| number = ML083510662 | | number = ML083510662 | ||
| issue date = 12/16/2008 | | issue date = 12/16/2008 | ||
| title = | | title = Notification of Licensed Operator Initial Examination - 05000369-09-301 and 05000370-09-301 | ||
| author name = Widmann M | | author name = Widmann M | ||
| author affiliation = NRC/RGN-II/DNMS | | author affiliation = NRC/RGN-II/DNMS | ||
| addressee name = Hamilton B | | addressee name = Hamilton B | ||
| addressee affiliation = Duke Energy Carolinas, LLC, Duke Power Co | | addressee affiliation = Duke Energy Carolinas, LLC, Duke Power Co | ||
| docket = 05000369, 05000370 | | docket = 05000369, 05000370 | ||
Line 14: | Line 14: | ||
| page count = 48 | | page count = 48 | ||
}} | }} | ||
See also: [[ | See also: [[see also::IR 05000369/2009301]] | ||
=Text= | =Text= | ||
{{#Wiki_filter:December 16, 2008 | {{#Wiki_filter:UNITED STATES | ||
NUCLEAR REGULATORY COMMISSION | |||
Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC McGuire Nuclear Station 12700 Hagers Ferry Road | REGION II | ||
Huntersville, NC 28078-8985 | SAM NUNN ATLANTA FEDERAL CENTER | ||
61 FORSYTH STREET, SW, SUITE 23T85 | |||
ATLANTA, GEORGIA 30303-8931 | |||
made for the administration of licensing examinations at the McGuire Nuclear Station. The Operating Test is scheduled to be administered during the weeks of May 11, and May 18, 2009. | December 16, 2008 | ||
Mr. Bruce H. Hamilton | |||
1021, "Operator Licensing Examination Standards for Power Reactors." | Vice President | ||
Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC | |||
To meet the above schedule, it will be necessary for your staff to furnish the examination outlines by February 25, 2009. | McGuire Nuclear Station | ||
outlines, examinations, and tests before they are submitted to the NRC for review and approval. | 12700 Hagers Ferry Road | ||
Huntersville, NC 28078-8985 | |||
receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled | SUBJECT: MCGUIRE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR | ||
INITIAL EXAMINATION - 05000369/2009301 AND 05000370/2009301 | |||
Dear Mr. Hamilton: | |||
In a telephone conversation on December 10, 2008, between Mr. Steve Helms, Supervisor | |||
Operator Training, and Mr. Gerard W. Laska, Senior Operations Examiner, arrangements were | |||
made for the administration of licensing examinations at the McGuire Nuclear Station. The | |||
Operating Test is scheduled to be administered during the weeks of May 11, and May 18, 2009. | |||
The written examination is scheduled to be administered the week of May 18, 2009. The on-site | |||
preparatory week is scheduled for the week of April 20, 2009. | |||
As agreed during the telephone conversation, your staff of the will prepare the operating test | |||
and the written examinations based on the guidelines in Revision 9, Supplement 1 of NUREG- | |||
1021, "Operator Licensing Examination Standards for Power Reactors." The U. S. Nuclear | |||
Regulatory Commission (NRC) regional office will discuss with your staff any changes that | |||
might be necessary before the examinations are administered. Your staff has also agreed to | |||
make copies of all examination materials that are necessary for administering the examination. | |||
To meet the above schedule, it will be necessary for your staff to furnish the examination | |||
outlines by February 25, 2009. The operating tests, written examinations, and the supporting | |||
reference materials identified in Attachment 2 of ES-201 will be due by March 27, 2009. The | |||
written examination outline was previously provided to your staff on October 08, 2008. Pursuant | |||
to 10 CFR 55.40(b) (3), an authorized representative of the facility licensee shall approve the | |||
outlines, examinations, and tests before they are submitted to the NRC for review and approval. | |||
All materials shall be complete and ready-to-use. | |||
We request that any personal, proprietary, sensitive unclassified, or safeguards information in | |||
your response be contained in a separate enclosure and appropriately marked. Any delay in | |||
receiving the required examination and reference materials, or the submittal of inadequate or | |||
incomplete materials, may cause the examinations to be rescheduled. | |||
DPC 2 | |||
average 500 hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. | In order to conduct the requested written examinations and operating test, it will be necessary | ||
Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503. | for your staff to provide adequate space and accommodations in accordance with ES-402, and | ||
to make the simulation facility available on the dates noted above. In accordance with ES-302, | |||
of information unless it displays a currently valid OMB control number. | your staff should retain the original simulator performance data (e.g., system pressures, | ||
temperatures, and levels) generated during the dynamic operating tests until the examination | |||
is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html | results are final. | ||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in | |||
