fu U.S. Nuclear Re g ulator y Commission (NRC)Bill Holsten NRCMichael Wentzel NRC
 
Ste p hen Eric Clai r Enter gy Nuclear O p erations, Inc.
(Enter gy)Dave Lach Enter gyRich Louie Enter gy A nd y Ta y lo r Enter gyDave Wootten Enter gy ENCLOSURE 2 TELEPHONE CONFERENCE CALL CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION (RAI), SET 2015-02 RELATED TO INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 (IP2 and IP3)
LICENSE RENEWAL APPLICATION DOCKET NOS. 50-247 AND 50-286 REGARDING LR-ISG-2013-01 JULY 1, 2015 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Operations, Inc., (Entergy) held a telephone conference call on July 1, 2015, to discuss and clarify the following requests for additional information (RAIs) concerning the license renewal application safety review.  
 
RAI 3.0.3-16  


===Background===
===Background===
 
As amended by letter dated March 10, 2015, LRA Table 3.3.2-19-43-IP3, Pressurizer System, states that loss of coating integrity is managed for metal components with internal coating in a treated borated water > 140&deg;F environment by the Coating Integrity Program.
As amended by letter dated March 10, 2015, LRA Table 3.3.2-19-43-IP3, "Pressurizer System," states that loss of coating integrity is managed for metal components with internal coating in a "treated borated water > 140&deg;F" environment by the Coating Integrity Program.  
Issue Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42, Aging Management of Loss of Coating or Lining Integrity for Internal Coatings/Linings on In-Scope Piping, Piping Components, Heat Exchangers, and Tanks. The changes to the LRA do not state the specific coating material used in systems with temperatures exceeding 140&deg;F. Therefore, the staff lacks sufficient information to conclude that the recommendations in AMP XI.M42 (e.g., inspection intervals, acceptance criteria) are sufficient for the materials exposed to temperatures greater than 140&deg;F.
 
Issue Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42, "Aging Management of Loss of Coating or Lining Integrity for Internal Coatings/Linings on In-Scope Piping, Piping Components, Heat Exchangers, and Tanks.The changes to the LRA do not state the specific coating material used in systems with temperatures exceeding 140&deg;F. Therefore, the staff lacks sufficient information to conclude that the recommendations in AMP XI.M42 (e.g., inspection intervals, acceptance criteria) are sufficient for the materials exposed to temperatures greater than 140&deg;F.  
 
Request State the coating materials exposed to temperatures greater than 140&deg;F. Provide the basis for concluding that loss of coating integrity is adequately managed in the subject environment.
Request State the coating materials exposed to temperatures greater than 140&deg;F. Provide the basis for concluding that loss of coating integrity is adequately managed in the subject environment.
Discussion
Discussion: Entergy requested clarification as to what information the staff was requesting.
: Entergy requested clarification as to what information the staff was requesting. The staff stated that AMP XI.M42 does not include any elevated temperature environments. As such, the staff needs to know the coating type to ensure that the condition monitoring recommendations of AMP XI.M42 are appropriate.
The staff stated that AMP XI.M42 does not include any elevated temperature environments. As such, the staff needs to know the coating type to ensure that the condition monitoring recommendations of AMP XI.M42 are appropriate.
RAI 3.0.3-17  
RAI 3.0.3-17


===Background===
===Background===
As amended by letter dated March 10, 2015, LRA Sections A.2.1.42, A.3.1.42, and B.1.43, Coating Integrity, state that the Coating Integrity Program will be implemented by December 31, 2024. In addition, Commitment 8, as revised, states that LRA Sections A.2.1.13, A.3.1.13 and B.1.14, Fire Water System, will be implemented by December 31, 2019.
ENCLOSURE 2


