| author name = Hammons D
| author name = Hammons D
| author affiliation = US Dept of Homeland Security, US Federal Emergency Mgmt Agency (FEMA)
| author affiliation = US Dept of Homeland Security, US Federal Emergency Mgmt Agency (FEMA)
| addressee name = Cline M M
| addressee name = Cline M
| addressee affiliation = NRC/NSIR, State of VA, Dept of Emergency Management
| addressee affiliation = NRC/NSIR, State of VA, Dept of Emergency Management
| docket = 05000280, 05000281
| docket = 05000280, 05000281
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:1J.S. Department of Homeland Security One Independence Mall, Sixth Floor 615 Chestnut Street Philadelphia.
{{#Wiki_filter:1J.S. Department of Homeland Security One Independence Mall, Sixth Floor 615 Chestnut Street Philadelphia. PA 19106-4404 Mr. Michael M. Cline State Coordinator Virginia Department of Emergency Management 10501 Trade Court Richmond, Virginia 23236-37 13
PA 19106-4404 Mr. Michael M. Cline State Coordinator Virginia Department of Emergency Management 10501 Trade Court Richmond, Virginia 23236-37 13  


==Dear Mr. Cline:==
==Dear Mr. Cline:==


Enclosed is the final report for the Surry Power Station (SPS) Plume Radiological Emergency Preparedness Exercise held on August 4,2009. There were no Deficiencies, one new performance issue (resolved), and three new planning issues identified as a result of the exercise.
Enclosed is the final report for the Surry Power Station (SPS) Plume Radiological Emergency Preparedness Exercise held on August 4,2009.
In addition, there were six prior performance issues successfully resolved through demonstration.
There were no Deficiencies, one new performance issue (resolved), and three new planning issues identified as a result of the exercise. In addition, there were six prior performance issues successfully resolved through demonstration.
Based on the results of the exercise, the offsite radiological emergency response plans and preparedness for the Commonwealth of Virginia and the affected local jurisdictions, site-specific to SPS, are adequate to protect the public health and safety in the event of a radiological emergency at the site. If you have any questions, please contact Darrell Hamrnons at (215) 93 1-5546. Sincerely, Darrell Hamrnons Regional Assistance Committee Chairperson Enclosure}}
Based on the results of the exercise, the offsite radiological emergency response plans and preparedness for the Commonwealth of Virginia and the affected local jurisdictions, site-specific to SPS, are adequate to protect the public health and safety in the event of a radiological emergency at the site.
If you have any questions, please contact Darrell Hamrnons at (215) 93 1-5546.
Sincerely, Darrell Hamrnons Regional Assistance Committee Chairperson Enclosure}}

Latest revision as of 00:00, 14 November 2019

FEMA, Transmittal of Final Report for Surry Plume Radiological Emergency Preparedness Exercise Held August 04, 2009
ML093340040
Person / Time
Site: Surry  Dominion icon.png
Issue date: 11/04/2009
From: Hammons D
US Dept of Homeland Security, Federal Emergency Management Agency
To: Cline M
Office of Nuclear Security and Incident Response, State of VA, Dept of Emergency Management
References
Download: ML093340040 (1)


Text

1J.S. Department of Homeland Security One Independence Mall, Sixth Floor 615 Chestnut Street Philadelphia. PA 19106-4404 Mr. Michael M. Cline State Coordinator Virginia Department of Emergency Management 10501 Trade Court Richmond, Virginia 23236-37 13

Dear Mr. Cline:

Enclosed is the final report for the Surry Power Station (SPS) Plume Radiological Emergency Preparedness Exercise held on August 4,2009.

There were no Deficiencies, one new performance issue (resolved), and three new planning issues identified as a result of the exercise. In addition, there were six prior performance issues successfully resolved through demonstration.

Based on the results of the exercise, the offsite radiological emergency response plans and preparedness for the Commonwealth of Virginia and the affected local jurisdictions, site-specific to SPS, are adequate to protect the public health and safety in the event of a radiological emergency at the site.

If you have any questions, please contact Darrell Hamrnons at (215) 93 1-5546.

Sincerely, Darrell Hamrnons Regional Assistance Committee Chairperson Enclosure