effect while the written examinations and operating tests are being administered. | |||
To permit timely NRC review and evaluation, your staff should submit preliminary reactor | |||
operator and senior reactor operator license applications (Office of Management and Budget | |||
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), | |||
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first | |||
examination date. If the applications are not received at least 30 days before the examination | |||
date, a postponement may be necessary. Signed applications certifying that all training has | |||
been completed should be submitted at least 14 days before the first examination date. | |||
This letter contains information collections that are subject to the Paperwork Reduction Act of | |||
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of | |||
Management and Budget, approval number Part 55 (3150-0018), which expires on | |||
June 30, 2009. The public reporting burden for this collection of information is estimated to | |||
average 500 hours per response, including the time for reviewing instructions, gathering and | |||
maintaining the data needed, writing the examinations, and completing and reviewing the | |||
collection of information. Send comments on any aspect of this collection of information, | |||
including suggestions for reducing the burden, to the Information and Records Management | |||
Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by | |||
Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and | |||
Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, | |||
DC 20503. | |||
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection | |||
of information unless it displays a currently valid OMB control number. | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be | |||
available electronically for public inspection in the NRC Public Document Room or from the | |||
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS | |||
is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html | |||
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
DPC 3 | |||
Thank you for your cooperation in this matter. Mr. Helms has been advised of the policies and | |||
Internet | guidelines referenced in this letter. If you have any questions regarding the NRC's examination | ||
procedures and guidelines, please contact Mr. Gerry Laska at (404) 562-4626, (Internet E-mail: | |||
of | gwl1@nrc.gov), or me at (404) 562-4550, (Internet E-mail: mtw@nrc.gov). | ||
Sincerely, | |||
/RA/ | |||
Malcolm T. Widmann, Chief | |||
Operations Branch | |||
Division of Reactor Safety | |||
Docket Nos.: 50-369, 50-370 | |||
License Nos.: NPF-9, NPF-17 | |||
(cc: w/encl - See Page 4) | |||
December 16, 2008 | |||
Mr. Bruce H. Hamilton | |||
Vice President | |||
Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC | |||
McGuire Nuclear Station | |||
12700 Hagers Ferry Road | |||
Huntersville, NC 28078-8985 | |||
SUBJECT: MCGUIRE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR | |||
INITIAL EXAMINATION - 05000369/2009301 AND 05000370/2009301 | |||
Dear Mr. Hamilton: | |||
In a telephone conversation on December 10, 2008, between Mr. Steve Helms, Supervisor | |||
Operator Training, and Mr. Gerard W. Laska, Senior Operations Examiner, arrangements were | |||
made for the administration of licensing examinations at the McGuire Nuclear Station. The | |||
Operating Test is scheduled to be administered during the weeks of May 11, and May 18, 2009. | |||
The written examination is scheduled to be administered the week of May 18, 2009. The on-site | |||
preparatory week is scheduled for the week of April 20, 2009. | |||
As agreed during the telephone conversation, your staff of the will prepare the operating test | |||
and the written examinations based on the guidelines in Revision 9, Supplement 1 of NUREG- | |||
1021, "Operator Licensing Examination Standards for Power Reactors." The U. S. Nuclear | |||
Regulatory Commission (NRC) regional office will discuss with your staff any changes that | |||
might be necessary before the examinations are administered. Your staff has also agreed to | |||
make copies of all examination materials that are necessary for administering the examination. | |||
To meet the above schedule, it will be necessary for your staff to furnish the examination | |||
outlines by February 25, 2009. The operating tests, written examinations, and the supporting | |||
reference materials identified in Attachment 2 of ES-201 will be due by March 27, 2009. The | |||
written examination outline was previously provided to your staff on October 08, 2008. Pursuant | |||
to 10 CFR 55.40(b) (3), an authorized representative of the facility licensee shall approve the | |||
outlines, examinations, and tests before they are submitted to the NRC for review and approval. | |||
All materials shall be complete and ready-to-use. | |||
We request that any personal, proprietary, sensitive unclassified, or safeguards information in | |||