As amended by letter dated March 10, 2015, LRA Sections A.2.1.42, A.3.1.42, and B.1.43, "Coating Integrity," state that the Coating Integrity Program will be implemented by December 31, 2024. In addition, Commitment 8, as revised, states that LRA Sections A.2.1.13, A.3.1.13 and B.1.14, "Fire Water System,"
Issue The implementation schedule for LRA Section B.1.43 ranges up to nine years, from 2015 to 2024. In addition, implementation of Commitment 8, as revised, ranges from 2015 to 2019.
will be implemented by December 31, 2019.
Issue The implementation schedule for LRA Section B.1.43 ranges up to nine years, from 2015 to 2024. In addition, implementation of Commitment 8, as revised, ranges from 2015 to 2019.
SRP-LR Table 3.0-1 for AMP XI.M42 states that the first inspections of internal coatings should be completed no later than the last refueling outage prior to the period of extended operation.
SRP-LR Table 3.0-1 for AMP XI.M42 states that the first inspections of internal coatings should be completed no later than the last refueling outage prior to the period of extended operation.
The staff recognizes that Indian Point Unit 2 has entered timely renewal and Indian Point Unit 3 may shortly enter timely renewal. As such, it does not appear that the inspection section schedule recommended in Table 3.0-1 will be met. Further, it is not clear to the staff how loss of coating integrity will be managed in the time frame prior to the programs being implemented.  
The staff recognizes that Indian Point Unit 2 has entered timely renewal and Indian Point Unit 3 may shortly enter timely renewal. As such, it does not appear that the inspection section schedule recommended in Table 3.0-1 will be met. Further, it is not clear to the staff how loss of coating integrity will be managed in the time frame prior to the programs being implemented.
 
Request State how loss of coating integrity will be managed between now and the proposed implementation dates and the basis for concluding that coating integrity will be adequately managed in this time period.
Request State how loss of coating integrity will be managed between now and the proposed implementation dates and the basis for concluding that coating integrity will be adequately managed in this time period.  
Discussion: Entergy stated that they understood what information the NRC staff was requesting.
 
RAI 3.0.3-18
Discussion
: Entergy stated that they understood what information the NRC staff was requesting.
RAI 3.0.3-18  


===Background===
===Background===
As amended by letter dated March 10, 2015, LRA Section B.1.14, "Fire Water System," provides an enhancement to the "corrective actions" program element associated with returning degraded coatings (i.e., peeling, delaminated, or blistered) coatings to service without repair, replacement or removal. No exceptions related to conducting adhesion testing are stated in LRA Section B.1.43, "Coating Integrity."
As amended by letter dated March 10, 2015, LRA Section B.1.14, Fire Water System, provides an enhancement to the corrective actions program element associated with returning degraded coatings (i.e., peeling, delaminated, or blistered) coatings to service without repair, replacement or removal. No exceptions related to conducting adhesion testing are stated in LRA Section B.1.43, Coating Integrity.
Issue GALL Report AMP XI.M42, element 7, "corrective actions," recommends that the coatings/linings for in-scope components that do not meet acceptance criteria are repaired, replaced, or removed. GALL Report AMP XI.M42 allows an alternative, which recommends, among other things, that adhesion testing be performed before returning degraded (i.e., peeling, delaminated, or blistered) coatings to service. For the alternative for returning a coating exhibiting peeling and delamination to service without repair, the Fire Water System program does not include adhesion testing as part of the alternative. In addition, the enhancement states that for coatings exhibiting blistering, "light tapping" of the coating will be performed to determine the extent of blistering. AMP XI.M42 only recommends the use of "light tapping" when it is physically impossible to perform adhesion testing.  
Issue GALL Report AMP XI.M42, element 7, corrective actions, recommends that the coatings/linings for in-scope components that do not meet acceptance criteria are repaired, replaced, or removed. GALL Report AMP XI.M42 allows an alternative, which recommends, among other things, that adhesion testing be performed before returning degraded (i.e., peeling, delaminated, or blistered) coatings to service. For the alternative for returning a coating exhibiting peeling and delamination to service without repair, the Fire Water System program does not include adhesion testing as part of the alternative. In addition, the enhancement states that for coatings exhibiting blistering, light tapping of the coating will be performed to determine the extent of blistering. AMP XI.M42 only recommends the use of light tapping when it is physically impossible to perform adhesion testing.
 
LRA Section B.1.14 did not state an exception to adhesion testing even though the proposed changes to the Fire Water System program were not consistent with GALL Report AMP XI.M42.
LRA Section B.1.14 did not state an exception to adhesion testing even though the proposed changes to the Fire Water System program were not consistent with GALL Report AMP XI.M42.
LRA Section B.1.43 does not state an exception to adhesion testing. It is not clear to the staff whether adhesion testing will be conducted prior to returning degraded coatings/linings within the scope of the Coating Integrity Program to service.  
LRA Section B.1.43 does not state an exception to adhesion testing. It is not clear to the staff whether adhesion testing will be conducted prior to returning degraded coatings/linings within the scope of the Coating Integrity Program to service.
 
Request
Request
: 1. State whether the Coating Integrity Program will include adhesion testing prior to returning degraded coatings/linings to service. 2. If the Coating Integrity Program does not include adhesion testing for returning degraded coatings/linings to service, explain why adhesion testing is not needed as part of the alternative for returning degraded coatings to service for in-scope fire water system  
: 1. State whether the Coating Integrity Program will include adhesion testing prior to returning degraded coatings/linings to service.
 
: 2. If the Coating Integrity Program does not include adhesion testing for returning degraded coatings/linings to service, explain why adhesion testing is not needed as part of the alternative for returning degraded coatings to service for in-scope fire water system components.
components.
Discussion: Entergy stated that it intends to perform adhesion testing as recommended in AMP XI.M42. As such, no exceptions were stated related to adhesion testing. As such, the staff agreed to delete this RAI and would document the use of adhesion testing, as stated by the applicant, as appropriate.}}
Discussion
: Entergy stated that it intends to perform adhesion testing as recommended in AMP XI.M42. As such, no exceptions were stated related to adhesion testing. As such, the staff agreed to delete this RAI and would document the use of adhesion testing, as stated by the applicant, as appropriate.}}

Latest revision as of 10:33, 5 February 2020

Lr Hearing - (External_Sender) FW: Draft Phone Call Summary - IPEC LRA
ML15195A193
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 07/13/2015
From:
- No Known Affiliation
To:
Division of License Renewal
References
Download: ML15195A193 (10)


Text

IPRenewal NPEmails From: Louie, Richard [rlouie@entergy.com]

Sent: Monday, July 13, 2015 6:57 AM To: Wentzel, Michael

Subject:

[External_Sender] FW: Draft Phone Call Summary - IPEC LRA Attachments: 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review.docx Importance: High Follow Up Flag: Follow up Due By: Tuesday, July 14, 2015 8:00 AM Flag Status: Flagged

Mike, Please note below, a comment regarding the attached phone call summary.

Rich From: TAYLOR, ANDREW C Sent: Monday, July 13, 2015 1:28 AM To: Louie, Richard Cc: Lach, David J

Subject:

FW: Draft Phone Call Summary - IPEC LRA Importance: High Rich -

After further review, we have determined that we do have comments on this phone call summary.

We need NRC to specify which statement in LR-ISG-2013-01 indicates that Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42 as claimed in DRAFT- RAI 3.0.3-16 Andy Andrew Taylor, P.E.

Acting Manager Entergy Nuclear License Renewal Services 479-858-3531 From: Louie, Richard Sent: Tuesday, July 07, 2015 7:58 AM To: TAYLOR, ANDREW C

Subject:

FW: Draft Phone Call Summary

Andy, 1

Let me know if you have any comments.

Rich From: Wentzel, Michael [1]

Sent: Tuesday, July 07, 2015 8:42 AM To: Louie, Richard

Subject:

Draft Phone Call Summary

Rich, Attached is a draft of the phone call summary from our phone call last week. Please let me know if you have any comments.
Thanks, Mike Michael Wentzel Project Manager NRR/DLR/RPB2 (301) 415-6459 michael.wentzel@nrc.gov 2

Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 5225 Mail Envelope Properties (CB159DC717B797428E92782CE3B5F40B0F16BF9B)

Subject:

[External_Sender] FW: Draft Phone Call Summary - IPEC LRA Sent Date: 7/13/2015 6:56:51 AM Received Date: 7/13/2015 6:56:56 AM From: Louie, Richard Created By: rlouie@entergy.com Recipients:

"Wentzel, Michael" <Michael.Wentzel@nrc.gov>

Tracking Status: None Post Office: JDCXMETSP003.etrsouth.corp.entergy.com Files Size Date & Time MESSAGE 1339 7/13/2015 6:56:56 AM 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review.docx 81821 Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: Follow up By 7/14/2015 8:00:00 AM

UNITTED STATES S NUCCLEARREGU ULATORY CO OMMISSION WASHINGT TON, D.C. 20555 5-0001 LICENSE EE: Enterggy Nuclear Operations, O Inc.