your response be contained in a separate enclosure and appropriately marked. Any delay in | |||
receiving the required examination and reference materials, or the submittal of inadequate or | |||
incomplete materials, may cause the examinations to be rescheduled. | |||
DPC 2 | |||
In order to conduct the requested written examinations and operating test, it will be necessary | |||
for your staff to provide adequate space and accommodations in accordance with ES-402, and | |||
to make the simulation facility available on the dates noted above. In accordance with ES-302, | |||
your staff should retain the original simulator performance data (e.g., system pressures, | |||
temperatures, and levels) generated during the dynamic operating tests until the examination | |||
results are final. | |||
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in | |||
effect while the written examinations and operating tests are being administered. | |||
To permit timely NRC review and evaluation, your staff should submit preliminary reactor | |||
operator and senior reactor operator license applications (Office of Management and Budget | |||
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), | |||
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first | |||
examination date. If the applications are not received at least 30 days before the examination | |||
date, a postponement may be necessary. Signed applications certifying that all training has | |||
been completed should be submitted at least 14 days before the first examination date. | |||
This letter contains information collections that are subject to the Paperwork Reduction Act of | |||
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of | |||
Management and Budget, approval number Part 55 (3150-0018), which expires on | |||
June 30, 2009. The public reporting burden for this collection of information is estimated to | |||
average 500 hours per response, including the time for reviewing instructions, gathering and | |||
maintaining the data needed, writing the examinations, and completing and reviewing the | |||
collection of information. Send comments on any aspect of this collection of information, | |||
including suggestions for reducing the burden, to the Information and Records Management | |||
Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by | |||
Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and | |||
Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, | |||
DC 20503. | |||
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection | |||
of information unless it displays a currently valid OMB control number. | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be | |||
available electronically for public inspection in the NRC Public Document Room or from the | |||
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS | |||
is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html | |||
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
_________________________ XG SUNSI REVIEW COMPLETE | |||
OFFICE RII:DRS RII:DRS RII:DRP | |||
SIGNATURE /RA/ /RA/ /RA/ | |||
NAME Gerard Laska Malcolm Widmann JMoorman | |||
DATE 12/16/2008 12/16/2008 12/16/2008 12/ /2008 12/ /2008 12/ /2008 12/ /2008 | |||
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO | |||
DPC 4 | |||
cc w/encl: | |||
Steven D. Capps David A. Repka | |||
720 East Fourth Street Charlotte, NC | Engineering Manager Winston Strawn LLP | ||
Duke Power Company, LLC d/b/a Duke Electronic Mail Distribution | |||
Department of Environmental Health N.C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution | Energy Carolinas, LLC | ||
Electronic Mail Distribution County Manager of Mecklenburg County | |||
Duke Energy Carolinas, LLC Electronic Mail Distribution | 720 East Fourth Street | ||
Scotty L. Bradshaw Charlotte, NC 28202 | |||
William B. McGuire Nuclear Station U.S. NRC 12700 Hagers Ferry Rd Huntersville, NC | Training Manager | ||
Duke Power Company, LLC d/b/a Duke Beverly O. Hall | |||
DPC 5 | Energy Carolinas, LLC Chief, Radiation Protection Section | ||
Electronic Mail Distribution Department of Environmental Health | |||
N.C. Department of Environmental | |||
Kenneth L. Ashe Commerce & Natural Resources | |||
Regulatory Compliance Manager Electronic Mail Distribution | |||
Duke Power Company, LLC d/b/a Duke | |||
Energy Carolinas, LLC Dhiaa M. Jamil | |||
Electronic Mail Distribution Group Executive and Chief Nuclear Officer | |||
Duke Energy Carolinas, LLC | |||
R. L. Gill, Jr. Electronic Mail Distribution | |||
Manager | |||
Nuclear Regulatory Issues & Industry Affairs Senior Resident Inspector | |||
Duke Power Company, LLC d/b/a Duke Duke Energy Corporation | |||
Energy Carolinas, LLC William B. McGuire Nuclear Station | |||
Electronic Mail Distribution U.S. NRC | |||
12700 Hagers Ferry Rd | |||
Lisa F. Vaughn Huntersville, NC 28078 | |||
Associate General Counsel | |||
Duke Energy Corporation | |||
526 South Church Street-EC07H | |||
Charlotte, NC 28202 | |||
Kathryn B. Nolan | |||
Senior Counsel | |||
Duke Energy Corporation | |||