FACILITY Y: Indian n Point Nucle ear Generating Unit Noss. 2 and 3 SUBJEC CT: SUMM MARY OF TELEPHONE E CONFERE ENCE CALL HELD ON JULY J 1, 2015, BETW WEEN THE U.S. U NUCLE EAR REGUL LATORY CO OMMISSION AND ENTE ERGY NUCL LEAR OPER RATIONS, IN NC. CONCER RNING THE E DRAFT REQU UEST FOR ADDITIONA A AL INFORMA ATION FOR THE REVIE EW OF THE INDIAAN POINT NUCLEAR GENERATING G UNIT NOS S. 2 AND 3, LICENSE RENE EWAL APPL LICATION, SET S 2015-02 2 (TAC NOS S. MD5407 ANDA MD540 08)

The U.S.. Nuclear Re egulatory Co ommission (N NRC) staff and represen ntatives of Enntergy Nucleear Operations, Inc., (Enntergy)held a telephone conference call on July 1, 2015,to discuss d and clarify the e NRC staffs request foor additional information (RAI) conce erning the Indian Point Nuclear Generating G Unit U Nos. 2 and a 3 licensse renewal applicationsa afety review.

Enclosurre 1 providess a listing of the participaants and Enclosure 2 co ontains a listing of the RAAIs discusse ed with Enterrgy, includingg a brief desscription of th he status.

Entergy had h an oppo ortunity to coomment on this t summaryy.

Michael We entzel, Project Manager Projects Braanch 2 Division of License L Rennewal Office of Nuuclear Reacttor Regulatioon Docket Nos.

N 50-247 and 50-286 Enclosurre:

As stated d cc w/enccl: Listserv

  • concurrence via e-mail OFFICE LA:DLR PM:RPB2:DLR BC:RPB1:DLR PM:RPB2:DLR NAME MWentzel YDiaz MWentzel DATE

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON JULY 1, 2015, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC. CONCERNING THE DRAFT REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION, SET 2015-02 (TAC NOS. MD5407 AND MD5408)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRsrg Resource RidsOgcMailCenter Resource MWentzel JWeil, OCA BFu MGray, RI WHolsten ABurritt, RI YDiaz DonaldJackson, RI DMorey MModes, RI DPickett NSheehan, RI OPA STurk, OGC DScrenci, RI OPA BMizuno, OGC DTifft, RI DRoth, OGC NMcNamara, RI BHarris, OGC GNewman, RI SBurnell, OPA JSStewart, RI DMcIntyre, OPA BPinson, RI

TELEPHONE CONFERENCE CALL INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JULY 1, 2015 PARTICIPANTS: AFFILIATIONS:

Bart Fu U.S. Nuclear Regulatory Commission (NRC)

Bill Holsten NRC Michael Wentzel NRC Stephen Eric Clair Entergy Nuclear Operations, Inc. (Entergy)

Dave Lach Entergy Rich Louie Entergy Andy Taylor Entergy Dave Wootten Entergy ENCLOSURE 1

TELEPHONE CONFERENCE CALL CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION (RAI), SET 2015-02 RELATED TO INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 (IP2 and IP3)

LICENSE RENEWAL APPLICATION DOCKET NOS. 50-247 AND 50-286 REGARDING LR-ISG-2013-01 JULY 1, 2015 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Operations, Inc., (Entergy) held a telephone conference call on July 1, 2015, to discuss and clarify the following requests for additional information (RAIs) concerning the license renewal application safety review.

RAI 3.0.3-16

Background

As amended by letter dated March 10, 2015, LRA Table 3.3.2-19-43-IP3, Pressurizer System, states that loss of coating integrity is managed for metal components with internal coating in a treated borated water > 140°F environment by the Coating Integrity Program.

Issue Environments with high temperatures are not evaluated to be bounding within the assumptions of GALL AMP XI.M42, Aging Management of Loss of Coating or Lining Integrity for Internal Coatings/Linings on In-Scope Piping, Piping Components, Heat Exchangers, and Tanks. The changes to the LRA do not state the specific coating material used in systems with temperatures exceeding 140°F. Therefore, the staff lacks sufficient information to conclude that the recommendations in AMP XI.M42 (e.g., inspection intervals, acceptance criteria) are sufficient for the materials exposed to temperatures greater than 140°F.

Request State the coating materials exposed to temperatures greater than 140°F. Provide the basis for concluding that loss of coating integrity is adequately managed in the subject environment.

Discussion: Entergy requested clarification as to what information the staff was requesting.

The staff stated that AMP XI.M42 does not include any elevated temperature environments. As such, the staff needs to know the coating type to ensure that the condition monitoring recommendations of AMP XI.M42 are appropriate.

RAI 3.0.3-17

Background

As amended by letter dated March 10, 2015, LRA Sections A.2.1.42, A.3.1.42, and B.1.43, Coating Integrity, state that the Coating Integrity Program will be implemented by December 31, 2024. In addition, Commitment 8, as revised, states that LRA Sections A.2.1.13, A.3.1.13 and B.1.14, Fire Water System, will be implemented by December 31, 2019.

ENCLOSURE 2

Issue The implementation schedule for LRA Section B.1.43 ranges up to nine years, from 2015 to 2024. In addition, implementation of Commitment 8, as revised, ranges from 2015 to 2019.

SRP-LR Table 3.0-1 for AMP XI.M42 states that the first inspections of internal coatings should be completed no later than the last refueling outage prior to the period of extended operation.

The staff recognizes that Indian Point Unit 2 has entered timely renewal and Indian Point Unit 3 may shortly enter timely renewal. As such, it does not appear that the inspection section schedule recommended in Table 3.0-1 will be met. Further, it is not clear to the staff how loss of coating integrity will be managed in the time frame prior to the programs being implemented.

Request State how loss of coating integrity will be managed between now and the proposed implementation dates and the basis for concluding that coating integrity will be adequately managed in this time period.

Discussion: Entergy stated that they understood what information the NRC staff was requesting.

RAI 3.0.3-18

Background

As amended by letter dated March 10, 2015, LRA Section B.1.14, Fire Water System, provides an enhancement to the corrective actions program element associated with returning degraded coatings (i.e., peeling, delaminated, or blistered) coatings to service without repair, replacement or removal. No exceptions related to conducting adhesion testing are stated in LRA Section B.1.43, Coating Integrity.

Issue GALL Report AMP XI.M42, element 7, corrective actions, recommends that the coatings/linings for in-scope components that do not meet acceptance criteria are repaired, replaced, or removed. GALL Report AMP XI.M42 allows an alternative, which recommends, among other things, that adhesion testing be performed before returning degraded (i.e., peeling, delaminated, or blistered) coatings to service. For the alternative for returning a coating exhibiting peeling and delamination to service without repair, the Fire Water System program does not include adhesion testing as part of the alternative. In addition, the enhancement states that for coatings exhibiting blistering, light tapping of the coating will be performed to determine the extent of blistering. AMP XI.M42 only recommends the use of light tapping when it is physically impossible to perform adhesion testing.

LRA Section B.1.14 did not state an exception to adhesion testing even though the proposed changes to the Fire Water System program were not consistent with GALL Report AMP XI.M42.

LRA Section B.1.43 does not state an exception to adhesion testing. It is not clear to the staff whether adhesion testing will be conducted prior to returning degraded coatings/linings within the scope of the Coating Integrity Program to service.

Request

1. State whether the Coating Integrity Program will include adhesion testing prior to returning degraded coatings/linings to service.
2. If the Coating Integrity Program does not include adhesion testing for returning degraded coatings/linings to service, explain why adhesion testing is not needed as part of the alternative for returning degraded coatings to service for in-scope fire water system components.

Discussion: Entergy stated that it intends to perform adhesion testing as recommended in AMP XI.M42. As such, no exceptions were stated related to adhesion testing. As such, the staff agreed to delete this RAI and would document the use of adhesion testing, as stated by the applicant, as appropriate.