526 South Church Street-EC07H | |||
Charlotte, NC 28202 | |||
DPC 5 | |||
Letter to Bruce H. Hamilton from Malcolm T. Widmann dated December 16, 2008 | |||
SUBJECT: MCGUIRE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR | |||
INITIAL EXAMINATION - 05000369/2009301 AND 05000370/2009301 | |||
Distribution w/encl: | |||
RIDSNRRDIRS | |||
PUBLIC | |||
J. Stang, NRR (PM: CT, MG) | |||
}} | }} |
Latest revision as of 11:23, 14 November 2019
ML083510662 | |
Person / Time | |
---|---|
Site: | Mcguire, McGuire ![]() |
Issue date: | 12/16/2008 |
From: | Widmann M Division of Nuclear Materials Safety II |
To: | Brandi Hamilton Duke Energy Carolinas, Duke Power Co |
References | |
50-369/09-301, 50-370/09-301 | |
Download: ML083510662 (48) | |
See also: IR 05000369/2009301
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
SAM NUNN ATLANTA FEDERAL CENTER
61 FORSYTH STREET, SW, SUITE 23T85
ATLANTA, GEORGIA 30303-8931
December 16, 2008
Mr. Bruce H. Hamilton
Vice President
Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC
McGuire Nuclear Station
12700 Hagers Ferry Road
Huntersville, NC 28078-8985
SUBJECT: MCGUIRE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR
INITIAL EXAMINATION - 05000369/2009301 AND 05000370/2009301
Dear Mr. Hamilton:
In a telephone conversation on December 10, 2008, between Mr. Steve Helms, Supervisor
Operator Training, and Mr. Gerard W. Laska, Senior Operations Examiner, arrangements were
made for the administration of licensing examinations at the McGuire Nuclear Station. The
Operating Test is scheduled to be administered during the weeks of May 11, and May 18, 2009.
The written examination is scheduled to be administered the week of May 18, 2009. The on-site
preparatory week is scheduled for the week of April 20, 2009.
As agreed during the telephone conversation, your staff of the will prepare the operating test
and the written examinations based on the guidelines in Revision 9, Supplement 1 of NUREG-
1021, "Operator Licensing Examination Standards for Power Reactors." The U. S. Nuclear
Regulatory Commission (NRC) regional office will discuss with your staff any changes that
might be necessary before the examinations are administered. Your staff has also agreed to
make copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by February 25, 2009. The operating tests, written examinations, and the supporting
reference materials identified in Attachment 2 of ES-201 will be due by March 27, 2009. The
written examination outline was previously provided to your staff on October 08, 2008. Pursuant
to 10 CFR 55.40(b) (3), an authorized representative of the facility licensee shall approve the
outlines, examinations, and tests before they are submitted to the NRC for review and approval.
All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
DPC 2
In order to conduct the requested written examinations and operating test, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications (Office of Management and Budget
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of
Management and Budget, approval number Part 55 (3150-0018), which expires on
June 30, 2009. The public reporting burden for this collection of information is estimated to
average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and
maintaining the data needed, writing the examinations, and completing and reviewing the
collection of information. Send comments on any aspect of this collection of information,
including suggestions for reducing the burden, to the Information and Records Management
Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by
Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and
Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington,
DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection
of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS
is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
DPC 3
Thank you for your cooperation in this matter. Mr. Helms has been advised of the policies and
guidelines referenced in this letter. If you have any questions regarding the NRC's examination
procedures and guidelines, please contact Mr. Gerry Laska at (404) 562-4626, (Internet E-mail:
gwl1@nrc.gov), or me at (404) 562-4550, (Internet E-mail: mtw@nrc.gov).
Sincerely,
/RA/
Malcolm T. Widmann, Chief
Operations Branch
Division of Reactor Safety
Docket Nos.: 50-369, 50-370
(cc: w/encl - See Page 4)
December 16, 2008
Mr. Bruce H. Hamilton
Vice President
Duke Power Company, LLC d/b/a Duke Energy Carolinas, LLC
McGuire Nuclear Station
12700 Hagers Ferry Road
Huntersville, NC 28078-8985
SUBJECT: MCGUIRE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR
INITIAL EXAMINATION - 05000369/2009301 AND 05000370/2009301
Dear Mr. Hamilton:
In a telephone conversation on December 10, 2008, between Mr. Steve Helms, Supervisor
Operator Training, and Mr. Gerard W. Laska, Senior Operations Examiner, arrangements were
made for the administration of licensing examinations at the McGuire Nuclear Station. The
Operating Test is scheduled to be administered during the weeks of May 11, and May 18, 2009.
The written examination is scheduled to be administered the week of May 18, 2009. The on-site
preparatory week is scheduled for the week of April 20, 2009.
As agreed during the telephone conversation, your staff of the will prepare the operating test
and the written examinations based on the guidelines in Revision 9, Supplement 1 of NUREG-
1021, "Operator Licensing Examination Standards for Power Reactors." The U. S. Nuclear
Regulatory Commission (NRC) regional office will discuss with your staff any changes that
might be necessary before the examinations are administered. Your staff has also agreed to
make copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by February 25, 2009. The operating tests, written examinations, and the supporting
reference materials identified in Attachment 2 of ES-201 will be due by March 27, 2009. The
written examination outline was previously provided to your staff on October 08, 2008. Pursuant
to 10 CFR 55.40(b) (3), an authorized representative of the facility licensee shall approve the
outlines, examinations, and tests before they are submitted to the NRC for review and approval.
All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
DPC 2
In order to conduct the requested written examinations and operating test, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications (Office of Management and Budget
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of
Management and Budget, approval number Part 55 (3150-0018), which expires on
June 30, 2009. The public reporting burden for this collection of information is estimated to
average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and
maintaining the data needed, writing the examinations, and completing and reviewing the
collection of information. Send comments on any aspect of this collection of information,
including suggestions for reducing the burden, to the Information and Records Management
Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by
Internet electronic mail at BJS1@NRC.GOV; and to the Desk Officer, Office of Information and
Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington,
DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection
of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS
is accessible from the NRC Web site at http://www.nrc.gov/readingrm/adams.html
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
_________________________ XG SUNSI REVIEW COMPLETE
OFFICE RII:DRS RII:DRS RII:DRP
SIGNATURE /RA/ /RA/ /RA/
NAME Gerard Laska Malcolm Widmann JMoorman
DATE 12/16/2008 12/16/2008 12/16/2008 12/ /2008 12/ /2008 12/ /2008 12/ /2008
E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO
DPC 4
cc w/encl:
Steven D. Capps David A. Repka
Engineering Manager Winston Strawn LLP
Duke Power Company, LLC d/b/a Duke Electronic Mail Distribution
Energy Carolinas, LLC
Electronic Mail Distribution County Manager of Mecklenburg County
720 East Fourth Street
Scotty L. Bradshaw Charlotte, NC 28202
Training Manager
Duke Power Company, LLC d/b/a Duke Beverly O. Hall
Energy Carolinas, LLC Chief, Radiation Protection Section
Electronic Mail Distribution Department of Environmental Health
N.C. Department of Environmental
Kenneth L. Ashe Commerce & Natural Resources
Regulatory Compliance Manager Electronic Mail Distribution
Duke Power Company, LLC d/b/a Duke
Energy Carolinas, LLC Dhiaa M. Jamil
Electronic Mail Distribution Group Executive and Chief Nuclear Officer
Duke Energy Carolinas, LLC
R. L. Gill, Jr. Electronic Mail Distribution
Manager
Nuclear Regulatory Issues & Industry Affairs Senior Resident Inspector
Duke Power Company, LLC d/b/a Duke Duke Energy Corporation
Energy Carolinas, LLC William B. McGuire Nuclear Station
Electronic Mail Distribution U.S. NRC
12700 Hagers Ferry Rd
Lisa F. Vaughn Huntersville, NC 28078
Associate General Counsel
Duke Energy Corporation
526 South Church Street-EC07H
Charlotte, NC 28202
Kathryn B. Nolan
Senior Counsel
Duke Energy Corporation
526 South Church Street-EC07H
Charlotte, NC 28202
DPC 5
Letter to Bruce H. Hamilton from Malcolm T. Widmann dated December 16, 2008
SUBJECT: MCGUIRE NUCLEAR STATION - NOTIFICATION OF LICENSED OPERATOR
INITIAL EXAMINATION - 05000369/2009301 AND 05000370/2009301
Distribution w/encl:
RIDSNRRDIRS
PUBLIC